Binnings Construction Co. v. Carpenter Bros., Inc.

267 So. 2d 750, 1972 La. App. LEXIS 6077
CourtLouisiana Court of Appeal
DecidedOctober 4, 1972
DocketNo. 5064
StatusPublished

This text of 267 So. 2d 750 (Binnings Construction Co. v. Carpenter Bros., Inc.) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Binnings Construction Co. v. Carpenter Bros., Inc., 267 So. 2d 750, 1972 La. App. LEXIS 6077 (La. Ct. App. 1972).

Opinion

BAILES, Judge.

This appeal is from the judgment of the trial court denying recovery to plaintiff, Binnings Construction Company, Inc. (Bin-nings), of alleged expenses incurred in moving pile driving equipment to the construction site on the Louisiana State University campus at Baton Rouge in anticipation of performing work under a subcontract from defendant, Carpenter Brothers, Inc. (Carpenter). Also named defendant in this action was Louisiana State University and Agricultural and Mechanical College (LSU). On an exception to venue LSU was dismissed as a defendant in the main demand, however it was retained at the trial level as third party defendant to the third party demand asserted by Carpenter. Further, Carpenter reconvened against Binnings to recover the sum of $700.00 representing the additional cost of contracting for the construction work originally to be undertaken by Binnings.

In addition to the trial court rejecting plaintiff’s claim against defendant, the defendant’s reconventional demand was rejected as well as its third party demand against the third party defendant, LSU. The defendant, Carpenter, has answered the appeal of Binnings urging that judgment be awarded in its favor for $700.00.

The judgments of the trial court dismissing LSU from the principal demand on the exception to venue and the rejection of the third party demands of Carpenter against LSU are final as no appeal was taken therefrom.

The dispute between the parties arose from a contract between LSU and Carpenter for the construction of the Joan Chaffe Miller Hall, a dormitory on the main campus of LSU at Baton Rouge.

In furtherance of performance under the contract, Carpenter offered for bidding the work of furnishing and driving cast-in-place piles for this building. There is no dispute between the parties about the price or other contract conditions, except a question arose as to the type of pile to be furnished and driven by Binnings. This dispute arose out of a divergence of interpretation of what type pile was required by the specifications.

We quote here the pertinent portions of the General Conditions and specifications of the contract between LSU and Carpenter, all of which the plaintiff either had actual knowedge of or is charged with constructive knowledge. From the testimony of witnesses knowledgeable about such matters, it appears to be a fair statement that the general conditions are standard for contracts of this type.

[752]*752“GENERAL CONDITIONS
« * * *
“35. Architect/Engineer’s Authority
“The Architect/Engineer shall give all orders and directions contemplated under this contract and specifications relative to the execution of the work. The Architect/Engineer shall determine the amount, quality, acceptability and fitness of the several kinds of work and materials which are to be paid for under this contract and shall decide all questions which may arise in relation to said work and the construction thereof. The Architect/Engineer’s estimates and decisions shall be final and conclusive, except as herein otherwise expressly provided. In case any question shall arise between the parties hereto relative to said contract or specifications, the determination or decision of the Architect/Engineer shall be a condition precedent to the right of the Contractor to receive any money or payment for work under this contract affected in any manner or to any extent by such question.
“The Architect/Engineer shall decide the meaning and intent of any portion of the specifications and of any plans or drawings where the same may be found obscure or be in dispute. Any differences or conflicts in regard to their work which may arise between the Contractor under this contract and other Contractors performing work for the Owner shall be adjusted and determined by the Architect/Engineer.
“ * * *
“FOUNDATION PILING
“SCOPE
“All general and supplemental conditions of the contract shall apply to all work included under this Division.
“Contractor shall furnish and drive, complete in place, all steel encased poured-in-place concrete piling shown on the drawings or specified and shall furnish and/or perform all other work and services specified herein.
“GENERAL
“The foundations are 'based on a bearing capacity of 50 tons for each pile. The pile lengths shall be 60 feet extending from cut off elevations, except as may be modified.
“No piles, other than control piles, shall be ordered until loading of test piles has been completed. The Architect will promptly consult with the contractor as to the lengths of piles to be ordered after correlating data obtained from load tests and control piles. Should radical change in design be advisable on the basis of the results of the load tests, the contractor will be promptly notified.
“Eight (8) sample soil borings were made at the site and the complete report of the findings is available at the Architect’s office for the guidance of the contractors. The information furnished on these logs is believed to be correct but is not guaranteed to prevail over the entire site.
“The contractor’s attention is directed to “Excavating, Filling, Backfilling”, Division 2, for piling excavation.
“TYPES OF PILES AND MATERIAL SPECIFICATIONS
“In each case in the following types of piling specified, weights, thickness and diameters specified are the minimum acceptable for design load carrying capacity.
“It shall be the contractor’s responsibility to select adequate metal thickness and piling sections to enable the pile to withstand the driving stresses and lateral pressures imposed upon the piles due to driving adjacent piles and due to lateral earth pressures without buckling or crushing.
“TYPE A_* * *
[753]*753“TYPE B_* * *
“TYPE C — Composite Steel Pipe, Spirally Corrugated Steel Shell Piles Concrete Pilled: These piles shall he cast-in-place concrete filled Armco Hel-cor Shell Piles as furnished by the Armco Drainage and Metal Products, Inc. Piles shall be a spirally corrugated steel shell casing driven in contact with the ground and left in place. The Helcor shell section shall have a nominal diameter of 1214" and shall be closed at the tip end with a suitable flat steel plate.”

While the trial judge did not assign written reasons for judgment, it does appear that he found the Architect-Engineer had the authority, under the general conditions of the contract, to determine the acceptability of any and all materials relating to fulfillment of the contract; and it further appears that he decided that the pile proposed by the plaintiff did not have the approval of the Architect-Engineer; that this approval was a suspensive condition of the contract which resulted in there being no binding contract between the parties unless and until the plaintiff met this condition. Thus, if there was no contract there was no liability by the defendant to the plaintiff for expenses in moving the equipment to the job site.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

JH Jenkins Contractor, Inc. v. City of Denham Springs
216 So. 2d 549 (Louisiana Court of Appeal, 1968)
Detroit Football Company v. Robinson
186 F. Supp. 933 (E.D. Louisiana, 1960)
Blaushild v. Rockhold
7 La. App. 709 (Louisiana Court of Appeal, 1927)
Pyro Incinerator & Supply Corp. v. Gervais F. Favrot Co.
210 So. 2d 356 (Louisiana Court of Appeal, 1968)

Cite This Page — Counsel Stack

Bluebook (online)
267 So. 2d 750, 1972 La. App. LEXIS 6077, Counsel Stack Legal Research, https://law.counselstack.com/opinion/binnings-construction-co-v-carpenter-bros-inc-lactapp-1972.