IN THE COURT OF APPEALS OF NORTH CAROLINA
No. COA24-320
Filed 2 April 2025
Mecklenburg County, No. 23 CVS 9269
BILFINGER INC., Plaintiff,
v.
CARGILL, INCORPORATED, Defendant.
Appeal by Defendant from Order entered 29 November 2023 by Judge George
C. Bell in Mecklenburg County Superior Court. Heard in the Court of Appeals 23
October 2024.
Bell, Davis & Pitt, P.A., by Joshua B. Durham and Edward B. Davis; Eversheds Sutherland (US) LLP, by Lee C. Davis, pro hac vice, and Tracey K. Ledbetter, pro hac vice, for plaintiff-appellee.
Robinson, Bradshaw & Hinson, P.A., by Edward F. Hennessey, IV; Faegre Drinker Biddle & Reath LLP, by Aaron Van Oort, pro hac vice, for defendant- appellant.
HAMPSON, Judge.
Factual and Procedural Background
Cargill, Incorporated (Defendant) appeals from an Order denying its Motion to
Compel Arbitration and granting Bilfinger Inc.’s (Plaintiff) Motions to Stay
Arbitration and to Supplement the Record entered on 29 November 2023. The Record
before us tends to reflect the following:
Defendant owns facilities across the country, including a facility located in
Charlotte, North Carolina. At the Charlotte facility, Defendant refines, packages, BILFINGER INC. V. CARGILL, INC.
Opinion of the Court
and ships edible vegetable oil and shortening products. Plaintiff is an international
contractor and construction company. On or about 26 March 2021, Plaintiff
contracted with Defendant to provide mechanical and piping services on Defendant’s
projects throughout the country. The parties executed a Master Services Agreement
(MSA), the general contract framework for all projects entered into between the
parties. For individual projects over $250,000, the parties agreed to supplement the
MSA with project-specific contracts. The MSA provides that if a project-specific
contract addresses a topic addressed by the MSA, the MSA will render those terms
null and void:
7(d). . . . Notwithstanding any terms in the [project-specific contract] documents, to the extent that a topic is addressed or a remedy is provided for in this Agreement, corresponding terms or remedies set forth in the [project-specific contract] documents are null and void and of no [e]ffect as to the rights or obligations of either [Defendant] or [Plaintiff]. To the extent that a topic is not addressed or a remedy is not provided for in this Agreement, then the terms of the [project-specific contract] shall control for that specific topic or remedy.
Plaintiff began a project at Defendant’s Charlotte facility to construct two new
hydrogenation towers and expand its processing operations. The contract price for
the project exceeded $250,000, so the parties entered into a project-specific agreement
to supplement the MSA; the project-specific agreement expressly incorporates by
reference another document, the “General Conditions” of the agreement (collectively,
Construction Contract). Both the MSA and the Construction Contract contain
sections titled “Dispute Resolution”, which discuss the procedures to be undertaken
-2- BILFINGER INC. V. CARGILL, INC.
in the event a dispute arises between the parties. Under MSA Section 26, if a dispute
arises, the parties must first attempt to resolve it by reporting it in writing to senior
management representatives. If senior management does not resolve the dispute
within twenty days of receiving notice, then the parties may agree to mediate the
dispute, but “regardless whether mediation has occurred, either party may pursue
court action”:
26(b). After [twenty days] and upon mutual agreement of the parties, either party may submit the Dispute to a third party mediator recognized in the field of alternative dispute resolution, and acceptable to the other party. The mediation will be non- binding, and occur at a time and place acceptable to both parties with each party bearing its respective costs. After [twenty days], regardless whether mediation has occurred, either party may pursue court action pursuant to the requirements and limitations set forth in this Agreement. Notwithstanding any other provision of this Agreement, each Party is entitled to immediate access to the courts to: (i) toll any statute of limitation or (ii) seek appropriate injunctive relief or other equitable remedy if, in such party’s sole discretion, such action is deemed necessary to avoid irreparable damage or preserve the status quo.
By contrast, under Article 16 of the Construction Contract, “[a]ll claims arising out of
the Contract Documents shall be subject to arbitration[.]”
Indeed, disputes eventually arose between the parties. The parties referred
the disputes to senior management, as contemplated by the MSA. Senior
management did not resolve the disputes within twenty days. In accordance with
MSA Section 26, Plaintiff brought an action against Defendant in Mecklenburg
County Superior Court on 26 May 2023, alleging a claim for Breach of Contract and
-3- BILFINGER INC. V. CARGILL, INC.
seeking foreclosure of a mechanic’s lien. On 24 July 2023, Defendant filed a Demand
for Arbitration with the American Arbitration Association. On 26 July 2023,
Defendant filed Motions to Compel Arbitration and Stay Judicial Proceedings, relying
on the arbitration clause contained in Article 16 of the Construction Contract.
Plaintiff filed a Cross-Motion to Stay Arbitration on 5 September 2023. The Motions
were heard before the trial court on 12 September 2023. The same day, Plaintiff filed
a Motion to Supplement the Record with an additional affidavit (Second Affidavit),
which it had served on Defendant the night prior.
On 29 November 2023, the trial court denied Defendant’s Motion to Compel
Arbitration and granted Plaintiff’s Motion to Supplement the Record and Motion to
Stay Arbitration. On 12 December 2023, Defendant timely filed Notice of Appeal.
