Belfiore Developers, LLP v. Elvia Besil Sampieri and Haffan Properties, LLC

CourtCourt of Appeals of Texas
DecidedMarch 6, 2018
Docket01-17-00847-CV
StatusPublished

This text of Belfiore Developers, LLP v. Elvia Besil Sampieri and Haffan Properties, LLC (Belfiore Developers, LLP v. Elvia Besil Sampieri and Haffan Properties, LLC) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Belfiore Developers, LLP v. Elvia Besil Sampieri and Haffan Properties, LLC, (Tex. Ct. App. 2018).

Opinion

Opinion issued March 6, 2018

In The

Court of Appeals For The

First District of Texas ———————————— NO. 01-17-00847-CV ——————————— BELFIORE DEVELOPERS, LLP, Appellant V. ELVIA BESIL SAMPIERI AND HAFFAN PROPERTIES, LLC, Appellees

On Appeal from the 334th District Court Harris County, Texas Trial Court Case No. 2017-44139

MEMORANDUM OPINION

Belfiore Developers, LLP (“Belfiore”) challenges the trial court’s order,

granting Elvia Besil Sampieri and Haffan Properties, LLC’s motion to vacate an

arbitration award. In three issues, Belfiore contends that the trial court erred in

vacating the award. We reverse and render.

Background

In February 2014, Belfiore began construction of Belfiore Condominiums, a

26-story luxury condominium building in Houston, containing 46 residential units.

Belfiore developed the high-rise with the following purchaser in mind: wealthy

people with large homes who want to downsize but still want adequate living space.

Each condominium unit contains approximately 4,500 square feet of living area with

an additional 700 square feet of terrace space. The condominiums have many high-

end amenities, including 24-hour concierge and valet services and private elevator

lobbies.

Buyers who can afford this type of high-end condominium want the ability to

customize their home. For this reason, purchasers frequently buy high-end

condominiums either before or during construction to allow them to work with

designers and decorators to customize the unit. To allow for customization, Belfiore

began selling units in the building in May 2013, nine months before construction on

the high-rise building began.

On October 6, 2014, Elvia Besil Sampieri contracted with Belfiore to buy two

condominium units, Unit 702 and Unit 1102. Sampieri signed a separate purchase

contract for each unit. The purchase price for Unit 702 was $2,480,000, and the

purchase price for Unit 1102 was $2,700,000.

2 The purchase contracts required Sampieri to pay 20 percent of the purchase

price up front as an “Initial Payment.” On October 17, 2014, Sampieri deposited the

initial payments of $496,000 for Unit 702 and $540,000 for Unit 1102 with the title

company designated in the purchase agreements. The initial payment for each

property would be applied to the total purchase price, which was due at closing.

In Paragraph 17, entitled “Liquidated Damages/Default,” the purchase

contracts each provided,

c. In the event of any default by Purchaser [Sampieri] under this Contract, Seller [Belfiore] may (i) terminate this Contract, in which event the Initial Payment shall be delivered to [Belfiore] as liquidated damages and not as a penalty because of the uncertainty and difficulty of ascertaining and measuring [Belfiore’s] actual damages, and neither [Sampieri] nor [Belfiore] shall have any further rights or obligations under this Contract, (ii) enforce specific performance of this Contract, or (iii) seek damages or any other available remedies.

In August 2015, Sampieri entered into another contract with Belfiore, a

“Construction Rider,” pertaining to Unit 1102. Sampieri and her family planned to

reside in Unit 1102, and the Construction Contract covered customized “build out”

work for the unit. Sampieri agreed to pay $618,898 for the work. She initially paid

Belfiore, $309,000, half of the agreed amount, but did not pay the remaining

$309,000.

3 Construction of the high-rise condominium building was substantially

completed in February 2016.1 The closings for both Unit 702 and Unit 1102 were

scheduled for March 10, 2016. However, Sampieri failed to close on the properties

and failed to pay Belfiore the remainder of the purchase price for the condominium

units.

