Berthold v. St. Louis Electric Construction Co.

65 S.W. 784, 165 Mo. 280, 1901 Mo. LEXIS 274
CourtSupreme Court of Missouri
DecidedNovember 26, 1901
StatusPublished
Cited by12 cases

This text of 65 S.W. 784 (Berthold v. St. Louis Electric Construction Co.) is published on Counsel Stack Legal Research, covering Supreme Court of Missouri primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Berthold v. St. Louis Electric Construction Co., 65 S.W. 784, 165 Mo. 280, 1901 Mo. LEXIS 274 (Mo. 1901).

Opinion

GANTT, J.

In June, 1897, the St. Louis Electric Construction Company was desirous of purchasing a quantity of poles suitable for stringing telephone wires, and accordingly advertised for proposals to furnish them, inviting bids according to the specifications prepared by it.

The firm of Berthold & Jennings, the plaintiffs, were the successful bidders, and on June 21, 1897, said electric company and Berthold & Jennings entered into a written contract to which the specifications upon which the bids were made, were annexed and made part of the contract.

As the stipulations of the contract are constantly invoked by counsel to maintain their several contentions, it will be well to state the substance thereof.

By the contract and specifications, Berthold & Jennings agreed to furnish and deliver to the construction company on or before the twenty-first day of February, 1898, the materials set forth in the specifications, namely, white cedar' poles of the following dimensions and approximate number, to-wit:

[287]*287Eor the poles so to be delivered, the construction company agreed to pay Berthold & Jennings as follows:

Eor poles 35 feet long......................$ 3.74 each.
Eor poles 40 feet long...................... 4.78 each.
Eor poles 45 feet long...................... 6.11 each.
Eor poles 50 feet long...................... 12.65 each.
Eor poles 55 feet long...................... 13.53 each.
Eor poles 60 feet long...................... 20.18 each.
Eor poles 65 feet long...................... 25.85 each.

Payment for each month’s delivery was to be made on the tenth of the month following the delivery.

The specifications provide that the “poles shall be of the best quality straight-grained white cedar, free from large or loose knots, checks and twists. They shall be straight, well proportioned from top to butt, the bark shall be entirely peeled, and the poles shaved in a neat and workmanlike manner from the top to a distance from the butt specified in the table hereinafter shown,” and shall “be furnished and delivered f. o. b. cars, in the company’s yards, at St. Louis, Missouri.

“The company will have a duly-appointed inspector at point of shipment, and the contractor shall not ship any material objected to by the inspector.
“The final inspection will take place at St. Louis, as material is unloaded from the cars, and if any pole is damaged in transit, it will be replaced by the contractor.
“Payment will be made on the report of the final inspectional at St. Louis. The payments will be made on the tenth of the month following the delivery, less ten per cent, which shall be retained until the contract has been completed, when it shall become due if the work has been fulfilled to the satisfaction of the general manager and chief engineer of the company.
“A bond for $25,000, satisfactory to the company, shall be furnished by the contractor.”

[288]*288The contract contained the following special provisions:

“The delivery shall begin within sixty days after the award of the contract and continue uninterruptedly and be completed six months after said sixty days. The class of poles to be shipped from time to time, shall be as ordered by the chief engineer of the company.
“The said party of the second part shall give his personal attention to the work and not sublet the same or any part thereof without the written consent of the party of the first part.
“Failure to comply with this stipulation or carry on the work as herein required either as to the rate of progress or otherwise shall be deemed a breach of this contract if the party of the first part shall so elect and any and all damages resulting therefrom shall be paid for by the said party of the second part.”

Also this provision:

“It is hereby mutually agreed and expressly understood that the said party of the first part shall have the right to suspend the execution of this contract and to annul the same whenever the said party of the second part shall fail to carry out the worlc with a satisfactory rate of progress or comply with all and singular the terms and stipulations as herein set forth and that such suspension or annulment shall not affect the right of the party of the first part to recover any of the damages resulting from such failure.”