Appellate Jurisdiction
“[A]n appeal from the trial court’s denial of a motion to compel arbitration is
an interlocutory order.” U.S. Trust Co., N.A. v. Stanford Grp. Co., 199 N.C. App. 287,
289, 681 S.E.2d 512, 513 (2009) (citation omitted). Generally, “a party has ‘no right
of immediate appeal from interlocutory orders and judgments.’ ” Bartels v. Franklin
Operations, LLC, 288 N.C. App. 193, 195, 885 S.E.2d 357, 359 (2023) (quoting
Goldston v. Am. Motors Corp., 326 N.C. 723, 725, 392 S.E.2d 735, 736 (1990)).
However, “ ‘an order denying arbitration, although interlocutory, is immediately
appealable because it involves a substantial right which might be lost if appeal is
delayed.’ ” Brown v. Centex Homes, 171 N.C. App. 741, 743, 615 S.E.2d 86, 87 (2005)
-4- BILFINGER INC. V. CARGILL, INC.
(quoting Prime S. Homes, Inc. v. Byrd, 102 N.C. App. 255, 258, 401 S.E.2d 822, 825
(1991)); N.C. Gen. Stat. § 7A-27(b)(3)(a) (2023) (appeal lies of right directly to the
Court of Appeals from any interlocutory order or judgment of a superior court in a
civil action or proceeding which affects a substantial right); N.C. Gen. Stat. § 1-
569.28(a)(1) (2023) (appeal may be taken from an order denying a motion to compel
arbitration).
However, we have also held that where no arbitration agreement is found to
exist, the interlocutory appeal does not affect a substantial right and is subject to
dismissal.1 See JRM, Inc. v. HJH Companies, Inc., 287 N.C. App. 592, 598, 883
1 Our dissenting colleague—who authored JRM, Inc.—now takes issue with the approach that
case requires us to employ. Indeed, prior to JRM, Inc., we have also simply affirmed in other similar instances. See, e.g., Register v. Wrightsville Health Holdings, LLC, 271 N.C. App. 257, 843 S.E.2d 464 (2020) (affirming trial court’s denial of motion to compel arbitration); Sciolino v. TD Waterhouse Investor Servs., Inc., 149 N.C. App. 642, 562 S.E.2d 64 (2002) (same); Kennedy v. Branch Banking & Trust Co., 165 N.C. App. 275, 600 S.E.2d 520 (2004) (unpublished) (same). Under N.C. Gen. Stat. § 1-569.6(b) (2023), “[t]he court shall decide whether an agreement to arbitrate exists or a controversy is subject to an agreement to arbitrate.” On the motion of a person showing an agreement to arbitrate, the court shall order the parties to arbitrate unless it finds there is no enforceable agreement to arbitrate. N.C. Gen. Stat. § 1-569.7(a)(2) (2023) (emphasis added). Previously, our statute governing proceedings on a motion to compel or stay arbitration considered whether the party opposing the motion to compel arbitration denied the existence of an agreement to arbitrate. See N.C. Gen. Stat. § 1-567.3 (repealed 2004) (emphasis added). Thus, the language surrounding whether an arbitration agreement “exists” when reviewing a motion to compel or stay arbitration appears to be an artifact of caselaw applying old statutory language. See e.g., Sciolino, 149 N.C. App. at 645, 562 S.E.2d at 66 (“When a party disputes the existence of a valid arbitration agreement, the trial judge must determine whether an agreement to arbitrate exists.” (citing N.C. Gen. Stat. § 1-567.3(a) (1999) (repealed 2004)); Slaughter v. Swicegood, 162 N.C. App. 457, 461, 591 S.E.2d 577, 580 (2004) (citing N.C. Gen. Stat. § 1-567.3 (2001) (repealed 2004)); Evangelistic Outreach Ctr. v. Gen. Steel Corp., 181 N.C. App. 723, 726, 640 S.E.2d 840, 843 (2007) (“If a party claims that a dispute is covered by an agreement to arbitrate but the adverse party denies the existence of an arbitration agreement, the trial court shall determine whether an agreement exists.” (quoting Slaughter, 162 N.C. App. at 461, 591 S.E.2d at 580)). Where the existence of an arbitration agreement is solely at issue, such as in JRM, Inc., the proper approach may be to treat the appeal as interlocutory and determine whether the appeal should
-5- BILFINGER INC. V. CARGILL, INC.
S.E.2d 217, 221 (2023). Here, the trial court concluded there was no agreement to
arbitrate because any arbitration agreement was null and void. Thus, if a valid
agreement to arbitrate does not exist, Defendant has failed to show a substantial
right is affected and this Court lacks jurisdiction to review the trial court’s
interlocutory order denying Defendant’s motion to compel arbitration. See id.
Issues
The issues on appeal are whether the trial court: (I) abused its discretion by
admitting Plaintiff’s Second Affidavit; and (II) properly denied the Motion to Compel
Arbitration on the basis there was no agreement to arbitrate between the parties
because the MSA rendered the alleged arbitration clause null and void.
