Bern v. Boston Consolidated Gas Co.

39 N.E.2d 576, 310 Mass. 651, 1942 Mass. LEXIS 632
CourtMassachusetts Supreme Judicial Court
DecidedJanuary 27, 1942
StatusPublished
Cited by23 cases

This text of 39 N.E.2d 576 (Bern v. Boston Consolidated Gas Co.) is published on Counsel Stack Legal Research, covering Massachusetts Supreme Judicial Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Bern v. Boston Consolidated Gas Co., 39 N.E.2d 576, 310 Mass. 651, 1942 Mass. LEXIS 632 (Mass. 1942).

Opinion

Cox, J.

This is an appeal from the order of the Appellate Division for the Northern District dismissing the report of the trial judge, who found for the defendant on the ground stated that it was not negligent. The first count of the plaintiff’s declaration is for negligence, the second is for a nuisance based upon the violation of G. L. (Ter. Ed.) c. 164, § 70, and the third is for nuisance in that the defendant unlawfully made an excavation in a public way.

There was evidence that at about 10:40 a.m. on Saturday, December 30, 1939, a service man of the defendant went to a house where it had been notified that gas was leaking. Some time later in the morning the matter was referred to the defendant’s main office, and, before noon, the defendant began to dig a trench in one of the public streets of Newton, and found a leak in the gas main that constituted a dangerous condition. The defendant neither sought nor obtained any permit to open the trench. The city hall was closed from noon on Saturday until the Tuesday following. The main was repaired, and the defendant “back-filled” the trench on January 3. At about 12:30 a.m. on January 15, when it was raining very hard and had been raining for hours, the plaintiff sustained injuries when the automobile that he was operating went into a hole that was two feet by two feet in area and one foot in depth around which there were no safeguards. Although the evidence does not so state, the parties have assumed, and the trial judge found, that this hole was where the defendant had excavated some two weeks before. Although the surround[653]*653ing surface of the street was macadam, the trench surface was sand and gravel. The trial judge found that it was too late on the Saturday when the leak was discovered for the defendant to get a permit from the city to dig the trench, that it was impossible for it to get one before Tuesday morning, January 2, and that the leaking gas created an emergency that required immediate attention. He made no finding as to the time when the trench was filled, beyond stating that this was done after the main had been repaired. He stated that there was no evidence before him as to how the trench was dug or how it was filled. He also found that the hole had been there only a few hours, and that it was the “torrential” downpour of rain that caused a portion of the trench to settle. The report states that it contains all the evidence material to the question reported.

The trial judge refused to give several of the plaintiff’s requests for rulings, and in each instance gave his reasons therefor. We are of opinion that there was error as to the second request, and, inasmuch as there must be a new trial and as the consideration of this second request necessarily deals with some of the questions involved in the other requests, it is unnecessary to consider them.

The second request was that there was evidence to warrant a finding for the plaintiff. The judge denied this request “because . . . [he found] as a fact that the. defendant was not negligent.” It is unnecessary to consider whether the request comes within the purview of Rule 27 of the District Courts (1940), requiring specification. It was reviewed by the Appellate Division and is before this court on this appeal. Milmore v. Landau, 307 Mass. 589, 590, and cases cited. The request was proper, and it was error to deny it, unless, as matter of law, it was inapplicable, or unless the judge, by clear and definite findings, has demonstrated that it was inapplicable or immaterial because of the findings. Home Savings Bank v. Savransky, 307 Mass. 601, 603, 604, and cases cited. Where, as here, the plaintiff alleged as one ground of recovery that the defendant had created a nuisance that caused the plaintiff’s injuries, it is apparent that the reason given by the trial judge for the [654]*654refusal of this request, that is, that the defendant was not negligent, was not sufficient if there was evidence of the creation of a nuisance that caused the injuries. Furthermore, the general finding for the defendant does not go to the extent of curing an error in the refusal of such a request. Home Savings Bank v. Savransky, 307 Mass. 601, 605-606. It is to be observed again that the finding for the defendant is predicated upon the finding that it was not negligent. In the absence of any finding as to the existence or nonexistence of a nuisance, it cannot be said on this record that the trial judge has demonstrated that the second request was inapplicable or immaterial. Compare Himelfarb v. Novadel Agene Corp. 305 Mass. 446, 448, and cases cited. A nuisance may exist without negligence. Ferriter v. Herlihy, 287 Mass. 138, 143.

