Bennett, J. v. Braund, M.

Superior Court of Pennsylvania·Decided January 27, 2026·No. 105 WDA 2025·Unpublished·Dubow

Opinion

NON-PRECEDENTIAL DECISION - SEE SUPERIOR COURT O.P. 65.37

JENNIFER BENNETT : IN THE SUPERIOR COURT OF : PENNSYLVANIA

Appellant :

:

:

v. :

:

:

MICHAEL T. BRAUND AND MICHAEL : No. 105 WDA 2025 T. BRAUND CONSTRUCTION, INC. :

Appeal from the Order Entered December 20, 2024 In the Court of Common Pleas of Butler County Civil Division at No(s):

AD-2024-10292

BEFORE: OLSON, J., DUBOW, J., and BENDER, P.J.E. MEMORANDUM BY DUBOW, J.: FILED: JANUARY 27, 2026 Appellant, Jennifer Bennett (“Owner”), appeals from the December 20, 2024 order sustaining the preliminary objections filed by Appellees, Michael T. Braund and Michael T. Braund Construction, Inc. (“Builder”), and dismissing Owner’s complaint with prejudice after finding that the parties had entered into a valid agreement to arbitrate and Owner’s claims are within the scope of the agreement.1 Owner challenges the court’s finding that her claims are within the scope of the arbitration agreement. After careful review, we affirm

the portion of the order that sustained the preliminary objections and reverse

1 In general, an order sustaining preliminary objections and compelling a case

to arbitration is interlocutory. Schantz v. Dodgeland, 830 A.2d 1265, 1266 (Pa. Super. 2003). However, where, as here, the trial court sustains preliminary objections based on a valid and applicable agreement to arbitrate and dismisses the case, rather than issuing a stay, the plaintiff may take an immediate appeal. Stern v. Prudential Financial, Inc., 836 A.2d 953, 955 n.1 (Pa. Super. 2003).

the portion of the order that dismissed with prejudice, rather than stayed, the action pending arbitration.

The relevant facts and procedural history are as follows. On May 10, 2021, the parties executed an “Agreement for Construction of Dwelling House on Owner’s Lot” (“Builder Agreement”), which pertained to construction of Owner’s home in Mars, Pennsylvania. The Builder Agreement included, inter alia, provisions regarding default/termination and dispute resolution. Section 14 of the Builder Agreement concerned the parties’ rights and remedies if either party is in default and explained which disputes are subject to arbitration and which are not.

In particular, Section 14(a), titled “Payment of Contract Price Dispute,”

permitted Builder to enforce Owner’s payment obligations under the Builder Agreement. Section 14(a) explicitly provided that those claims are not subject to arbitration and that Builder must, instead, bring actions to enforce Owner’s payment obligations at law. Builder Agreement, 5/10/21, at § 14(a).

Section 14(b), a termination provision, explained that Builder had the right to terminate the Builder Agreement if Owner defaults by failing to pay any portion of the contract price, fails to maintain insurance as required by the Builder Agreement, or “persistently fails to cooperate with” Builder. Id. at § 14(b).

Section 14(d)(1), a termination provision titled “Owners Right to Terminate,” permitted Owner to terminate the Builder Agreement if “Builder fails to satisfy its obligations under this Agreement to construct the

Improvements.” Id. at § 14(d)(1). In other words, the Builder Agreement provides Owner the remedy of termination if Builder failed to satisfy its obligations under the Builder Agreement. Of most importance to our analysis, this provision is silent about whether the parties must resolve disputes arising from this paragraph by arbitration or before a trial court. It merely provides a remedy to Owner if Builder fails to properly construct the improvements.

Section 14(e), however, addressed which disputes must be resolved by arbitration. In particular, this provision is titled “Other Disputes,” provided a list of claims that must be submitted to arbitration including claims arising out of the construction of the improvements. It specified as follows:

[s]ubject to the provisions of subsection (a) [excluding from arbitration any claims by Builder to enforce Owner’s obligations to pay sums due under the Agreement], any controversy or claim arising out of or relating to this Agreement, the construction of the Improvements, or any matter related to breach of contract, fraud, misrepresentations, warranty and/or negligence shall be settled by negotiation between the parties, or if any party concludes that further negotiation will be fruitless, by binding arbitration in accordance with the procedures set forth in section 15 relating to arbitration.