Analysis
I. Admission of Second Affidavit
As a threshold matter, Defendant contends the trial court erred by granting
Plaintiff’s Motion to Supplement the Record and admitting the Second Affidavit. This
Court reviews a trial court’s ruling on an untimely affidavit for abuse of discretion.
be dismissed or not based on a review of the merits. See 287 N.C. App. at 597-98, 883 S.E.2d at 220- 21. Where the enforceability of an existing arbitration agreement is at issue, however, the more appropriate approach may be to accept the matter as involving a substantial right and decide the case squarely on the merits. See Pressler v. Duke Univ., 199 N.C. App. 586, 685 S.E.2d 6 (2009). See also Arthur Andersen LLP v. Carlisle, 556 U.S. 624, 628-29, 129 S. Ct. 1896, 1900-01, 173 L.Ed.2d 832 (2009) (holding the underlying merits of an appeal from an order denying a stay pending arbitration are irrelevant in determining whether an appellate court has jurisdiction over the appeal). Nonetheless, where a panel of the Court of Appeals has decided the issue, albeit in a different case, we are bound by that precedent. In re Civil Penalty, 324 N.C. 373, 384, 379 S.E.2d 30, 37 (1989). As such, we faithfully apply JRM, Inc.’s rubric to this matter. Moreover, the effect of the mandate is the same: in the absence of an agreement to arbitrate, the trial court’s order denying arbitration will be upheld and the appeal dismissed as interlocutory.
-6- BILFINGER INC. V. CARGILL, INC.
Lane v. Winn-Dixie Charlotte, Inc., 169 N.C. App. 180, 184, 609 S.E.2d 456, 458-59
(2005).
Rule 6(d) of the North Carolina Rules of Civil Procedure generally requires
affidavits in support of a motion be served with the motion and—unless otherwise
provided—affidavits in opposition to a motion be served at least two days before the
hearing on the motion. N.C. Gen. Stat. § 1A-1, Rule 6(d) (2023). However, even “[i]f
the opposing affidavit is not served on the other parties at least two days before the
hearing on the motion, the court may continue the matter for a reasonable period to
allow the responding party to prepare a response, proceed with the matter without
considering the untimely served affidavit, or take such other action as the ends of
justice require.” Id.
Here, Plaintiff served the Second Affidavit on Defendant less than two days
before the hearing on the Motion to Compel Arbitration. Nonetheless, the trial court,
in its discretion, accepted the Second Affidavit as part of the Record. Specifically, the
trial court noted the Second Affidavit was submitted in response to an argument first
raised by Defendant in its memorandum opposing Plaintiff’s Motion to Stay
Arbitration.
In particular, the trial court relied on the Second Affidavit solely for
determining the purpose of the MSA’s preemption clause and to find—counter to
Defendant’s argument—the parties did not specifically negotiate any of the terms in
Article 16 of the Construction Contract:
-7- BILFINGER INC. V. CARGILL, INC.
7. Section 7(d) of the MSA provides that “to the extent that a topic is addressed or a remedy is provided for in this Agreement [the MSA], corresponding terms or remedies set forth in the [Construction Contract] are null and void and of no affect as to the rights or obligations of either [Defendant] or [Plaintiff]” . . . The purpose of this language was to spare the parties the effort of reviewing the lengthy form contracts to determine each and every way that some clause might cover the same topic already addressed by and agreed to in the MSA. ([Second Affidavit], filed on September 11, 2023 . . . at ¶¶ 3-5.)
....
10. The parties did not specifically negotiate any of the terms in Article 16 of the general conditions of the [Construction Contract]. ([Second Affidavit] at ¶¶ 4-5.)
There is no indication the trial court relied on the Second Affidavit in
specifically concluding MSA Section 7(d) rendered Article 16 of the Construction
Contract null and void. To the contrary, the trial court concluded the MSA rendered
the Construction Contract’s Dispute Resolution provisions null and void by its own
terms, reasoning that because MSA Section 26 and Article 16 of the Construction
Contract cover the “exact same” topic, the terms contained in the Construction
Contract are null and void.
Thus, the trial court’s consideration of the late-filed affidavit was solely
supplemental in purpose and used to rebut an argument newly raised by Defendant
in Defendant’s own opposition to Plaintiff’s motion. See Rolling Fashion Mart, Inc. v.
Mainor, 80 N.C. App. 213, 216, 341 S.E.2d 61, 63 (1986) (no abuse of discretion in
admitting untimely affidavit where “affidavit was clearly supplemental in that it did
-8- BILFINGER INC. V. CARGILL, INC.
no more than explain the transactions referred to in the earlier affidavits filed by the
parties and provide copies of the documents involved in those transactions.”).
Therefore, Defendant has not demonstrated any abuse of discretion by the trial court
in admitting and considering the Second Affidavit. See Lane, 169 N.C. App. at 184-
85, 609 S.E.2d at 458-59 (finding trial court did not err in allowing affidavit to be
admitted after motion was filed where “[p]laintiffs have failed to show abuse of
discretion in the trial court’s decision to deny plaintiffs’ request to strike [the]
affidavit.”). Consequently, the trial court did not commit reversible error in allowing
Plaintiff to supplement the Record with the Second Affidavit.
II. Motion to Compel Arbitration
Defendant contends the trial court erred in concluding there was no valid
agreement to arbitrate. Under N.C. Gen. Stat. § 1-569.7 (2023),
(a) On motion of a person showing an agreement to arbitrate and alleging another person’s refusal to arbitrate pursuant to the agreement:
(2) If the refusing party opposes the motion, the court shall proceed summarily to decide the issue and order the parties to arbitrate unless it finds that there is no enforceable agreement to arbitrate.
This Court has elaborated “the trial court must perform a two-step analysis
requiring the trial court to ascertain both (1) whether the parties had a valid
agreement to arbitrate, and also (2) whether the specific dispute falls within the
-9- BILFINGER INC. V. CARGILL, INC.
substantive scope of that agreement.” U.S. Trust Co., N.A., 199 N.C. App. at 290, 681
S.E.2d at 514 (citation and quotation marks omitted). “ ‘[T]he trial court’s findings
regarding the existence of an arbitration agreement are conclusive on appeal where
supported by competent evidence, even where the evidence might have supported
findings to the contrary.’ ” Ellis-Don Constr., Inc. v. HNTB Corp., 169 N.C. App. 630,
633-34, 610 S.E.2d 293, 296 (2005) (citations omitted). We review the trial court’s
conclusions of law de novo. Hager v. Smithfield E. Health Holdings, LLC, 264 N.C.
