Besmehn v. Pacific Coast Shipping Co. Monrovia

632 P.2d 454, 53 Or. App. 384, 1981 Ore. App. LEXIS 2978
CourtCourt of Appeals of Oregon
DecidedAugust 3, 1981
DocketNo. A7708-11770, CA 14091
StatusPublished

This text of 632 P.2d 454 (Besmehn v. Pacific Coast Shipping Co. Monrovia) is published on Counsel Stack Legal Research, covering Court of Appeals of Oregon primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Besmehn v. Pacific Coast Shipping Co. Monrovia, 632 P.2d 454, 53 Or. App. 384, 1981 Ore. App. LEXIS 2978 (Or. Ct. App. 1981).

Opinion

GILLETTE, P. J.

Plaintiff Besmehn is a longshoreman who was injured while unloading steel from the defendant Pacific Coast Shipping Company’s ship, the Pacmonarch. Defendant-appellant Schnitzer Steel Products Co. (Schnitzer) is the owner of the dock at which the vessel was berthed at the time and is the consignee of the cargo being unloaded. Third party defendant Brady-Hamilton Stevedore Company (Brady) was hired by Pacific Coast to unload the Pacmonarch. It was plaintiff’s employer at the time of the accident. Plaintiff sued Pacific Coast and Schnitzer for negligence, claiming that the defendants were negligent in failing to use certain dockside cranes, as opposed to cranes located on the ship, for unloading the cargo. Schnitzer filed a third-party complaint against Brady, claiming that if Schnitzer was liable to plaintiff, the liability was caused by Brady’s negligence. The jury found that the defendant Pacific Coast was not at fault, that Schnitzer was 35 percent at fault, that Brady was 51 percent at fault and that plaintiff was 14 percent negligent. Judgment was entered against defendant Schnitzer for $129,000.1 Schnitzer appeals; we affirm.

The only parties to the appeal are plaintiff Besmehn and defendant Schnitzer. Schnitzer claims that the trial court erred in denying its motions for an involuntary nonsuit, for a directed verdict and for judgment notwithstanding the verdict because Schnitzer, in its capacity as owner of the dock and consignee of the cargo, owed no duty to plaintiff to provide dockside cranes for discharge of the cargo. Alternatively, Schnitzer contends that, even if it had such a duty, there is no evidence that it was in breach of [387]*387that duty in this case. In considering defendant’s contention, "we view the evidence in the light most favorable to the prevailing party and give that party the benefit of all reasonable inferences that may be drawn from the evidence.” Davis v. Portland General Electric Co., 286 Or 195, 197, 593 P2d 1135 (1979). The relevant facts are as follows:

Pacific Coast Shipping Company (Pacific Coast) entered into a contract with Schnitzer to carry steel for Schnitzer from Japan to Portland. According to the agreement, the vessel was on "berth terms.” This means that the Pacmonarch had the responsibility both to load and unload the cargo. Through its management agent in Portland, Lasco Shipping, Pacific Coast hired Brady, an independent contractor, to unload the cargo from the Pacmonarch. Plaintiff was one of the longshoremen Brady hired to do the work. Schnitzer owned the cargo carried by the Pacmonarch and unloaded by Brady’s employes. Schnitzer also owned and controlled the dock where the Pacmonarch was berthed and the "whirly” (dockside) cranes located on the dock.

The Pacmonarch is equipped with a type of crane known as a Munck crane. It consists of a metal beam suspended by two legs which are mounted on tracks running the length of the ship. The beam itself runs across the ship. Attached to the beam is a metal structure known as a head block. The head block moves across the beam from a point over the hatch or hold, where the ship’s cargo is located, to a point over the dock. An operator sits in a control bubble on the underside of the head block and from that point controls the lifting gear, also located on the block. The lifting gear is lowered into the hold, picks up the cargo and then carries the cargo over and onto the dock.

