Berkeley Cement, Inc. v. Regents of the Univ. of Cal.

242 Cal. Rptr. 3d 252, 30 Cal. App. 5th 1133
CourtCalifornia Court of Appeal, 5th District
DecidedJanuary 7, 2019
DocketF073455; F073586
StatusPublished
Cited by18 cases

This text of 242 Cal. Rptr. 3d 252 (Berkeley Cement, Inc. v. Regents of the Univ. of Cal.) is published on Counsel Stack Legal Research, covering California Court of Appeal, 5th District primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Berkeley Cement, Inc. v. Regents of the Univ. of Cal., 242 Cal. Rptr. 3d 252, 30 Cal. App. 5th 1133 (Cal. Ct. App. 2019).

Opinion

HILL, P.J.

*1137Plaintiff Berkeley Cement, Inc. (Berkeley) appeals from the judgment entered against it after a jury trial in this dispute over construction of a building on the Merced campus of the University of California. Berkeley contends the jury's findings on the complaint and on the cross-complaint were fatally inconsistent; the trial court incorrectly instructed the jury that a particular specification in the parties' contract was a performance specification, rather than a design specification, based on an incorrect interpretation of the contract; the trial court improperly cut off plaintiff's cross-examination of a key witness before it was complete; the trial court improperly excluded relevant evidence on the issue of damages after holding a hearing on its admissibility; and the trial court erred in including expert witness fees and mediation fees in its award of costs to defendant. We conclude the expert witness fees were improperly included in the award of costs, but no other error in the judgment has been demonstrated. We modify the judgment to exclude the award of expert fees and affirm.

FACTUAL AND PROCEDURAL BACKGROUND

Defendant Regents of the University of California (University) requested bids for construction of a social sciences and management building (SSMB) on University's Merced campus. Berkeley submitted the *255low bid for the structural concrete work and was granted the contract. To create an attractive, energy efficient, and long-lasting structure, the plans and specifications called for a cast-in-place concrete building. Because the building was designed with architecturally exposed concrete, that is, areas exposed to view where the concrete itself was the finished surface of the building, the design specifications required a high quality concrete finish. They required the use of self-consolidating concrete in the architecturally exposed elements. They specified the aggregate (rock) to be used in the concrete in order to achieve a consistent color, and set a standard requiring minimization of the "bug holes" (voids in the concrete surface created by air pockets) in the architectural concrete.

When self-consolidating concrete was used to construct walls and columns, the construction required erection of formwork into which the concrete was poured. The contract documents required Berkeley to prepare mock-ups prior to pouring the walls and columns in place, to "permit verification of workmanship and visual qualities of the final completed installation." The architectural finish of the concrete was affected by the concrete mix, the formwork, and the placement of the concrete in the formwork.

Problems arose, delaying Berkeley's performance. The aggregate specified in the contract documents was not immediately available, and Berkeley used *1138a substitute, which was later approved by University. Mock-ups were rejected by University; the concrete in the mock-ups exhibited bug holes excessive in quantity and size, rock pockets, discoloration, striations or "tiger striping," and honeycombing. Berkeley also experienced formwork "blowouts," where the formwork broke and the wall had to be redone. There was evidence the formwork Berkeley rented from its initial supplier was not designed for the pressures exerted by the self-consolidating concrete, which were higher than those exerted on formwork by conventional concrete.

Because of these and other difficulties, the concrete work fell behind schedule. Eventually, Berkeley engaged a subcontractor to provide and install formwork, in lieu of the rented and self-installed formwork it used initially. Additionally, University permitted Berkeley to complete the project using flowable conventional concrete, with which Berkeley was more familiar, instead of the self-consolidating concrete called for in the contract. Construction of the building was completed, and University paid Berkeley the full contract price for its work.

Berkeley submitted a Claim for Equitable Adjustment against University, seeking compensation for work it performed, which it claimed was extra work outside the contract. University denied the claim. Berkeley filed this action, alleging causes of action for breach of contract, breach of the implied covenant of good faith and fair dealing, and breach of the implied covenant of the correctness of the plans and specifications. It sought to recover compensation for alleged extra work and delays in construction, which it blamed on defective specifications for the concrete mix and University's alleged interference with Berkeley's performance by improperly rejecting its proposed concrete mix design, shop drawings, and mockups. University cross-complained against Berkeley for breach of contract, alleging the architectural concrete finish of the building did not meet the contract standards for uniformity of color and lack of bug holes, and Berkeley did not perform within the contract time, causing University to incur additional expenses.

*256After a lengthy jury trial, the jury found University did not breach the contract or either of the implied covenants; on the cross-complaint, it found Berkeley breached the contract, but University was not harmed by the breach. Berkeley's motion for judgment notwithstanding the verdict or for a new trial was denied. The trial court awarded costs to University. Berkeley appeals, challenging the judgment against it on its complaint and certain costs awarded.1

*1139DISCUSSION

I.-IV.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Reyes-Gonzalez v. Color Marble CA2/7
California Court of Appeal, 2026
Romero v. The F.A. Barlett Tree Expert Co. CA2/7
California Court of Appeal, 2025
Banda-Wash v. Wash CA5
California Court of Appeal, 2025
Gogal v. Deng
California Court of Appeal, 2025
Mallon v. Hologic CA6
California Court of Appeal, 2025
Madison v. Theodore CA2/7
California Court of Appeal, 2025
Chang v. Fire Insurance Exchange CA2/7
California Court of Appeal, 2024
People v. Superior Court (J.A.) CA5
California Court of Appeal, 2024
Rostack Investments v. Sabella CA2/8
California Court of Appeal, 2023
Vargas v. Gallizzi
California Court of Appeal, 2023
Valenti v. City of San Diego
California Court of Appeal, 2023
Valenti v. City of San Diego CA4/1
California Court of Appeal, 2023
Srabian v. Triangle Truck Center CA5
California Court of Appeal, 2022
Rozanova v. Uribe
California Court of Appeal, 2021
Ayala Boring v. HPS Mechanical CA4/1
California Court of Appeal, 2021
P. ex rel. Tonti v. Living Rebos CA2/1
California Court of Appeal, 2020
Segal v. ASICS America Corp.
California Court of Appeal, 2020

Cite This Page — Counsel Stack

Bluebook (online)
242 Cal. Rptr. 3d 252, 30 Cal. App. 5th 1133, Counsel Stack Legal Research, https://law.counselstack.com/opinion/berkeley-cement-inc-v-regents-of-the-univ-of-cal-calctapp5d-2019.