Bethlehem Steel Corp. v. United States

511 F.2d 529, 206 Ct. Cl. 122
United States Court of Claims·Decided February 19, 1976·No. No. 44-68·Published·Cited by 8 cases

Opinions

Nichols, Judge,

delivered the opinion of the court:

This case of Wunderlich Act review of a contract dispute under Dispute Clause procedure (41 U.S.C. §§ 321-22) is now before us for the third time. On the first occasion, 191 [125] Ct. Cl. 141, 423 F. 2d 300 (1970), we held that the Armed Services Board of Contract Appeals (ASBCA) had erred as a matter of law in not following certain Armed Services Procurement Regulations (ASPE) we considered applicable to the dispute. After Board preliminary proceedings reported at 71-1 BCA ¶8640, Bethlehem on May 10, 1971, applied to us for an order terminating stay and for other relief. This we denied in an unreported order, without opinion. The Board proceedings then resumed and resulted in the decision now under review, 73-1 BCA ¶9898. We affirm.

Our 1970 decision details the controversy as it had evolved up to that time and we need not repeat it all here. Briefly, Bethlehem had built five Navy destroyers under two fixed price contracts, Nobs-3556 and 3648, both of which contained clauses allowing for labor and material escalation, but enabling the Contracting Officer to deny any upward adjustment thereunder in whole or in part, if he found that it was not required to enable the Contractor to earn a fair and reasonable profit under the contract, Art. 6, Par. (e). After full performance, plaintiff claimed $3,347,000 escalation under Nobs-3556 and $2,404,900 under Nobs-3648. The latter claim has now been allowed by the Board in its entirety and having-been dismissed is not before us for review. The original Board decision allowed $1,064,151 under Nobs-3556 making a total profit of 5% of costs. The Board’s theory was that plaintiff had agreed to a limit of 5%. We were unable to find evidence of agreement to that limit. Further, the Board had determined the level of reasonable profit without reference to the published guidelines of the Department of Defense which told how contract clauses limiting contractors to reasonable profit levels (hereinafter, profit limitation provision) were to be interpreted and applied.

In Newport News Shipbuilding & Drydock Co. v. United States, 179 Ct. Cl. 97, 374 F. 2d 516 (1967), we had already held that in making a profit limitation decision under a Navy contract clause of the same type, the Board had erred in not following published guidelines. On retrial, the Board, as we indicated it should, followed the guidelines enacted after the contract date and before its original decision, hereinafter called the “unweighted guidelines.” It allowed Newport News [126] full escalation, 71-1 BCA ¶8705. The case was settled on that basis. In Bethlehem, the fact appeared that the Department of Defense had superseded the original “unweighted guidelines” with so-called “weighted guidelines”, after the original Board decision hi Newport News and before that in Bethlehem.

Plaintiff in Bethlehem argued for use of the “weighted guidelines” on retrial. Defendant seemed to argue for no guidelines at all, attacking the “weighted guidelines” as unsuitable for the Bethlehem contract even if required for most others. This was because, in defendant’s view, the “weighted guidelines” would fail to allow weight for the fact the Navy had awarded this contract to Bethlehem, though it was a high bidder, to keep its Quincy, Massachusetts facility in the shipbuilding business. At that point, however, defendant indicated no preference for the “unweighted guidelines”.

This issue caused us much concern. Since, in Newport News we had held a guideline regulation to apply to a contract written at an earlier date, when no guidelines existed, it seemed consistent that any further amending or superseding provisions should be applicable likewise, right up to the original Board trial on the facts. This would make the amended or “weighted guidelines” the proper ones to use in the Bethlehem retrial. What happens, however, if the guidelines are amended or modified again, between the original trial and retrial of the issue? In Newport News, apparently by mutual consent, the new guidelines were not given effect at the retrial and the Board used the ones it should have used at the original trial. It was nevertheless obvious to us that this was not the only possible answer.

The determination of a supposedly reasonable level of profit by administrative fiat after the event, and not by operation of the market place, is not an easy operation that anyone can perform. Without guidelines the power to do it confers, as we said in Bethlehem I, a kind of roving absolutism inimical to our institutions (p. 155). In the administration of our most widely used system of profit limitation under Government contracts, the Renegotiation Act of 1951, 50 U.S.C. (App.) § 1191 and ff., and its predecessors back to 1942, the need for guidelines has been recognized from the [127] beginning, almost, and they are provided both in statutory provisions and in regulations. 50 U.S.C. (App.) § 1213(e); 32 C.F.K. § 1460.1 and ií. The ASPE indicated a recognition of the same need, and we were understandably reluctant to believe there could be any profit limitation provisions in Department of Defense contracts, they were not intended to apply to. By the same token, new regulations, we would presume, reflected more extended experience with profit limitation, and would if applied to previously existing contracts, produce a more satisfactory result than previous regulations or no regulations at all. On the other hand, it certainly was possible the authors of regulations might be unaware at times of all the previously awarded contracts remaining unsettled, to which they might apply, and they might obtain unforeseen and undesired results. If this occurred, they should be free to correct their errors.

As we have recently held in Hills Transp. Co. v. United States, 204 Ct. Cl. 51, 492 F. 2d 1394 (1974) whether, in the absence of express provision, a procurement regulation can have retroactive application to a contract earlier awarded, is not to be decided by any wooden rules, but by reference to the character and intent of the contract and of the regulation involved. Here, factors favoring retroactive application are the long lapse of time under these shipbuilding contracts, between original award and final settlement, and the remedial effect of a guideline regulation, any regulation, as against the assignment of a “roving absolutism” to a Contracting Officer in granting or denying escalation.

In view of the foregoing considerations we deemed it unwise to nail defendant inescapably to the mast of the “weighted guidelines” method. While stating that as things were, plaintiff was entitled to use of that method on retrial, we held that even then, defendant could make a retroactive change in the method. Our words, as reported, were as follows:

Free access — add to your briefcase to read the full text and ask questions with AI

Bethlehem Steel Corp. v. United States, 511 F.2d 529, 206 Ct. Cl. 122 (cc 1976).

511 F.2d 529 (Bethlehem Steel Corp. v. United States) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Holloway Construction Co. v. United States
32 Cont. Cas. Fed. 72,389 (Court of Claims, 1984)
Harold J. Sullivan v. Department of the Navy
720 F.2d 1266 (Federal Circuit, 1983)
Ryder v. United States
585 F.2d 482 (Court of Claims, 1978)
Coast Indian Community v. United States
550 F.2d 639 (Court of Claims, 1977)
Aero Spacelines, Inc. v. United States
530 F.2d 324 (Court of Claims, 1976)
Doggett v. United States
207 Ct. Cl. 478 (Court of Claims, 1975)
Mason & Hanger-Silas Mason Co. v. United States
518 F.2d 1341 (Court of Claims, 1975)