App. 350, 354-55, 826 S.E.2d 567, 571 (2019) (citation omitted).
The parties do not contest that “to the extent that a topic is addressed or a
remedy is provided for” in the MSA, it renders corresponding contents in the
Construction Contract null and void. The parties disagree, however, as to what the
language “to the extent” contemplates in this context. Defendant argues MSA Section
26 “did not prescribe terms for arbitration” and thus “addressed dispute resolution
only to the extent it involved senior management, mediation by mutual agreement,
and access to the courts for the limited purpose of tolling the statute of limitations
and to avoid irreparable damage or preserve the status quo[.]” In other words,
Defendant contends, because the MSA does not expressly say anything about
arbitration, it does not “address” arbitration and thus does not render Article 16 of
the Construction Contract null and void. Consequently, according to Defendant,
Article 16 of the Construction Contract requires the parties to arbitrate their dispute.
The MSA provides
- 10 - BILFINGER INC. V. CARGILL, INC.
[n]otwithstanding any terms in the [Construction Contract] documents, to the extent that a topic is addressed or a remedy is provided for in this Agreement, corresponding terms or remedies set forth in the [Construction Contract] documents are null and void and of no [e]ffect as to the rights or obligations of either [Defendant] or [Plaintiff].
The MSA also provides “[t]o the extent that a topic is not addressed or a remedy is
not provided for in [the MSA],” then the terms of the Construction Contract shall
control on that specific topic or remedy (emphasis added). Both the MSA and the
Construction Contract contain sections with the heading “Dispute Resolution”.
Within those sections, each discusses the procedures for resolving a dispute, with the
MSA allowing for court action and the Construction Contract requiring all disputes
to be arbitrated.
In denying Defendant’s Motion to Compel Arbitration, the trial court
concluded:
5. Section 7(d) of the MSA provides that “to the extent that a topic is addressed or a remedy is provided for in this Agreement [the MSA], corresponding terms or remedies set forth in the [Construction Contract] documents are null and void and of no [e]ffect as to the rights or obligations of either [Defendant] or [Plaintiff].” (Emphasis added). Thus, the parties agreed in advance that if the MSA and the [Construction Contract] cover the same topic, the provisions of the MSA apply and the provisions of the [Construction Contract] are “null and void and of no [e]ffect.”
6. Because MSA § 26 and [the Construction Contract] § 16 cover the exact same “topic” of dispute resolution, the terms of the [Construction Contract] on the topic of dispute resolution are “null and void” under the MSA.
- 11 - BILFINGER INC. V. CARGILL, INC.
7. The dispute resolution section of the [Construction Contract] General Conditions, including the delegation clause, therefore never governed the rights or obligations of [Plaintiff] or [Defendant] (on the topic of Dispute Resolution), the parties never agreed to arbitration as a matter of the plain language of the contracts, and the parties never agreed that the arbitrator would decide arbitrability.
(emphasis in original). In support of these conclusions, the trial court made specific
findings, including the following:
7. Section 7(d) of the MSA provides that “to the extent that a topic is addressed or a remedy is provided for in this Agreement [the MSA], corresponding terms or remedies set forth in the [Construction Contract] are null and void and of no [e]ffect as to the rights or obligations of either [Defendant] or [Plaintiff]” . . . .
8. The MSA contains a section on the topic of (and is specifically titled) “Dispute Resolution,” which provides that disputes will be resolved first by negotiation among senior management representatives of the parties; thereafter, “either party may pursue court action.” (MSA § 26.)
9. The general conditions to the [Construction Contract] also contain a section on the topic of (and specifically titled) “Dispute Resolution” which states that the parties will resolve disputes through arbitration ([Construction Contract], General Conditions § 16.)
(emphasis in original). These findings accurately recite the relevant provisions of
each agreement and are, therefore, supported by the evidence.
Defendant argues “having the same heading or touching the same topic is not
enough to prompt preemption under Section 7(d).” However, as the trial court found,
not only do the agreements share headings on the same topic, but the substantive
provisions under each heading also address what the parties are to do in the event a
- 12 - BILFINGER INC. V. CARGILL, INC.
dispute arises between them.
Defendant further contends the parties agreed the MSA would preempt
overlapping “contradictory” terms in the Construction Contract and only to the extent
the MSA prescribed those terms. Defendant urges us to read the MSA and the
Construction Contract “harmoniously,” such that the terms of the agreements do not
overlap, giving effect to the provisions of both agreements. Defendant argues the
agreements should be interpreted together, such that any dispute between the parties
must first be submitted to senior management in accordance with MSA Section 26,
then either party may seek to resolve the dispute through mediation—also in
accordance with MSA Section 26; absent mutual agreement to mediate the dispute,
it shall be subject to arbitration in accordance with Article 16 of the Construction
Contract—and a party may only immediately pursue court action in order to toll the
statutes of limitations or seek injunctive or equitable relief pursuant to MSA Section
26.
It is true, this Court should interpret contracts “in a manner that gives effect
to all of its provisions, if the court is reasonably able to do so.” Johnston Cty. v. R.N.
Rouse & Co., Inc., 331 N.C. 88, 94, 414 S.E.2d 30, 34 (1992) (citation omitted).
