Birch & Davis International, Inc. v. Warren M. Christopher, Secretary of State

4 F.3d 970, 39 Cont. Cas. Fed. 76,561, 1993 U.S. App. LEXIS 23534, 1993 WL 349700
CourtCourt of Appeals for the Federal Circuit
DecidedSeptember 13, 1993
Docket92-1384
StatusPublished
Cited by32 cases

This text of 4 F.3d 970 (Birch & Davis International, Inc. v. Warren M. Christopher, Secretary of State) is published on Counsel Stack Legal Research, covering Court of Appeals for the Federal Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Birch & Davis International, Inc. v. Warren M. Christopher, Secretary of State, 4 F.3d 970, 39 Cont. Cas. Fed. 76,561, 1993 U.S. App. LEXIS 23534, 1993 WL 349700 (Fed. Cir. 1993).

Opinion

PLAGER, Circuit Judge.

Appellant, Birch & Davis International, Inc. (Birch), protested a procurement conducted by the Agency for International Development (agency). Although four bids, including two from Birch, were technically acceptable, the contracting officer excluded all but one bid from the initial competitive range. Both Birch bids were excluded.

When Birch challenged this action before the General Services Administration Board of Contract Appeals (Board), the Board held the contracting officer’s decision to be reasonable and within her discretion. Birch appealed the Board’s decision here. We conclude that the Competition in Contracting Act (CICA) and the Federal Acquisition Regulations (FAR) implementing it do not allow a contracting officer to eliminate competitors from the initial competitive range if there is any reasonable chance that they will be selected. The decision of the Board is vacated and the case remanded for proceedings consistent with this opinion.

BACKGROUND AND PROCEDURAL HISTORY

On April 1, 1991 the Agency for International Development issued a Request for Proposals (RFP) for the design and implementation of a computerized management information system for the Egyptian Health Insurance Organization. The proposals were to be evaluated for technical merit factors, worth a combined total of 90 points, and a cost factor, worth 10 points.

Birch submitted three proposals, while four other companies submitted one each. A technical evaluation panel scored the seven bids and deemed four to be technically acceptable. Two of these four were from Birch, leaving three competitors in the bidding. Although Birch’s technical scores were the lowest of the four bids — 10.8 and 12 points behind the highest score — all four of the technically acceptable proposals had numerous deficiencies. Even the highest-scoring bid, from Maximus, scored only 67.5 out of 90 possible points. After the contracting officer factored in the cost evaluations, Maxi-mus’ lead over Birch increased to 15.01 and 15.94 points. Maximus’ total score was 77.05 out of 100 possible points.

On December 10,1991 the contracting officer informed Birch and another bidder that their proposals had been excluded from the initial competitive range. See FAR, 48 C.F.R. § 15.609(a) (1991). This action left Maximus as the sole offeror in range. Because a contracting officer need not conduct discussions with offerors outside the competitive range, see id. § 15.610(b), the contracting officer held discussions with Maximus only.

*972 On December 20,1991 Birch filed a protest with the Board of Contract Appeals (Board), contending that the contracting officer had improperly excluded Birch’s bids from the competitive range. The protest also alleged generally that the technical and cost evaluations were fatally flawed.

In its decision on February 27, 1992, the Board found no error in the calculation of technical and cost scores. Birch & Davis Int’l, Inc. v. Agency for Int’l Dev., 92-2 B.C.A. (CCH) ¶ 24,881 at 124,097-98, 1992 WL 45953 (GSBCA 1992). The Board acknowledged the broad discretion of contracting officers to determine competitive range, but gave “close scrutiny” to the contracting officer’s decision in this case because it restricted the competitive range to a single proposal. Using this close scrutiny, the Board concluded that the contracting officer’s action was reasonable. Id. at 124,098. The Board stated that:

[T]he record ... reflects a thorough and conscientious effort on the part of the TEP [technical evaluation panel] members. The contracting officer has obviously relied heavily upon it. Protester [Birch] has provided us with no evidence which would cause us to doubt the accuracy of the TEP findings or the contracting officer’s reasonable reliance upon it.
We recognize, as did the contracting officer herself, that many of the deficiencies found in protester’s three proposals are obviously of an informational nature and might have been readily remedied through discussions with protester. The same, however, can be said of the deficiencies noted in the other proposals as well — none of which were particularly close to obtaining the highest possible overall score in the initial evaluation. Comments contained in the TEP report ... strongly suggest that, with discussions, the scores of all offerors might significantly improve.... Since the potential for improvement of scores appears to have existed for all offers, the point spread apparent in the initial evaluation was of particular importance and apparently was a significant factor in the contracting officer’s decision not to include protester’s offers in the competitive range.
We see no reason to take issue with the contracting officer’s determination in this case. The record shows that this decision was not made hastily or without consultation.
Whether we agree or disagree with her final decision is immaterial. The test is whether it was a reasonable decision made within the limits of her assigned discretion.

Id. at 124,098-99.

On March 4, 1992 Birch moved for reconsideration of the Board’s decision, on the ground that it failed to address an issue raised in the protest. Birch had argued that the agency, by not seeking full and open competition, violated the Competition in Contracting Act. In its denial of reconsideration on May 6, 1992, the Board rejected Birch’s argument because it was based on the erroneous assumption that the contracting officer’s decision was improper. Birch & Davis Int’l, Inc. v. Agency for Int’l Dev., 92-3 B.C.A. (CCH) ¶ 25,082 at 125,020, 1992 WL 94529 (GSBCA 1992). The Board in its earlier decision had already held that the contracting officer’s decision was proper.

On March 5, 1992 Birch also moved for consideration by the full Board, claiming that the decision in this case conflicted with prior Board decisions. In its denial on May 6, 1992, 1992 WL 94524, the Board found no conflict; its conclusion that the contracting officer’s decision was reasonable turned on specific facts unique to this case. Id. at 125,021. Birch appealed the Board’s decision to this court.

Birch argues that the contracting officer’s exclusion of Birch from the competitive range violated FAR, 48 C.F.R. § 15.609(a), which requires that the competitive range “include all proposals that have a reasonable chance of being selected for award. When there is doubt as to whether a proposal is in the competitive range, the proposal should be included.” Birch contends that the score difference between Birch and Maximus was not insurmountable, especially since Maxi-mus’ bid scored far below the maximum possible score of 100. Birch’s bids were techni *973 cally acceptable, and contained mainly informational deficiencies that could easily be corrected after discussions. Thus, says Birch, its proposals had “a reasonable chance of being selected.”

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Carlson v. Clapper
N.D. California, 2020
(PS) Collins v. XL Construction
E.D. California, 2020
Rivada Mercury, LLC v. United States
131 Fed. Cl. 663 (Federal Claims, 2017)
System Dynamics International, Inc. v. United States
130 Fed. Cl. 499 (Federal Claims, 2017)
Fcn, Inc. v. United States
124 Fed. Cl. 365 (Federal Claims, 2015)
Qbe, LLC v. United States
120 Fed. Cl. 397 (Federal Claims, 2015)
Cmi Management, Inc v. United States
115 Fed. Cl. 276 (Federal Claims, 2014)
Caddell Construction Co., Inc. v. United States
111 Fed. Cl. 49 (Federal Claims, 2013)
Science Applications International Corp. v. United States
108 Fed. Cl. 235 (Federal Claims, 2012)
Chenega Management, LLC v. United States
96 Fed. Cl. 556 (Federal Claims, 2010)
FAS Support Services, LLC v. United States
93 Fed. Cl. 687 (Federal Claims, 2010)
USfalcon, Inc. v. United States
92 Fed. Cl. 436 (Federal Claims, 2010)

Cite This Page — Counsel Stack

Bluebook (online)
4 F.3d 970, 39 Cont. Cas. Fed. 76,561, 1993 U.S. App. LEXIS 23534, 1993 WL 349700, Counsel Stack Legal Research, https://law.counselstack.com/opinion/birch-davis-international-inc-v-warren-m-christopher-secretary-of-cafc-1993.