Bella Monte Owners Association v. Vial Fotheringham LLP

CourtDistrict Court, D. Utah
DecidedDecember 16, 2021
Docket2:19-cv-00212
StatusUnknown

This text of Bella Monte Owners Association v. Vial Fotheringham LLP (Bella Monte Owners Association v. Vial Fotheringham LLP) is published on Counsel Stack Legal Research, covering District Court, D. Utah primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Bella Monte Owners Association v. Vial Fotheringham LLP, (D. Utah 2021).

Opinion

IN THE UNITED STATES DISTRICT COURT FOR THE DISTRICT OF UTAH

BELLA MONTE OWNERS ORDER AND MEMORANDUM ASSOCIATION, INC., DECISION

Plaintiff, Case No. 2:19-cv-00212-TC-JCB v. District Judge Tena Campbell Magistrate Judge Jared C. Bennett VIAL FOTHERINGHAM, LLP,

Defendant.

Defendant law firm Vial Fotheringham, LLP (VF) formerly represented Plaintiff Bella Monte Owners Association, Inc. in a construction defect case in Utah state court (the “Underlying Action”). After the trial court excluded a critical expert report from evidence, the Underlying Action settled. Bella Monte was dissatisfied with how the case turned out, so it sued VF for legal malpractice. VF has now moved for summary judgment. It asks the court to find that Bella Monte has failed to meet its burden on “collectability”—i.e., that Bella Monte has failed to prove that it would have recovered more money in the Underlying Action had the expert report not been excluded. It also argues that each of the Underlying Claims would have failed, and so the court should find that VF cannot be liable for damages flowing from those claims. For the following reasons, the court GRANTS IN PART and DENIES IN PART VF’s motion. FACTUAL BACKGROUND1 Bella Monte is the management association for its namesake condominium complex in Draper, Utah. Construction on the complex began in 2006 and continued through 2013. The

1 Because legal malpractice involves a “case within a case,” the court will differentiate between parties and events in the “Underlying Action” and parties and events in the “Malpractice Action” by using those two terms. project can be divided into two phases: Phase 1 (Buildings 1 through 13) and Phase 2 (Buildings 14 through 23 and the Clubhouse). Bella Monte noticed structural problems at the complex, which led to Bella Monte hiring VF to file the Underlying Action in 2015 against the developers of the complex—Bella Monte, LLC, Compass Investments L.C., and Compass Development Group, Inc. (collectively, the “Developers”)—alleging construction defects. The complaint (the

“Underlying Complaint”) was filed on October 5, 2015. The Developers filed a third-party complaint against 21 Construction (the “General Contractor”). The General Contractor filed a fourth-party complaint against several Subcontractors. (The Developers, General Contractor, and Subcontractors are collectively the “Underlying Defendants.”) Bella Monte’s Underlying Complaint asserted eighteen claims against the Developers. Ten were tort claims, seven were contract claims, and one claim sought to pierce the corporate veil.2 During the Underlying Action, Bella Monte (VF) retained an expert, Sean Gores, who prepared an expert report (the “Gores Report”). The Gores Report concluded that the total cost to repair the defects at the complex would be $7,263,594, and it apportioned the damages among

the Underlying Defendants. Of this sum, the cost to repair Buildings 14 through 23 and the Clubhouse was $3,507,251. The Underlying Defendants had two expert witnesses who were prepared to testify to the repair cost being between $236,086.41 and $502,302. In the Underlying Action, fact discovery closed in March 2018. Bella Monte (VF) disclosed the Gores Report in April—past the deadline. As a result, the Underlying Defendants moved to preclude evidence or argument about damages at trial. The motion requested that Bella Monte be prohibited from submitting the

2 Four Underlying Action claims—Thirteen, Fourteen, Seventeen, and Eighteen—are not at issue in the Malpractice Action. Seven tort claims and seven contract claims remain here. Gores Report, due to its failure to provide an estimate of damages in its initial disclosures or in response to the Underlying Defendants’ interrogatories. Bella Monte (VF) opposed the motion, arguing that there had been no way to provide an estimate earlier in the case because its investigation into the scope of defects was ongoing throughout the litigation. Three months later, the trial court granted the motion to exclude the Gores Report. The

trial court found that Bella Monte (VF) did not comply with the initial disclosure requirements imposed by Utah Rule of Civil Procedure 26. Rather than appeal the order, Bella Monte settled the Underlying Action for $500,000 in October 2018. Each Underlying Defendant paid a portion of this settlement, with the money coming from their respective insurance companies. (Opp’n Ex. S, ECF No. 124-4.) Some of the Underlying Defendants’ insurance policies had policy exclusions that could have excluded coverage for some of Bella Monte’s alleged construction defects. But apart from the insurers sending reservation of rights letters to Bella Monte, coverage was not an issue in the Underlying Action. Within six months of the settlement, Bella Monte brought the Malpractice Action against

VF, arguing that VF’s failure to comply with the Rule 26 disclosure requirements had damaged Bella Monte in the amount of around $7,000,000. VF moved to dismiss the Malpractice Action (ECF No. 8), which the court denied. (ECF Nos. 27 & 28.) Later, Bella Monte moved for partial summary judgment on two of VF’s affirmative defenses, along with some elements of legal malpractice. (ECF No. 41.) The court granted the motion on the defenses but denied it for the rest. (ECF No. 73.) Now VF has moved for summary judgment on all Bella Monte’s claims.3 (ECF No. 107.)