However, we also must interpret a contract by its plain language when possible. See
Internet East, Inc. v. Duro Communications, Inc., 146 N.C. App. 401, 405, 553 S.E.2d
84, 87 (2001) (“Where the terms of a contractual agreement are clear and
unambiguous, the courts cannot rewrite the plain meaning of the contract.”). See also
- 13 - BILFINGER INC. V. CARGILL, INC.
Morrell v. Hardin Creek, Inc., 371 N.C. 672, 686, 821 S.E.2d 360, 369 (2018) (the
Court must “enforce the parties’ intent as evidenced by the clear and explicit language
of the [contract]”).
Here, the language of the MSA states: to the extent a topic is addressed or a
remedy is provided for in the MSA, corresponding terms or remedies set forth in the
Construction Contract are null and void and of no effect as to the rights or obligations
of either Plaintiff or Defendant. The trial court concluded the same:
8. It is not necessary for the Court to determine whether the MSA and [the Construction Contract] dispute resolution provisions conflict because the MSA explicitly states that where a “topic” or “remedy” is addressed in the MSA, then a corresponding topic or remedy in the [Construction Contract] is null and void.
Indeed, MSA Section 7(d) contemplates there may be overlap of topics or remedies in
subsequent project-specific agreements such as the Construction Contract—and
provides that in such instances, the terms contained in the MSA should control.
Moreover, we may not “creatively interpret the parties’ actual . . . agreement in the
manner urged . . . and must instead enforce the parties’ intent as evidenced by the
clear and explicit language of the” MSA—that the MSA renders any corresponding
terms in the Construction Contract null and void. Morrell, 371 N.C. at 686, 821
S.E.2d at 369.
Further, the cases cited by Defendant for its argument a contract should be
construed in a manner that gives full effect to all provisions are distinguishable from
the facts before us. See R.N. Rouse & Co., Inc., 331 N.C. at 90, 414 S.E.2d at 32
- 14 - BILFINGER INC. V. CARGILL, INC.
(contract stated “in the event of any conflicting statements or requirements” between
two agreements, the subsequent agreement would control (emphasis added)
(quotation marks omitted)); Internet East, Inc., 146 N.C. App. at 405-06, 553 S.E.2d
at 87 (agreement compelled arbitration “[u]nless the parties shall agree otherwise”);
In re Hall, 210 N.C. App. 409, 415, 708 S.E.2d 174, 178 (2011) (construing two
agreements in a harmonious manner where neither agreement provided for control
over the other); Lowder, Inc. v. Highway Comm., 26 N.C. App. 622, 642, 217 S.E.2d
682, 695 (1975) (contract contained “no indication” one clause was to “override” the
other), cert. denied, 288 N.C. 393, 218 S.E.2d 467 (1975). Indeed, none of these cases
concern an agreement which purported to have a voiding effect on corresponding
terms and remedies in other agreements.
The dissent places heavy emphasis on the language in MSA Section 26(b)
stating “Notwithstanding any other provision of [the MSA], each Party is entitled to
immediate access to the courts to: (i) toll any statute of limitation or (ii) seek
appropriate injunctive relief or other equitable remedy if, in such party’s sole
discretion, such action is deemed necessary to avoid irreparable damage or preserve
the status quo.”
Contrary to the dissent’s assertion, our interpretation of the MSA and
Construction Contract gives consistent effect to this provision. Section 26(a) requires
the parties to first refer “[a]ny controversy or claim” to senior management by written
request. Section 26(b) allows the parties—twenty days after referring the dispute to
- 15 - BILFINGER INC. V. CARGILL, INC.
senior management—to either mediate the dispute or pursue court action “pursuant
to the requirements and limitations set forth in [the MSA].” Thus, read in the full
context of the agreement, Section 26(b) allows the parties to immediately access the
courts to toll any statute of limitation or seek injunctive or equitable relief without
first submitting the dispute to management or pursuing mediation as prescribed in
Section 26(a) and (b) if such action is “deemed necessary to avoid irreparable damage
or preserve the status quo.” (emphasis added). In other words, the parties may
immediately seek court action to preserve their rights while undertaking the dispute
resolution process mandated by the MSA. Otherwise, the parties must follow the
requirements and limitations set forth in the MSA and the remainder of Section 26—
which Plaintiff has done here.
Here, MSA Section 7(d) expressly provides that to the extent the MSA
addresses a topic, it renders corresponding terms or remedies set forth in the
Construction Contract null and void. Thus, the Record supports the trial court’s
Findings that the MSA and the Construction Contract both contain sections titled
“Dispute Resolution” and that MSA Section 26 provides specific terms for dispute
resolution—expressly allowing for resolution in court—and Article 16 of the
Construction Contract provides its own dispute resolution process—arbitration.
These Findings, in turn, support the trial court’s Conclusion that because MSA
Section 26 and Article 16 of the Construction Contract “cover the exact same ‘topic’ ”,
Article 16 of the Construction Contract is null and void. Consequently, consistent
- 16 - BILFINGER INC. V. CARGILL, INC.
with JRM, Inc., this appeal is interlocutory and does not affect a substantial right,
subjecting it to dismissal. See 287 N.C. App. at 598, 883 S.E.2d at 221.
Conclusion
Accordingly, for the foregoing reasons, Defendant’s appeal from the trial
court’s Order Denying its Motion to Compel Arbitration is dismissed.
DISMISSED.
Judge FLOOD concurs.
Judge TYSON dissents by separate opinion.
- 17 - No. COA24-320 – Bilfinger Inc. v. Cargill, Inc.