On the day in question, plaintiff and another longshoreman were in one of the Pacmonarch’s holds unloading steel pipe. The pipe, which was 20 feet long and four inches in diameter, was being hoisted out in bundles of approximately 10 to 12 pipes. The usual procedure for unloading the bundles of pipe in such cases is described as follows: Two men stand at opposite ends of the pipe. As the crane’s lifting gear is lowered into the hold, each man grabs one of the slings attached to the lifting gear and wraps the [388]*388sling around his end of the bundle of pipe. Once the slings are in place, the operator of the crane picks the load up slowly to set the slings tight. The men in the hold then move out of the way and the load is hoisted out.

The slings and the load form a triangle with the hook of the crane’s lifting gear at the apex, the bundle of pipe as the base (which may extend outside the slings) and the slings as the sides. On the day of the injury, the fourth load of pipe was ready to be lifted from the hold in which plaintiff was working. As the operator started to move the load, the sling on plaintiff’s side of the bundle slipped toward the other end of the bundle, causing the ends of the pipes nearest plaintiff to flare out and hit him. The plaintiff was knocked down by the blow and suffered a fractured leg.

The safety and use of the Munck crane to unload bundles of steel pipe, as compared to the "whirly” crane, was subject to testimony at trial. Because of the design of the Munck crane, the amount of "drift” or clearance the crane has when lifting cargo is only about 15 to 20 feet. The "drift” is the distance between the point at which the cargo comes out of the hatch and the greatest height to which it can be lifted by the crane. As a result of this limited clearance when a Munck crane is used, the slings that are used are short and a severe angle of attachment of the slings to the load is created. Thus, the possibility exists that the slings can slide into the middle of the load. In contrast to the Munck crane, the dockside crane has unlimited clearance. Dockside cranes run on tracks located on the dock and alongside the vessel. They allow longer slings and a device known as a spreader bar to be used when lifting bundles of pipe. The severe angle created when the Munck crane and short slings are used is eliminated and the spreader bar keeps the slings separated so they cannot slip together.

The Brady employes who were on the job the day plaintiff was injured testified that they were aware of the dangers of the Munck crane and felt that it would have been safer to use the dockside cranes. Walter Smith, Brady’s safety engineer, testified that he discussed the problems and hazards of using the Munck crane with the [389]*389longshoremen’s union business manager and that he and the manager then discussed the matter with Herbert Fear, the person responsible for supervising the loading and unloading activities on the dock for Schnitzer. Smith stated that he told Fear that using the Munck cranes to unload the steel was unsafe and that he, Smith, was concerned about someone getting hurt. Smith indicated that he asked Fear to discontinue using the Munck crane and to allow use of the dockside cranes. According to Smith, Fear agreed that the dockside cranes would be better, but he declined to switch because use of the dockside cranes would make it difficult to use the Munck cranes in the ship’s other hatches later and because it was company policy to use the cranes on the ship. Jack Grohs, the walking boss (foreman) on duty that day for Brady, testified that he also asked Fear if the dockside cranes could be used, but Fear refused, indicating that the company wanted the ship’s cranes to be used.

Fear testified that he is a superintendent in charge of scrap iron loading and steel discharging for Schnitzer. On the day of the accident, he was on the dock to assist the stevedore, Brady, in discharging the steel. Fear admitted that he talked with Smith and the business manager and that they asked to use the dockside cranes.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Executive Jet Aviation, Inc. v. City of Cleveland
409 U.S. 249 (Supreme Court, 1972)
Davis v. Portland General Electric Co.
593 P.2d 1135 (Oregon Supreme Court, 1979)
Oksenholt v. Lederle Laboratories
625 P.2d 1357 (Court of Appeals of Oregon, 1981)
Brennen v. City of Eugene
591 P.2d 719 (Oregon Supreme Court, 1979)
Shepler v. Weyerhaeuser Co.
569 P.2d 1040 (Oregon Supreme Court, 1977)

Cite This Page — Counsel Stack

Bluebook (online)
632 P.2d 454, 53 Or. App. 384, 1981 Ore. App. LEXIS 2978, Counsel Stack Legal Research, https://law.counselstack.com/opinion/besmehn-v-pacific-coast-shipping-co-monrovia-orctapp-1981.