On March 15, 2016, Belfiore notified Sampieri that she had defaulted on the

purchase contracts by failing to pay Belfiore the remainder of the purchase prices

for the two condominium units on the agreed closing date. In its notices, Belfiore

informed Sampieri that it was terminating the purchase contracts and exercising its

right to enforce the liquidated-damages provision found in Paragraph 17.c. Pursuant

to this provision, Belfiore requested the title company to release Sampieri’s initial

payments of $496,000 and $540,000, which corresponded to 20 percent of each

condominium’s purchase price.

Sampieri disputed Belfiore’s entitlement to the 20 percent initial payments

being held by the title company, taking the position that the liquidated-damages

provision contained in the purchase agreements was not enforceable. As a result of

the dispute, the funds were not released by the title company to Belfiore.

1 In February 2016, Sampieri assigned her interest in the purchase contracts to Haffan Properties, a company founded and owned by Sampieri. However, the assignment did not release Sampieri from her personal obligations under any of the contracts. Thus, because their interests are aligned, we refer to Haffan Properties and Sampieri collectively as “Sampieri.” 4 To resolve the dispute, Sampieri filed a claim for arbitration as required by

Paragraph 18 of the purchase agreements, which provides,

18. Arbitration/Limitation of Claims. All claims for breach of this Contract or otherwise are limited solely to the specific remedies provided for herein. Purchaser and Seller hereby further agree that any controversy, claim or dispute arising out of or relating to (a) this Contract, (b) any breach of this Contract, (c) the sales transaction reflected in this Contract, (d) the construction of the Unit which is the subject of this Contract, and/or (e) any representations or warranties, express or implied, relating to the Property and the Unit, may be decided by arbitration in accordance with the Construction Industry Arbitration Rules of the American Arbitration Association. All decisions by the arbitrators shall be final, and any judgment upon the award rendered by the arbitrators may be confirmed, entered and enforced in any court having proper jurisdiction. The decision of the arbitrators must be based on and consistent with Texas law (without regard to its conflicts of law), and all hearings and proceedings shall take place in Houston, Harris County, Texas. Any action, regardless of form, arising out of the transactions under this Contract must be brought by Purchaser within two (2) years of the date that the cause of action accrues.

The dispute was submitted to a three-member Arbitration Panel. After a three-

day hearing, at which both sides offered witness testimony and documentary

evidence, the Arbitration Panel rendered its written Arbitration Award.

In the Award, the Arbitration Panel wrote, “The purchase of each unit required

a 20% deposit, which equated to $496,000 in the case of Unit 702 and $540,000 in

the case of Unit 1102. The dispute in this matter centers around whether Belfiore is

entitled to the 20% pursuant to the liquidated-damages clause contained in the

contracts.” The Panel recognized, “Counsel for both sides agree that, under Texas

5 law, for a liquidated damages provision to be enforceable (1) actual damages must

[be] difficult to prove and (2) stipulated damages must be a reasonable estimate of

the actual damages.”

Citing to Texas case law, the Arbitration Panel offered the following

evaluation of the evidence presented at the hearing:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Flores v. Millennium Interests, Ltd.
185 S.W.3d 427 (Texas Supreme Court, 2005)
Nafta Traders, Inc. v. Quinn
339 S.W.3d 84 (Texas Supreme Court, 2011)
Phillips v. Phillips
820 S.W.2d 785 (Texas Supreme Court, 1992)
Baker v. International Record Syndicate, Inc.
812 S.W.2d 53 (Court of Appeals of Texas, 1991)
Naylor v. Siegler
613 S.W.2d 546 (Court of Appeals of Texas, 1981)
SP Terrace, LP v. Meritage Homes of Texas, LLC
334 S.W.3d 275 (Court of Appeals of Texas, 2010)
Port Arthur Steam Energy LP v. Oxbow Calcining LLC
416 S.W.3d 708 (Court of Appeals of Texas, 2013)
FPL Energy, LLC v. TXU Portfolio Management Co.
426 S.W.3d 59 (Texas Supreme Court, 2014)

Cite This Page — Counsel Stack

Bluebook (online)
Belfiore Developers, LLP v. Elvia Besil Sampieri and Haffan Properties, LLC, Counsel Stack Legal Research, https://law.counselstack.com/opinion/belfiore-developers-llp-v-elvia-besil-sampieri-and-haffan-properties-llc-texapp-2018.