TYSON, Judge, dissenting.
The majority’s opinion wrongfully dismisses Defendant’s immediately-
available appeal of the trial court’s denial of his motion to compel arbitration. The
two clauses and remedies in the Master Service Agreement (“MSA”) and the later and
more specific Construction Contract are consistent and harmonious. The content and
exclusions of the specific provisions read together reflect the intent and agreement of
the parties. The paragraph headers are merely surplus and non-binding.
The MSA does not specifically exclude arbitration as an additional option and
remedy to senior managements’ meeting, mediation, and does not prevent the parties
from resorting to the courts in the limited instances stated. The MSA provides:
either party may pursue court action pursuant to the requirements and limitations set forth in this Agreement. Notwithstanding any other provision of this Agreement, each Party is entitled to immediate access to the courts to: (i) toll any statute of limitation or (ii) seek appropriate injunctive relief or other equitable remedy if, in such party’s sole discretion, such action is deemed necessary to avoid irreparable damage or preserve the status quo. (emphasis supplied).
Resorting to the courts is expressly limited by and to the enumerated purposes stated
in this “Notwithstanding” and overriding provision.
It makes perfect sense for the parties to expressly agree to a later and more
specific individualized Construction Contract, in addition to the MSA, for capital
projects over $250,000, as opposed to smaller or nickel and dime daily maintenance
between the parties. An arbitration option is needed as a supplement to the informal BILFINGER INC. V. CARGILL, INC.
TYSON, J., dissenting
discussion between management and non-binding mediation for a prompt, final and
binding decision. Much more is at stake for both parties on large projects. The delays
inherent during litigation, while in the midst of large-scale projects, are intolerable
for both parties.
This is a multi-million or multi-hundred-million dollar project. The project-
specific Construction Contract is later in time, was specifically agreed to, and is in
addition to, amends, and extends the MSA. The addition of arbitration as another
procedure and remedy to resolve disputes does not usurp or conflict with any “topic”
or provisions of the MSA. A more specific and later-in-time agreement takes priority
and controls over an earlier and more general agreement. See Wood-Hopkins
Contracting Co. v. N.C. State Ports Auth., 284 N.C. 732, 738, 202 S.E.2d 473, 476
(1974) (“[W]hen general terms and specific statements are included in the same
contract and there is a conflict, the general terms should give way to the specifics.”).
The presence of arbitration as a remedy to quickly resolve disputes in the project-
specific Construction Contract, is binding and is entirely consistent with the parties’
expressed intent in the later agreement.
The Federal Arbitration Act “was enacted in 1920 in response to widespread
judicial hostility to arbitration agreements.” AT&T Mobility LLC v. Concepcion, 563
U.S. 333, 339, 179 L. Ed. 2d 742, 750 (2011) (citing Hall Street Associates, L.L.C. v.
Mattel, Inc., 552 U.S. 576, 581, 170 L.Ed.2d 254 (2008)).
The Federal Arbitration Act provides:
2 BILFINGER INC. V. CARGILL, INC.
A written provision in any maritime transaction or a contract evidencing a transaction involving commerce to settle by arbitration a controversy thereafter arising out of such contract or transaction . . . shall be valid, irrevocable, and enforceable, save upon such grounds as exist at law or in equity for the revocation of any contract.
9 U.S.C. § 2 (2024) (emphasis supplied).
The Supreme Court of the United States “described this provision as reflecting
both a ‘liberal federal policy favoring arbitration,’ and the ‘fundamental principle that
arbitration is a matter of contract.”’ Id. (internal citations omitted). Justice Scalia,
writing for the majority of the Court held “courts must place arbitration agreements
on an equal footing with other contracts, and enforce them according to their terms.
Id. (internal citations omitted).
The trial court erred in denying Defendant’s motion to compel arbitration and
the majority’s opinion errs in dismissing Defendant’s timely appeal. I respectfully
dissent.
I. Background
An express agreement between the parties to arbitrate disputes, and the denial
of that mechanism to resolve those disputes, triggers immediate review. To cease
progress mid-point and languish in litigation purgatory will kill a large construction
project quicker than anything else. Disputes over specific approvals, permits, time,
materials, finance, completion, quality and delivery schedules demand prompt and
final resolution. That is the reason Congress and our General Assembly and multiple
3 BILFINGER INC. V. CARGILL, INC.
binding precedents provide enforcement and allow for interlocutory review of the
denial of an expressly-agreed-to alternative dispute resolution.
The later and more specific Construction Contract meets all the elements of a
valid express contract and should be enforced according to its terms. Neither
Plaintiff, the trial court, nor the majority’s opinion dispute the validity of the later
Construction Contract. In fact, it is that very contract Plaintiff seeks to enforce in an
unauthorized forum after Plaintiff had bargained for and agreed to arbitration to
timely resolve disputes under that very agreement!
Plaintiff brought a purported action in Mecklenburg County Superior Court on
26 May 2023 against Defendant alleging a claim for Breach of Contract and seeking
foreclosure of a mechanic’s lien. Neither of Plaintiff’s claims in the trial court seeks
to “toll any statute of limitation or (ii) seek appropriate injunctive relief” under the
MSA.
