Berkshire Land Co. v. Moran

177 N.W. 205, 210 Mich. 77
CourtMichigan Supreme Court
DecidedApril 10, 1920
DocketDocket No. 8
StatusPublished
Cited by2 cases

This text of 177 N.W. 205 (Berkshire Land Co. v. Moran) is published on Counsel Stack Legal Research, covering Michigan Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Berkshire Land Co. v. Moran, 177 N.W. 205, 210 Mich. 77 (Mich. 1920).

Opinion

Steere, J.

Plaintiff is an incorporated land company owning a subdivision in Crosse Pointe Park village traversed by a dedicated thoroughfare known as the Yorkshire highway. On March 25, 1916, it en[79]*79tered into a written contract with defendant Moran to pave said Yorkshire highway according to plans and specifications attached to and made a part of said contract. By the terms of this contract Moran was required to furnish a bond for its faithful performance and such bond of even date therewith was attached to the contract, defendant Fidelity & Deposit Company being surety thereon.

The specifications made a part of this contract required the work to be commenced on or before April 1, 1916, and completed within 120 days, or by August 1, 1916. Moran commenced préparation for the work early in April, that first required being certain rough grading, for which a steam shovel was obtained after some delay and put upon the job. Its work was finished in two or three weeks. Following this the work lagged and it is claimed comparatively little more was accomplished. In August, 1916, Moran threw up the contract and ceased all efforts, owing, as he testified, to his resources being exhausted. The first notice to the insurance company that he had failed in performance and was in default is dated August 80, 1916, to which no immediate reply was made. A second letter, dated September 9th, was sent the surety company referring to the first and saying in part:

“If it becomes necessary to relet the work, this action ought to be taken in the near future in order to prevent our client being put to the loss of having the property unimproved during the winter.”

'Under date of September 11th the surety company acknowledged the receipt of these letters, stating the. matter had been referred to its Detroit agent; and on October 7, 1916, its special agent wrote plaintiff that it would not exercise any right which it might have to complete the contract. On receipt of such notice plaintiff sought to obtain bids for its completion from [80]*80all available contractors, many of whom were unwilling to bid under the then uncertain conditions as to cost of labor and material, but on October 26, 1916, a bid was received from a responsible contractor named Cook followed by a contract with him to complete the contract according to the original plans and specifications at an increased cost, as plaintiff claimed, of over $9,000 more than Moran's contract price. Cook eventually completed the work according to agreement and was paid in full by plaintiff.

This action was brought in the circuit court of Wayne county against Moran and his surety to recover damages resulting from delay and additional cost of completing the contract as to which he defaulted, Upon the trial a verdict was directed by the court in favor of the defendant surety company on the ground that plaintiff had failed to comply with the conditions of Moran’s bond requiring prompt notice to the surety of his failure to complete his contract, and the jury was instructed as to Moran’s liability that plaintiff was entitled to a verdict in an amount somewhere between a minimum of $5,000 and a maximum of $9,455.48, which was submitted for the determination of the jury within those limits and a verdict was rendered against Moran for $6,080.48, and judgment entered accordingly.

Plaintiff thereafter removed the case to this court for review on numerous assignments of error which, as stated in its counsel’s brief, involve for consideration the two questions:

“1. Whether the fact that plaintiff did not notify the surety company immediately after August 1st that Moran had not completed the contract discharged the surety. * * *
“2. Whether the verdict against Moran could under the testimony have been for any sum less than $9,494.48, the amount paid by plaintiff in excess of what it would have been obliged to pay Moran.”

[81]*81The main contention is over the first question, to which the briefs of counsel are largely devoted. The trial court directed a verdict for the Fidelity & Deposit Company on the ground that it appeared by the undisputed testimony that plaintiff first breached the bonding contract by neglecting to seasonably notify the surety of Moran’s default, which was a condition precedent to its recovery.

The bond is in the sum of $25,000, runs to the Berkshire Land Company, called the “owner,” recites in the instrument that it is given by Moran as “principal” and the Fidelity & Deposit Company called the “surety.” It is conditioned in customary phraseology on the principal faithfully performing the described paving contract according to its terms, and is expressly made subject to certain stated conditions precedent and provisions, the material portions of which are as follows:

“1. The owner, as a condition precedent to any recovery hereunder, shall faithfully perform all the terms, covenants and conditions set forth in said contract and in this bond, or in either of them, to be performed by the owner at the time and in the manner specified.
“2. The owner shall notify the surety by registered letter, addressed and mailed to the surety at its home office in Baltimore, Maryland, of any breach of said contract by the principal, or any act or omission of the principal, or of any agent or employee of the principal which may involve or cause a loss for which the surety may be liable, immediately after which breach or act or omission shall have come to the knowledge of the owner or any representative of the owner authorized to supervise the performance of said contract and if the principal abandons said contract or is lawfully compelled by reason of a default to cease operations thereunder the surety shall have the right at its option to assume the contract and to sublet or complete the same.”

[82]*82The agreed date for completion of this contract was 120 days after April 1st which, accepting plaintiff’s computation, was August 1, 1916. The undisputed evidence is that the contractor not only failed to complete the work within the contract time, but totally failed to subsequently perform his agreement at a later time, as urged to do by plaintiff’s agent without the surety’s knowledge, or consent to an extension of time. Plaintiff had covenanted with the surety that in the event of the contractor’s. breach of his contract, or if he was guilty of any act or omission “which may involve or cause a loss for which the surety may be liable,” it would immediately after such “breach, act or omission came to its knowledge or that of any representative,” notify the surety by registered mail. That this was not done within the plain meaning and intent of the condition precedent so requiring, is conclusively shown by plaintiff’s own testimony. In a case closely analogous, which was referred to by the trial court in directing a verdict for the surety, it is said:

“The plaintiff failed to keep his covenant before the surety company had in any way failed to comply with those which it had made. On this account, he cannot enforce the fulfillment of the covenant of the defendant. He who commits the first substantial breach of a contract cannot maintain an action against the other contracting party for a subsequent failure on his part to perform.” (Citing many cases.) National Surety Co. v. Long, 60 C. C. A. 623, 125 Fed. 887.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

People v. Gordon
221 N.W.2d 600 (Michigan Court of Appeals, 1974)
MacNear v. Malow
276 N.W. 433 (Michigan Supreme Court, 1937)

Cite This Page — Counsel Stack

Bluebook (online)
177 N.W. 205, 210 Mich. 77, Counsel Stack Legal Research, https://law.counselstack.com/opinion/berkshire-land-co-v-moran-mich-1920.