Beckham v. William Bayley Co.

655 F. Supp. 288, 1987 U.S. Dist. LEXIS 1760
CourtDistrict Court, N.D. Texas
DecidedMarch 5, 1987
DocketCiv. A. CA3-85-0021-D
StatusPublished
Cited by16 cases

This text of 655 F. Supp. 288 (Beckham v. William Bayley Co.) is published on Counsel Stack Legal Research, covering District Court, N.D. Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Beckham v. William Bayley Co., 655 F. Supp. 288, 1987 U.S. Dist. LEXIS 1760 (N.D. Tex. 1987).

Opinion

MEMORANDUM OPINION AND ORDER

FITZWATER, District Judge.

The court must decide whether a requirement to arbitrate a disagreement regarding the intent of a contract mandates arbitration of a disagreement concerning performance of the contract. The court concludes that arbitration is not required. Accordingly, it denies defendant’s motion to dismiss for lack of subject matter jurisdiction and application to confirm arbitration award and motion for summary judgment. 1

I.

BACKGROUND FACTS AND PROCEDURAL HISTORY

In this removed action plaintiff, Edwin T. Beckham (“Beckham”), a general contractor, seeks damages from defendant, The William Bayley Company (“Bayley”), a steel casements and casement doors mate-rialman. Beckham filed suit in Texas state court contending the casements and doors, when delivered six months late, were warped, the latches would not engage in the keepers, the glazier was unable to install the glass and, as a result, the architects would not approve them for installation. Plaintiff contends the units were returned to defendant’s plant for correction *290 and re-delivered approximately 60 days later but that, during the interim, plaintiff was forced to close down all work on the job site due to the lack of doors and windows. Plaintiff sues defendant pursuant to the Texas Deceptive Trade Practices— Consumer Protection Act, TEX.BUS. & COMM.CODE ANN. §§ 17.41 et seq. (Vernon Supp.1986) (“TDTPA”), 2 for knowingly furnishing goods not of the standard or grade to produce a satisfactory window installation and for breach of warranty. Plaintiff seeks damages caused by the two and one-half months construction delay, attorney’s fees, and treble damages pursuant to the TDTPA.

At the time Bayley removed this action to federal court it filed a motion to dismiss for lack of subject matter jurisdiction or to stay pending arbitration. Thereafter, plaintiff filed his motion to stay or enjoin arbitration proceedings. At the time these motions were filed this civil action was assigned to a docket that did not have an active U.S. District Judge. A committee of this court rejected the request that an active judge be assigned to decide these motions. Absent a decision on the pending motions, Bayley proceeded to arbitration before the American Arbitration Association in Cincinnati, Ohio; Beckham refused to participate. The arbitrator issued an award in favor of Bayley. Subsequently, Bayley moved this court to confirm the arbitration award and for summary judgment.

II.