General Laws (Ter. Ed.) c. 164, § 70, provides, in substance, that a gas company may, with the written consent of the aldermen or selectmen, dig up and open the ground in the ways of a town, so far as necessary to accomplish its objects, but that such consent shall not affect the right or remedy to recover damages for an injury caused to persons or property by its acts; that it shall put all such ways in as good repair as they were in when opened; and that upon failure so. to do within a reasonable time it shall be guilty of a nuisance. The evidence disclosed that the trench was not filled by the defendant until Wednesday, January 3, and that this work was not completed until 2:30 p.m. on that day. The inference is warranted that during the time that this work was in progress, a permit could have, been procured if, as we do not decide, it then would have availed the defendant. The judge had the question of nuisance, squarely presented, inasmuch as four requests, posited upon nuisance, were refused on the ground that an emergency had arisen which justified the defendant in digging the trench without a permit. The reasons given - for the refusal of these requests, involving as.they do a finding that an emergency had. arisen and that therefore the defendant was justified in..digging the trench without a permit,. do not cure any, possible error in the refusal to give the second [655]*655request, for it is to be observed that the statute in question, which allows the opening of ways upon permit, also provides that, unless the person who opens the ways puts them in as good repair as they were in when opened, he shall be guilty of a nuisance. The plaintiff had the burden of showing the existence of a nuisance. Hunt Drug Co. v. Hubert, 298 Mass. 195, 196. No permit was obtained, and we may assume, without deciding, that the circumstances were such that the defendant could dig the trench without obtaining a permit. See Commonwealth v. Brooks, 99 Mass. 434; Herman v. Sladofsky, 301 Mass. 534, 538, 539. But whether the defendant had a permit or not, it was at least required to restore the way to the condition it was in before the excavation, Seltzer v. Amesbury & Salisbury Gas Co. 188 Mass. 242, and, apart from the question of any right under a permit, our attention has been called to no provision of law that would allow the defendant to create a nuisance in a public way. There was evidence that, although the surface of the street in question “about the place of the defect was a macadam road,” the trench surface was sand and gravel. Furthermore, although there was evidence that this was the condition of the street when the plaintiff was injured on January 15, it also appeared that the work of refilling the trench had been completed twelve days before.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Woods v. Brimm
27 Mass. L. Rptr. 389 (Massachusetts Superior Court, 2010)
Couture v. Carlo Molinari, Inc.
25 Mass. L. Rptr. 140 (Massachusetts Superior Court, 2009)
St. Elizabeth's Hospital v. Crane
1981 Mass. App. Div. 260 (Mass. Dist. Ct., App. Div., 1981)
Nelson v. Judd
49 Mass. App. Dec. 14 (Mass. Dist. Ct., App. Div., 1972)
Moran v. Tello
47 Mass. App. Dec. 62 (Mass. Dist. Ct., App. Div., 1971)
Riley v. New England Telephone & Telegraph Co.
234 N.E.2d 746 (Massachusetts Supreme Judicial Court, 1968)
Mealey v. Camuso
30 Mass. App. Dec. 79 (Mass. Dist. Ct., App. Div., 1964)
Votour v. City of Medford
12 Mass. App. Dec. 45 (Mass. Dist. Ct., App. Div., 1956)
Marshall v. Francis
124 N.E.2d 803 (Massachusetts Supreme Judicial Court, 1955)
Morgan v. High Penn Oil Co.
77 S.E.2d 682 (Supreme Court of North Carolina, 1953)
Simons v. Murray Realty, Inc.
112 N.E.2d 264 (Massachusetts Supreme Judicial Court, 1953)
Furnari v. Chianciola
14 Mass. App. Div. 147 (Massachusetts District Court, 1949)
Larson v. New England Telephone & Telegraph Co.
44 A.2d 1 (Supreme Judicial Court of Maine, 1945)
Woodbury v. Municipal Council
61 N.E.2d 647 (Massachusetts Supreme Judicial Court, 1945)
Hennessey v. Aloisi
10 Mass. App. Div. 77 (Mass. Dist. Ct., App. Div., 1945)
Sullivan v. Boston Consolidated Gas Co.
55 N.E.2d 608 (Massachusetts Supreme Judicial Court, 1944)
Brodeur v. Seymour
53 N.E.2d 566 (Massachusetts Supreme Judicial Court, 1944)
United Electric Light Co. v. Deliso Construction Co.
52 N.E.2d 553 (Massachusetts Supreme Judicial Court, 1943)
Rummel v. Peters
51 N.E.2d 57 (Massachusetts Supreme Judicial Court, 1943)
Perry v. Hanover
50 N.E.2d 41 (Massachusetts Supreme Judicial Court, 1943)

Cite This Page — Counsel Stack

Bluebook (online)
39 N.E.2d 576, 310 Mass. 651, 1942 Mass. LEXIS 632, Counsel Stack Legal Research, https://law.counselstack.com/opinion/bern-v-boston-consolidated-gas-co-mass-1942.