Blaushild v. Rockhold

7 La. App. 709, 1927 La. App. LEXIS 308
CourtLouisiana Court of Appeal
DecidedDecember 21, 1927
DocketNo. 3136
StatusPublished
Cited by6 cases

This text of 7 La. App. 709 (Blaushild v. Rockhold) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Blaushild v. Rockhold, 7 La. App. 709, 1927 La. App. LEXIS 308 (La. Ct. App. 1927).

Opinion

ODOM, J.

The defendants are general contractors and, on December 14, 1926, entered into a contract with the Jackson Parish School Board to erect a. public school building at Jonesboro in that parish according to plans and specifications made by J. W. ¡Smith, architect, of Monroe, Louisiana.

They subsequently entered into a contract with the plaintiff, Blaushild, to furnish all material and install the heating and plumbing system in said school building at the stipulated price of $7700.00.

The contract between plaintiff and defendants is in writing 'and is attached to and made part of the petition. It provides that plaintiff shall

“furnish all material of every kind and nature whatsoever, and all labor, and to erect and install, and complete all of the heating and plumbing system to be erected and installed in the new brick school building now under construction by the general contractor by and under contract with Jackson Parish School Board, all in accordance with the drawing, plans and specifications of J. W. Smith, architect, of Monroe, Louisiana, a copy of which is now on file in the recorder’s office of Jackson parish, Louisiana, and which copy is made a part hereof, * *

Alleging that defendants breached the contract and refused to permit him to do the work and that he would have made a net profit of $1700.00 if he had been allowed to do the work under the contract, he brought this suit against defendant for that amount.

Defendant, in - answer, admitted the execution of the document alleged to be the contract between them and plaintiff but plead, in substance, that it was signed and delivered with the distinct agreement and understanding that it should have no effect and should not be binding on them unless and until approved by the architect, J. W. Smith; that under the specifications, made a part of the contract, no sub-contractors could be employed without the approval and sanction of the architect, all of which was within the knowledge of plaintiff who was familiar with said specifications; and defendants further alleged that plaintiff made false and fraudulent representations as to his standing as a contractor with said architect which induced them to sign the instrument.

The lower court rejected plaintiff’s demands and he has appealed.

[711]*711OPINION

The substance of the defense is that the contract with plaintiff was only a conditional obligation or one entered into with a suspensive condition, to-wit: that J. W. Smith, the architect, would approve the contract; that the condition upon which the contract depended to make it valid and binding failed because the architect refused to approve it, and that therefore defendant is not bound.

We have no difficulty in reaching the conclusion that the contract was entered into with a suspensive condition, and while that condition is not expressed in the written instrument itself, it is implied from the nature of the contract and the presumed intent of the parties.

The parties to the contract well knew that the principal contractor could not sublet any of the work on the building to anyone who was not satisfactory to the architect.

Plaintiff was familiar with the general rule that the architect must approve all subcontracts. Besides this, the contract was entered into with special reference to the specifications, which were made a part of it.

These specifications provided in specific terms that the contractor should not employ any sub-contractor—

“that the architect may within a reasonable time object to as incompetent or unfit”.

Blaushild was familiar with these specifications. He had a copy of them and said he had read them before the contract was signed. He knew that he could not do the work without the sanction of the architect and he knew that the contract entered into could not ripen into a valid and binding obligation except upon condition that the architect would approve it.

He was not only informed by the specifications but he knew from general custom and the nature of the contract that the approval of the architect was a condition precedent to his doing the work. His knowledge of that fact is doubly manifest by his conduct. After the document was signed he sought and obtained prices o: material and labor for installing the plant. After doing so he was informed by defendant that Smith, the architect, had notified defendant, the Parish School Board and the building committee, that he was not acceptable as a sub-contractor. He at once, it. seems, sought advice of counsel, who told him to see the architect. He went to Monroe and saw Smith and sought his approval; to no avail. In the meantime, as stated, he had obtained prices on material and labor to install the plant.

The material man on numerous occasions urged him to place the order for the material, which he refused to do notwithstanding he was told that the price of material fluctuated and that it was necessary that the order be placed so that the material man might order the goods out at the current price. His asserted reason for not doing so was that he did not need them at that time. We are not impressed by his testimony on that point. We think his conduct in consulting counsel as to his rights and his refusal to place the order for the material indicate that he had in mind all the while that he had no contract which he could enforce, it not having been approved by the architect, and we think his counsel was probably of the same opinion for he advised a consultation with Smith, the architect. If he liad thought and his counsel had advised him that he had a binding contract he would have stood upon it without further ado.

In addition to this, S. J. Roekhold, one [712]*712of the defendants, testified that plaintiff went to see him at Jonesboro and sought the contract to install the plumbing and heating plant in the building and submitted a price, that he told Blaushild that Smith, the architect, would have to be consulted concerning all sub-contracts, and that the plaintiff then informed him that—

“he would be perfectly satisfactory to Mr. Smith and I told Mr. Blaushild that under those conditions, under the condition that he would see Mr. Smith and get his ‘O.K.’ on the contract, we would draw up the contract that day.”

On page 59 of the testimony he said:

“My agreement with Mr. Blaushild was this, we were drawing the contract that day with the understanding that he would see Mr. Smith before it went on file and get his ‘O.K.’ on it and put it on record and go ahead with the work.”'

On being asked what was done at the time, and if ^he signed the contract, and whether the whole transaction took but a few minutes, he said:

“I did with the statement from Mr. Blaushild that he would see Mr. Smith immediately and get his ‘O.K.’ on the contract and then would have it .recorded, and then it would, be valid.”

Sam Nomey, one of the defendants, testified that he was present when the document was signed and heard what was said and heard S. J. Rockhold tell Blaushild that if Smith failed to approve it, it would not be binding upon anybody, and that Blaushild said:

“If Smith don’t ‘O.K.’ it, it will be all right, it won’t be binding on either one.”

Henry Rockhold, son and employee of defendant, S. J.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Musquez v. Barksdale Federal Credit Union
343 So. 2d 401 (Louisiana Court of Appeal, 1977)
Binnings Construction Co. v. Carpenter Bros., Inc.
267 So. 2d 750 (Louisiana Court of Appeal, 1972)
Wagenvoord Broadcasting Co. v. Le Blanc
221 So. 2d 282 (Louisiana Court of Appeal, 1969)
Mire v. Haas
174 So. 374 (Louisiana Court of Appeal, 1937)
Reed & Brown, Inc. v. Morning Treat Coffee Co.
164 So. 449 (Louisiana Court of Appeal, 1935)
Ewell v. Giamanco
139 So. 515 (Louisiana Court of Appeal, 1932)

Cite This Page — Counsel Stack

Bluebook (online)
7 La. App. 709, 1927 La. App. LEXIS 308, Counsel Stack Legal Research, https://law.counselstack.com/opinion/blaushild-v-rockhold-lactapp-1927.