Defendant timely filed a Demand for Arbitration with the American
Arbitration Association on 24 July 2023. Defendant also filed Motions to Compel
Arbitration and to Stay Judicial Proceedings on 26 July 2023, relying upon the
arbitration clause contained in Article 16 of the Construction Contract. Plaintiff filed
a Cross-Motion to Stay Arbitration on 1 September 2023. The Motions were heard
before the trial court on 12 September 2023. The trial court denied Defendant’s
Motion to Compel Arbitration and granted Plaintiff’s motion to Stay Arbitration on
28 November 2023. On 12 December 2023, Defendant timely filed Notice of Appeal.
4 BILFINGER INC. V. CARGILL, INC.
II. Standard of Review
Federal and North Carolina statutes and precedents strongly encourage
arbitration as an agreed-upon and alternative means for parties to resolve their
disputes. Courts have held to enforce this principle, it is “well established that an
order denying a motion to compel arbitration is immediately appealable.” Cornelius
v. Lipscomb, 224 N.C. App. 14, 16, 734 S.E.2d 870, 871 (2012) (citing Edwards v.
Taylor, 182 N.C. App. 722, 724, 643 S.E.2d 51, 53 (2007)); U.S. Trust Co., N.A. v.
Stanford Grp. Co., 199 N.C. App. 287, 289, 681 S.E.2d 512, 513 (2009) (citation
omitted) (“[A]n appeal from the trial court’s denial of a motion to compel arbitration
is an interlocutory order.”). The trial court’s conclusions of law are reviewed de novo
on appeal. Hager v. Smithfield E. Health Holdings, LLC, 264 N.C. App. 350, 354-55,
826 S.E.2d 567, 571 (2019)
III. Analysis
A. N.C. Gen. Stat. § 1-569.7(a)(2)
N.C. Gen. Stat. § 1-569.7(a)(2) (2023) provides:
(a) On motion of a person showing an agreement to arbitrate and alleging another person’s refusal to arbitrate pursuant to the agreement:
(2) If the refusing party opposes the motion, the court shall proceed summarily to decide the issue and order the parties to arbitrate unless it finds that there is no enforceable agreement to arbitrate.
The trial court must perform a two-step analysis “to ascertain both: (1) whether
5 BILFINGER INC. V. CARGILL, INC.
the parties had a valid agreement to arbitrate; and also, (2) whether the specific
dispute falls within the substantive scope of that agreement.” U.S. Trust Co., N.A.,
199 N.C. App. at 290, 681 S.E.2d at 514.
Defendant argues MSA Section 26 “did not prescribe [nor proscribe] terms for
arbitration,” did not expressly prohibit it as a procedure or remedy, and “addressed
dispute resolution only to the extent it involved senior management, mediation by
mutual agreement, and access to the courts for the limited purpose of tolling the
statute of limitations and to avoid irreparable damage or preserve the status quo[.]”
Defendant correctly asserts the MSA does not expressly contain anything about
arbitration, does not “address” arbitration, and does not exclude or render Article 16
of the Construction Contract null and void.
B. Standards of Interpretation
The Construction Contract is a separate, distinct, specific, and more recent
contract between the parties, which contains all essential elements of a valid express
agreement. Wood-Hopkins Contracting Co., 284 N.C. at 738, 202 S.E.2d at 476.
Article 16 requires the parties to arbitrate resolution of their disputes on these larger-
scale construction projects.
Defendant correctly argues the MSA and the Construction Contract must be
read “harmoniously,” where a procedure or remedy is not mentioned nor prohibited
by the MSA, and the court is required to give effect to the provisions of both
agreements. Agreements between the parties must be interpreted together, any
6 BILFINGER INC. V. CARGILL, INC.
dispute between the parties must first be submitted to senior management in
accordance with MSA Section 26, then either party may seek to resolve the dispute
through non-binding mediation, also in accordance with MSA Section 26. Absent
mutual agreement to mediate, the dispute shall be subjected to arbitration in
accordance with Article 16 of the Construction Contract.
The trial court and the majority’s opinion failed to recognize or give effect to
the parties’ express agreement that, “Notwithstanding any other provision of this
Agreement,” a party may only immediately pursue court action in order “to toll the
statutes of limitations or to seek injunctive or equitable relief” pursuant to MSA
Section 26.
Trial and appellate courts must “enforce the parties’ intent as evidenced by the
clear and explicit language of the agreement(s).” Morrell v. Hardin Creek, Inc., 371
N.C. 672, 686, 821 S.E.2d 360, 369 (2018). “Where the terms of a contractual
agreement are clear and unambiguous, the courts cannot rewrite the plain meaning
of the contract.” Internet East, Inc. v. Duro Commc’ns, Inc., 146 N.C. App. 401, 405,
553 S.E.2d 84, 87 (2001) (internal citation omitted). The agreements must be
reviewed and enforced “in a manner that gives effect to all of its provisions, if the
court is reasonably able to do so.” Johnston Cty. v. R.N. Rouse & Co., Inc., 331 N.C.
88, 94, 414 S.E.2d 30, 34 (1992) (internal citation omitted).
C. JRM, Inc. v. HJH Companies, Inc
There is no finding nor conclusion the terms of either contract are ambiguous.
7 BILFINGER INC. V. CARGILL, INC.
The majority’s opinion further compounds this error by relying upon JRM, Inc. v.
HJH Companies, Inc., 287 N.C. App. 592, 598, 883 S.E.2d 217, 221 (2023). This Court
dismissed the appeal because no valid arbitration agreement existed, and no
substantial right was affected. This reliance is contrary to the express and plain
language of the admittedly-valid Construction Contract, not the MSA, which Plaintiff
specifically seeks to enforce, not in arbitration, as contractually required, but in the
trial court. Resorting to the trial court for breach is specifically prohibited in the
MSA, except as specifically allowed therein.