Berthold & Jennings gave the bond required by the specifications and at once took steps to carry out their contract.

Among other things, they entered into contract with the Northern Supply Company, of Chicago, to obtain from it the poles which they had agreed to deliver to the construction company. The specifications in their contract with the Northern Supply Company are in the exact language of the specifications in the contract between themselves and the construction company, and require the Northern Supply Company to furnish to [289]*289Berthold & Jennings, delivered at St. Louis, all the poles which the latter had contracted to deliver to the construction company except the 225 poles of 60 feet and 35 poles of 65 feet, of which it agreed to furnish one-half.

Trees from which the poles called for by the contract are made, grow only in Michigan, Canada and some in Wisconsin and Minnesota. There is no market for poles in St. Louis. They are not carried in stock there.

On the second of July, 1897, Berthold & Jennings notified the construction company to have its inspector report at the office of the Northern Supply Company, in Chicago, July 5, to Mr. Koss, saying: “Mr. Koss will go with him and give him all instructions regarding inspection of the poles. Their headquarters will be Eisher, Michigan.”

Upon receiving this notice, Mr. Ledlie, appellant’s chief engineer, instructed Mr. Brennecke, one of the company’s inspectors, then at Toledo, to report to Mr. Koss, in Chicago, which the inspector did on the morning of July 6. BEe went from there to Eisher, Michigan, where the Northern Supply Company was collecting the poles.

On July 14, Mr. Máxime Reber, the assistant engineer, got from Mr. Jennings letters of introduction to Mr. Eaithorn, the president, and Mr. Bagley, the manager, of the Northern Supply Company. BEe presented both letters and spent July 17 at Eisher. The letters introduced him as engineer of the St. Louis Electrical Construction Company, “who get the poles you are getting out for us on recent contract.” Mr. Reber on that date left with Bagley a memorandum or shipping order for the entire 5,000 poles, covered by plaintiffs’ and defendants’ contract, herein sued on.

The first shipment was made on the seventeenth day of July. On the twentieth day of July Mr. Jennings, one of the firm of plaintiffs, requested Mr. Ledlie, the chief engineer of defendant, to give him the orders for the poles and Ledlie re[290]*290plied he would send the orders up there; that he preferred to send the orders to the inspectors at Eisher, Michigan, and let them order them.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Diehr v. Thompson Chemicals Corp.
281 S.W.2d 572 (Missouri Court of Appeals, 1955)
United Brick & Tile Co. v. Ault
123 S.W.2d 39 (Supreme Court of Missouri, 1938)
Burns v. Reis
191 S.W. 1096 (Missouri Court of Appeals, 1917)
El Paso Milling Co. v. Davis
183 S.W. 361 (Missouri Court of Appeals, 1916)
Chas. E. & W. E. Peck, Ltd. v. Southwestern Lumber & Exporting Co.
59 So. 113 (Supreme Court of Louisiana, 1912)
Clark v. Asbury
134 S.W. 286 (Court of Appeals of Texas, 1911)
Schatzinger v. Lake View Land & Improvement Co.
23 Ohio C.C. Dec. 247 (Cuyahoga Circuit Court, 1910)
Manzke v. Goldenberg
129 S.W. 32 (Missouri Court of Appeals, 1910)
Laswell v. National Handle Co.
126 S.W. 969 (Missouri Court of Appeals, 1910)
Brown v. Trinidad Asphalt Manufacturing Co.
109 S.W. 22 (Supreme Court of Missouri, 1908)
Walker v. Grout Bros. Automobile Co.
102 S.W. 25 (Missouri Court of Appeals, 1907)
Worrell v. Kinnear Manufacturing Co.
49 S.E. 988 (Supreme Court of Virginia, 1905)

Cite This Page — Counsel Stack

Bluebook (online)
65 S.W. 784, 165 Mo. 280, 1901 Mo. LEXIS 274, Counsel Stack Legal Research, https://law.counselstack.com/opinion/berthold-v-st-louis-electric-construction-co-mo-1901.