3 VF’s motion does not mention Bella Monte’s second claim in the Malpractice Action, “Breach of Contract/Implied Covenant of Good Faith and Fair Dealing.” (Compl. ¶¶ 42–47, ECF No. 2-1.) At oral argument, VF’s counsel implied that this claim is analytically similar to the breach of fiduciary duty claim. LEGAL STANDARD In general, summary judgment is appropriate “if the movant shows that there is no genuine dispute as to any material fact and [that] the movant is entitled to judgment as a matter of law.” Fed. R. Civ. P. 56(a). “A fact is ‘material’ if, under the governing law, it could have an effect on the outcome of the lawsuit. A dispute over a material fact is ‘genuine’ if a rational jury

could find in favor of the nonmoving party on the evidence presented.” Tabor v. Hilti, Inc., 703 F.3d 1206, 1215 (10th Cir. 2013) (quoting E.E.O.C. v. Horizon/CMS Healthcare Corp., 220 F.3d 1184, 1190 (10th Cir. 2000)). When evaluating a motion for summary judgment, the court must view the facts and draw all reasonable inferences in favor of the nonmoving party. Id. (quoting Turner v. Pub. Serv. Co., 563 F.3d 1136, 1142 (10th Cir. 2009)). But this is true only if “there is a ‘genuine’ dispute as to those facts.” Scott v. Harris, 550 U.S. 372, 380 (2007). “Where the record taken as a whole could not lead a rational trier of fact to find for the nonmoving party, there is no ‘genuine issue for trial.’” Id. (quoting Matsushita Elec. Indus. Co. v. Zenith Radio Corp., 475 U.S. 574, 586–87

(1986)). “If the movant meets this initial burden, the burden then shifts to the nonmovant to set forth specific facts from which a rational trier of fact could find for the nonmovant.” Talley v. Time, Inc., 923 F.3d 878, 893–94 (10th Cir. 2019) (quoting Teets v. Great-W. Life & Annuity Ins. Co., 921 F.3d 1200, 1211 (10th Cir. 2019)). ANALYSIS “[W]hen bringing a legal malpractice suit, ‘[c]lients . . .

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Nordwind v. Rowland
584 F.3d 420 (Second Circuit, 2009)
Scott v. Harris
550 U.S. 372 (Supreme Court, 2007)
Hinsdale v. City of Liberal,KS
19 F. App'x 749 (Tenth Circuit, 2001)
Turner v. Public Service Co. of Colorado
563 F.3d 1136 (Tenth Circuit, 2009)
Tabor v. Hilti, Inc.
703 F.3d 1206 (Tenth Circuit, 2013)
Brigham City Sand & Gravel v. MacHinery Center, Inc.
613 P.2d 510 (Utah Supreme Court, 1980)
Hipwell by and Through Jensen v. Sharp
858 P.2d 987 (Utah Supreme Court, 1993)
Rorrer v. Cooke
329 S.E.2d 355 (Supreme Court of North Carolina, 1985)
George v. Caton
600 P.2d 822 (New Mexico Court of Appeals, 1979)
Power Constructors, Inc. v. Taylor & Hintze
960 P.2d 20 (Alaska Supreme Court, 1998)
Huber v. Watson
568 N.W.2d 787 (Supreme Court of Iowa, 1997)
Payne v. Lee
686 F. Supp. 677 (E.D. Tennessee, 1988)
Allen Decorating, Inc. v. Oxendine
483 S.E.2d 298 (Court of Appeals of Georgia, 1997)
Ridenour v. Lewis
854 P.2d 1005 (Court of Appeals of Oregon, 1993)
Albee Associates v. ORLOFF, LOWENBACH, STIFELMAN & SIEGEL, PA
721 A.2d 750 (New Jersey Superior Court App Division, 1999)

Cite This Page — Counsel Stack

Bluebook (online)
Bella Monte Owners Association v. Vial Fotheringham LLP, Counsel Stack Legal Research, https://law.counselstack.com/opinion/bella-monte-owners-association-v-vial-fotheringham-llp-utd-2021.