Id. at § 14(e) (emphasis added). Section 14(e) also indicated that “[t]he provisions of this section shall survive the Construction Closing.”2 Id.

Another arbitration provision, Section 15(a), reaffirmed, inter alia, that a party may elect to commence arbitration only after “concluding that further

2 The Builder Agreement defined the “Construction Closing” as “the date on

which the final installment of the purchase price is required to be paid, by cashier’s check or wired finds.” Id. at § 3(d).

negotiations will be unlikely to lead to a resolution of the dispute[.]” Id. at 15(a).

Owner obtained a home construction loan from Erie Bank and informed Erie Bank that she had selected Builder as her contractor. Erie Bank approved Owner’s selection of Builder as her contractor.

The parties agreed to a “draw schedule” in which Owner would pay Builder upon completion of various stages of the project. The payment procedure provided that: (1) once Builder completed each successive building stage, Builder would advise Erie Bank of completion and request the corresponding draw or disbursement; (2) Erie Bank would direct an inspector to confirm that Builder had completed the work necessary to trigger disbursement; (3) the inspector would inform Erie Bank of completion; (4) Erie Bank would prepare the disbursal request and forward it to Owner for her signature; and (5) Erie Bank would disburse the requested draw to Builder.

On October 11, 2021, Builder began the project after receiving Draw #1 from Erie Bank. On March 11, 2022, Builder informed Erie Bank that it was ready for Draw #2. Upon receiving this request, Erie Bank notified the real estate inspector via email that the project was ready for inspection to determine if Erie Bank should issue Draw #2. By letter dated March 15, 2022, the inspector advised Erie Bank that “the subject was viewed and found to be complete for the requirements of Draw #2 (10% foundation).” Letter, 3/15/22.

On March 23, 2022, Owner received from Erie Bank and electronically signed a “Construction Advance Authorization” authorizing a payment of $247,000 to Builder. That same day, after Owner approved the payment, Erie Bank disbursed funds in that amount via check to Builder.

On March 17, 2023, pursuant to Paragraph 14(d)(1) of the Builder Agreement, Owner terminated the Builder Agreement prior to completion of the construction on her home due to Builder’s alleged material breaches of the Builder Agreement.

On April 1, 2024, Owner filed a seven-count complaint raising claims of Breach of Contract, Negligent Misrepresentation, Unjust Enrichment, violations of the Pennsylvania Unfair Trade Practices and Consumer Protection Law (“UTPCPL”),3 and Fraudulent and/or Intentional Misrepresentation, and requesting that the trial court pierce the corporate veil. Owner claimed that Builder knowingly retained funds paid to it by Owner without completing the construction of Owner’s home amid significant construction delays and issues.

In particular, Owner claimed that Erie Bank overpaid Builder by $123,500 when it issued the $247,000 Draw #2 payment because the Draw Schedule provided for a Draw #2 payment of only $123,500. She contended that Builder failed to notify Owner of the overpayment and remains in possession of the extra $123,500 to which it was not entitled. Owner also claimed that after Builder received the erroneous disbursement, she began to

3 73 P.S. §§ 201-1-201-10.2.

Free access — add to your briefcase to read the full text and ask questions with AI

Bennett, J. v. Braund, M., (Pa. Ct. App. 2026).

Bennett, J. v. Braund, M. (Bennett, J. v. Braund, M.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Commonwealth v. Hardy
918 A.2d 766 (Superior Court of Pennsylvania, 2007)
Schantz v. Dodgeland
830 A.2d 1265 (Superior Court of Pennsylvania, 2003)
Salley v. Option One Mortgage Corp.
925 A.2d 115 (Supreme Court of Pennsylvania, 2007)
Insurance Adjustment Bureau, Inc. v. Allstate Insurance
905 A.2d 462 (Supreme Court of Pennsylvania, 2006)
Stern v. Prudential Financial, Inc.
836 A.2d 953 (Superior Court of Pennsylvania, 2003)
Banking v. Gesiorski
904 A.2d 939 (Superior Court of Pennsylvania, 2006)
Elwyn v. DeLuca
48 A.3d 457 (Superior Court of Pennsylvania, 2012)
Knight v. Springfield Hyundai
81 A.3d 940 (Superior Court of Pennsylvania, 2013)
In Re:Est. of Atkinson, J., Appeal of: Wells Fargo
2020 Pa. Super. 87 (Superior Court of Pennsylvania, 2020)