DISCUSSION

Whether a contract’s arbitration clause requires arbitration of a given dispute is a matter of contract interpretation, Totem Marine Tug & Barge, Inc. v. North American Towing, Inc., 607 F.2d 649, 651 (5th Cir.1979), which is to be performed by the court. AT & T Technologies, Inc. v. Communications Workers of America, — U.S. -, 106 S.Ct. 1415, 1420, 89 L.Ed.2d 648 (1986) (it is court’s duty to interpret agreement and determine whether parties intended to arbitrate). The court’s interpretive function must be carried out with appropriate deference to the strong federal policy that favors arbitration over litigation and requires that arbitration clauses be construed generously, in favor of arbitration. See Southland Corp. v. Keating, 465 U.S. 1, 10-11, 104 S.Ct. 852, 858, 79 L.Ed.2d 1 (1984). The law imposes a presumption in favor of arbitrability which requires, whenever the scope of an arbitration clause is fairly debatable or reasonably in doubt, that the court decide the interpretation question in favor of arbitration. See Moses H. Cone Memorial Hospital v. Mercury Construction Corp., 460 U.S. 1, 24-25, 103 S.Ct. 927, 941-42, 74 L.Ed.2d 765 (1983). The Federal Arbitration Act, 9 U.S.C. § 2, by its terms leaves no place for the exercise of discretion by a district court, but instead mandates that the court shall direct the parties to proceed to arbitration on issues to which an arbitration agreement has been signed. Dean Witter Reynolds, Inc. v. Byrd, 470 U.S. 213, 105 S.Ct. 1238, 1241, 84 L.Ed.2d 158 (1985). Accordingly, arbitration should not be denied unless it can be said with positive assurance that an arbitration clause is not susceptible to an interpretation that could cover the dispute in issue. United Steelworkers of America v. Warrior & Gulf Navigation Co., 363 U.S. 574, 582-83, 80 S.Ct. 1347, 1352-53, 4 L.Ed.2d 1409 (1960); Mar-Len of Louisiana, Inc. v. Parsons-Gilbane, 773 F.2d 633, 635-37 (5th Cir. 1985). Notwithstanding judicial deference to arbitration, a party may not be required to arbitrate a dispute that it did not agree to arbitrate, Commercial Metals Co. v. Balfour, Guthrie, and Co., Ltd., 577 F.2d 264, 266 (5th Cir.1978), and the controversy must come within the contract’s arbitration provision before the court can order arbitration. *291 Exp lo, Inc. v. Southern Natural Gas Co., 788 F.2d 1096, 1098 (5th Cir.1986).

With the foregoing principles in mind, the court turns to the arbitration clause at issue, which reads as follows:

ARBITRATION: Any disagreement between the Seller [Bayley] and the Purchaser [Beckham] as to the intent of this contract, at the request of either, shall be presented for arbitration in accordance with the requirements set forth by the American Institute of Architects, or the American Arbitration Association. (Emphasis added).

Defendant contends the clause requires the parties to arbitrate plaintiffs claim; plaintiff contends his suit complains of defendant’s performance under the contract and that the parties' contractual intent is undisputed.

Ordinarily, arbitration clauses contain a requirement by which the parties arbitrate “any controversy or claim arising out of or relating to [the] contract or the breach thereof” 3 or, with minor variation, “any controversy concerning the interpretation, performance, or application of [the] contract.” 4 See Butler Products Co. v. Unis-trut Corp.,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Papalote Creek II, L.L.C. v. Lower Colorado River
918 F.3d 450 (Fifth Circuit, 2019)
in Re: Giant Eagle, Inc.
Court of Appeals of Texas, 2015
Meyer v. WMCO-GP, LLC
211 S.W.3d 302 (Texas Supreme Court, 2006)
in Re: Fulton Performance Products, Inc.
Court of Appeals of Texas, 2002
Coffman v. Provost ★ Umphrey Law Firm, L.L.P.
161 F. Supp. 2d 720 (E.D. Texas, 2001)
Associated Air Freight, Inc. v. Meek
67 S.W.3d 249 (Court of Appeals of Texas, 2001)
Satarino v. A.G. Edwards & Sons, Inc.
941 F. Supp. 609 (N.D. Texas, 1996)
Pepe International Development Co. v. Pub Brewing Co.
915 S.W.2d 925 (Court of Appeals of Texas, 1996)
Belmont Constructors, Inc. v. Lyondell Petrochemical Co.
896 S.W.2d 352 (Court of Appeals of Texas, 1995)
Babcock & Wilcox Co. v. PMAC, LTD.
863 S.W.2d 225 (Court of Appeals of Texas, 1993)
Blount Intern. v. James River-Pennington
618 So. 2d 1344 (Supreme Court of Alabama, 1993)

Cite This Page — Counsel Stack

Bluebook (online)
655 F. Supp. 288, 1987 U.S. Dist. LEXIS 1760, Counsel Stack Legal Research, https://law.counselstack.com/opinion/beckham-v-william-bayley-co-txnd-1987.