The trial court erroneously concluded as a matter of law, “It is not necessary
for the Court to determine whether the MSA and [the Construction Contract] dispute
resolution provisions conflict because the MSA explicitly states that where a ‘topic’ or
‘remedy’ is addressed in the MSA, then a corresponding topic or remedy in the
[Construction Contract] is null and void.”
The fallacy and prejudicial error therein is neither arbitration as a procedure,
topic, nor remedy is mentioned at all in the MSA and is certainly not specifically
excluded. Where the parties themselves later agreed to and adopted this procedure
as an additional remedy to resolve disputes, it controls. Wood-Hopkins Contracting
Co., 284 N.C. at 738, 202 S.E.2d at 476.
MSA Section 7(d) also specifically provides. “To the extent that a topic is not
addressed or a remedy is not provided for in this Agreement, then the terms of the
[project-specific contract] shall control for that specific topic or remedy.” (emphasis
8 BILFINGER INC. V. CARGILL, INC.
supplied). The trial court also made no findings or conclusions concerning Plaintiff
wrongfully filing claims in court for breach of contract and to foreclose a lien in court,
where those actions are also specifically excluded as a remedy in the MSA Section
7(d) and are specifically prohibited by the agreement to arbitrate in the Construction
Contract. MSA Section 26 expressly limits the parties’ access to the courts:
“Notwithstanding any other provision of this Agreement, each Party is entitled to
immediate access to the courts to: (i) toll any statute of limitation or (ii) seek
appropriate injunctive relief or other equitable remedy if, in such party’s sole
discretion, such action is deemed necessary to avoid irreparable damage or preserve
The trial court and the majority’s opinion errs by giving primacy to a clause
that “addresses a topic” as opposed to the MSA not mentioning a “topic” nor
prohibiting a process or remedy. The trial court and the majority’s analysis also
ignores the plain language of the MSA to expressly limit either parties’ initial access
to the courts under the circumstances specifically stated: “each Party is entitled to
immediate access to the courts to: (i) toll any statute of limitation or (ii) seek
appropriate injunctive relief or other equitable remedy if, in such party’s sole
discretion, such action is deemed necessary to avoid irreparable damage or preserve
the status quo.” The topics and remedies in the contracts are simply not mutually
exclusive.
Plaintiff’s claims being asserted in court also directly violates this specified
9 BILFINGER INC. V. CARGILL, INC.
provision in the MSA, a “Notwithstanding” provision that expressly overrides all
others contained therein. The two agreements contain “no indication” one clause was
to “override” or exclude the other contract provision, where a process and remedy was
not specifically named or excluded, and where express limitations on filing suit for
relief for disputes is available only through specifically agreed-upon arbitration. See
Lowder, Inc. v. Highway Comm., 26 N.C. App. 622, 642, 217 S.E.2d 682, 695 cert.
denied, 288 N.C. 393, 218 S.E.2d 467 (1975).
The trial court and the majority’s opinion prejudicially err in denying
Defendant’s motion to compel arbitration and to dismiss Defendant’s timely appeal.
The decision to dismiss Defendant’s timely appeal is also contrary to the Supreme
Court of the United States’ holding in “Jurisdiction over the appeal, however, ‘must
be determined by focusing upon the category of the order appealed from, rather than
the strength of the grounds for reversing the order.’” Arthur Andersen LLP v.
Carlisle, 556 U.S. 624, 628, 173 L.Ed.2d 832, 838 (2009) (citing Behrens v. Pelletier,
516 U.S. 299, 311, 133 L.Ed.2d 773 (1996)). In other words, even if a litigant actually
has no right to arbitrate and a trial court so determines, the party is still entitled to
an immediate appeal and review on that issue.
IV. Admission of Untimely Second Affidavit
As I vote to address the merits of this timely interlocutory appeal and to
reverse the trial court’s denial of Defendant’s motion to compel arbitration, I also
address the trial court’s error in admitting an untimely affidavit to supplement the
10 BILFINGER INC. V. CARGILL, INC.
record. The trial court also granted Plaintiff’s Motion to Supplement the Record with
an additional untimely affidavit (Second Affidavit), which it had served on Defendant
the night prior to hearing.
North Carolina Rules of Civil Procedure 6(d) requires affidavits in support of
a motion to be served with the motion and, unless as otherwise provided, affidavits
in opposition to a motion must be served at least two days prior to the hearing on the
motion. N.C. Gen. Stat. § 1A-1, Rule 6(d) (2023).
Rule 6(d) further provides:
If the opposing affidavit is not served on the other parties at least two days before the hearing on the motion, the court may continue the matter for a reasonable period to allow the responding party to prepare a response, proceed with the matter without considering the untimely served affidavit, or take such other action as the ends of justice require.
Id. There are no findings or conclusions to support or excuse Plaintiff’s express
violation of Rule 6(d). Id.
The trial court simply stated the Second Affidavit was submitted in purported
response to an argument Defendant had raised in its memorandum opposing
Plaintiff’s Motion to Stay Arbitration. The order is devoid of any basis to deviate from
the stated requirements of Rule 6(d), and it should have been excluded. Id.
V. Conclusion
The trial court committed reversible error in denying Defendant’s motion to
compel and allowing Plaintiff to supplement the Record with the untimely Second
11 BILFINGER INC. V. CARGILL, INC.
Affidavit. The trial court’s order is properly reversed and remanded for entry of an
order allowing Defendant’s motion to compel arbitration and to strike Plaintiff’s
untimely affidavit. The majority’s dismissal of Defendant’s timely appeal is also
erroneous and prejudicial. I respectfully dissent.