Blair v. United States ex rel. Gregory-Hogan

150 F.2d 676
Court of Appeals for the Eighth Circuit·Decided July 24, 1945·No. Nos. 12871, 12875·Published·Cited by 23 cases

Opinion

RIDDICK, Circuit Judge.

On the first hearing of this case we approved the finding by the trial court of a breach by defendant Blair of his asphalt contract with the plaintiff Gregory-Hogan alleged in paragraph 11 of the complaint. A judgment for damages in favor of Gregory-Hogan resulting from this breach of contract was affirmed after reduction in the amount allowed by the trial court. We reversed the judgment of the lower court in favor of Gregory-Hogan on its claim allowed by the trial court under paragraph 6 of the complaint, in which it alleged liability on the part of defendant Blair for additional expenses incurred by Gregory-Hogan under the so-called speedup agreement between the parties. The contracts referred to are set out with sufficient particularity in our original opinion (8 Cir., 147 F.2d 840) and need not be restated here. In petitions for rehearing both parties assert error in respect to the matters stated.

Defendant Blair contends that, conceding that the evidence was sufficient to establish the breach by him of the asphalt contract, it nevertheless conclusively establishes the fact that the plaintiff Gregory-Hogan sustained no damage as the result of the breach.

The substance of paragraph 11 of the complaint is that the plaintiff was obligated under its asphalt contract to produce approximately 50,000 tons of asphalt for paving within the time specified in the contract; that, in order to comply with this requirement of the contract, it was necessary for plaintiff to rent and ship to the place of performance an asphalt plant capable of producing 500 tons of asphalt a day; that after the execution of the contract and after plaintiff had incurred the expense of installing the asphalt plant capable of doing the work, the defendant, without notice to or the consent of the plaintiff, caused the required amount of asphalt to be reduced from approximately 50,-000 tons to approximately 20,000 tons, with [677]*677the result that the plaintiff did not need and could not economically use the large equipment and installation which the original contract required. As damages for this breach of contract plaintiff sought to recover expenses incurred in shipping the large asphalt plant to the place of performance of the work, in installing and equipping the plant for the production of 50,000 tons of asphalt and in dismantling and returning the plant to the point from which it was shipped. Plaintiff offered evidence tending to show that it owned a smaller plant fully capable of furnishing the reduced quantity of asphalt within 150 days. The smaller plant was located at Fort Smith, Arkansas, very near the place of performance of the contract, whereas the larger plant was brought from Mississippi. Included in plaintiff’s alleged out-of-pocket expense was the rental value of the larger plant, presumably for the time it was not needed. In support of this item of expense, plaintiff offered proof to show the fair rental value of the plant and that it could have been rented to other contractors, if the asphalt contract, as originally executed, had not required its use in its performance.

The majority of the court were of the opinion that the charges for rent, included in the plaintiff’s alleged out-of-pocket expense, could not be allowed under the evidence in this case. We allowed a recovery in favor of the plaintiff on this claim in the sum of $16,981.74, representing plaintiff’s out-of-pocket expense in shipping, installing, and dismantling'an asphalt plant larger than was necessary for the performance of its contract. On reconsideration, we conclude that this recovery is not supported by any evidence in the record.

The so-called asphalt contract was executed on September 20, 1941. Within a very few days after the execution of the contract plaintiff learned that the Government had decided to reduce the amount of asphalt required under the contract by approximately the number of tons of reduction alleged in the complaint. This information came to the plaintiff before September 25, 1941, because on that date plaintiff advised the defendant of its receipt; and, on the contention that the reduction in the amount of asphalt contemplated under the contract would increase the unit cost in the performance of the contract, requested the defendant to ask the Government for an increase in the unit prices allowed on the work. On September 30, 1941, defendant Blair replied to plaintiff’s letter of September 25, 1941, confirming plaintiff’s information concerning the reduction in the amount of asphalt required under the contract and promising to submit to the proper officials of the Government plaintiff’s request for increased unit prices. Defendant’s letter of September 30, 1941, was acknowledged on October 22, 1941. Plaintiff signified its intention of proceeding with the performance of the contract as changed, and expressed confidence that defendant would adequately present to the Government plaintiff’s request for an increase in unit prices for the work under the contract.

There is nothing in the record to show when plaintiff began shipment of the large asphalt plant to the place of performance of the contract. In view of the fact that the plaintiff’s evidence establishes that it received knowledge of the reduction in the amount of asphalt required under the contract almost contemporaneously with its execution, it is hardly reasonable to suppose that the large asphalt plant had been dismantled at its location in Mississippi and shipped to a point near Fort Smith, Arkansas, where the work was to be done, and there assembled, before plaintiff had notice of the fact, if its testimony is to be accepted, that a plant of such capacity would not be required for the work to be done by it.

On January 12, 1942, defendant wrote to plaintiff, saying that he had received from the Government a change order providing for the changes in the original contract which resulted in the reduction of the asphalt required. In this letter defendant stated:

“You were advised sometime ago that the asphalt surfacing in the Motor Park Areas would be omitted, and this Change Order makes the omission a definite fact.

“This information is given to you so that you can plan your equipment arrangements accordingly.”

In view of the preceding correspondence between the parties, plaintiff’s testimony that the letter of January 12, 1942, was the first decisive information that there would be a change in the requirements concerning the amount of asphalt needed in performing the contract, and that up to January 12, 1942, it had to hold itself in readiness to produce 50,000 tons of asphalt, [678]*678does not seem entirely reasonable. But even so, accepting January 12, 1942, as the date of the breach of the asphalt contract, plaintiff’s own evidence shows that it was advised as early as November 4, 1941, that no asphalt work would be done before March 1, 1942. The contract, as originally written, required the work to be finished by March 25, 1942, but the date for completion was later extended to April 12, 1942. Plaintiff did not begin setting up its large asphalt plant until some time in the middle of February, 1942, after the receipt of decisive information, if its testimony is to be accepted, that the plant would not be required. The asphalt work was begun about March 1, 1942, but, although it is admitted that nothing occurred to delay the work, it was not completed until June 3, 1942.

Free access — add to your briefcase to read the full text and ask questions with AI

Blair v. United States ex rel. Gregory-Hogan, 150 F.2d 676 (8th Cir. 1945).

150 F.2d 676 (Blair v. United States ex rel. Gregory-Hogan) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Sonntag v. Shaw
2001 NMSC 015 (New Mexico Supreme Court, 2001)
Camino Real Mobile Home Park Partnership v. Wolfe
891 P.2d 1190 (New Mexico Supreme Court, 1995)
Morriss v. Wynia
603 S.W.2d 482 (Court of Appeals of Arkansas, 1980)
St. Joseph Hospital v. Corbetta Construction Co.
316 N.E.2d 51 (Appellate Court of Illinois, 1974)
A. J. Wolfe Co. v. Baltimore Contractors, Inc.
244 N.E.2d 717 (Massachusetts Supreme Judicial Court, 1969)
City of Salinas v. Souza & McCue Construction Co.
424 P.2d 921 (California Supreme Court, 1967)
United Protective Workers v. Ford Motor Co.
223 F.2d 49 (Seventh Circuit, 1955)
United States ex rel. Commercial Equipment Co. v. Wooten
121 F. Supp. 130 (W.D. Arkansas, 1954)
Boomer v. Abbett
263 P.2d 476 (California Court of Appeal, 1953)
Schlottman v. Pressey Pressey v. Schlottman
195 F.2d 343 (Tenth Circuit, 1952)
Deutsch v. Hoge
94 F. Supp. 33 (N.D. Ohio, 1949)