Beckenstein v. Potter & Carrier, Inc.

464 A.2d 18, 191 Conn. 150, 37 U.C.C. Rep. Serv. (West) 158, 1983 Conn. LEXIS 587
Supreme Court of Connecticut·Decided August 16, 1983·No. 11061·Published·Cited by 112 cases

Opinion

Arthur H. Healey, J.

In January, 1975, the plaintiffs, Henry and Louis Beckenstein (plaintiffs), filed this action against the defendants, Potter & Carrier, Inc. (Potter & Carrier), and General Aniline & Film Corporation (GAF). The plaintiffs claimed that Potter & Carrier had installed a defective roof on a manufacturing building constructed by the plaintiffs and that the materials for said roof had been manufactured by GAF. The plaintiffs have appealed the court’s decision, Alexander, J., sustaining a demurrer to two counts in their original complaint alleging a breach of implied warranty, and the trial court’s decision, Aspell, J., to direct a verdict for the defendants on the two counts in their substituted complaint. The first count of the substituted complaint alleged that Potter & Carrier had breached its contract with the plaintiffs by failing to construct the roof in a workmanlike manner. It also alleged that Potter & Carrier was the agent of GAF. The second count in the substituted complaint was based upon product liability.

In June of 1968, the plaintiffs entered into an agreement with Colt Industries, Inc. (Colt), whereby Colt conveyed a parcel of land located in the town of Rocky Hill to the plaintiffs, and the plaintiffs agreed to construct a manufacturing plant which they would then lease to Colt. In addition, Colt was given an option to repurchase both the land and the building under certain conditions. The lease between the parties contained a clause which stated, in part, that the building was to be constructed “substantially in accordance with the [152]*152outline plans and specifications agreed upon by the parties.” Some of the plans and specifications referred to in the lease were introduced into evidence. Henry Beckenstein also testified that it was his understanding that he was required to construct the building in accordance with these plans and specifications.

The plaintiffs undertook to construct the building through a corporation which they owned, National Building Supply Company. This company acted as the “coordinator” for the project. In addition, the general superintendent1 for the project was William Muller, one of whose responsibilities was to hire the subcontractors.

On May 29,1968, Muller entered into a contract with Potter & Carrier to construct the roof of the building for $37,000. One of the plans for the building stated that the roof was to be a “typical roof construction, twenty-year bond.” The contract entered into between Muller and Potter & Carrier called for the latter to install, inter alia, a “20 year smooth surface asbestos roof (Bonded).”

As explained by one of the plaintiffs’ witnesses, Robert Berryman, a roofing bond was something offered by the manufacturer of roofing materials, whereby, if one paid a premium, the manufacturer would agree to make any repairs on the roof during the period that the bond was in effect. There was also a dollar limit as to how much a manufacturer would be obligated to spend in making any repairs. The bond issued by GAF in this case, for example, was a twenty year bond which bound GAF to make repairs up to a sum not to exceed $8970.

There was no agreement between the plaintiffs and GAF to issue the bond covering the Colt building. Rather, the bond was issued pursuant to an agreement [153]*153entered into between Potter & Carrier and GAF. This agreement was entitled: “Approved Roofer’s Agreement.” In order to qualify for a bond pursuant to this agreement, Potter & Carrier had to satisfy certain conditions. For example, it had to notify GAF that it had been awarded a particular job at least two days before it commenced working on such job, as well as sending GAF notice of when it completed the job. In addition, the roofer had to comply with certain specifications of GAF governing the application of a particular roof. One of these conditions was that if GAF determined that any additional work or materials were required, it could direct Potter & Carrier to complete them. Finally, once a bond had been issued, the agreement between Potter & Carrier and GAF required Potter & Carrier to give a two year guarantee to GAF for its workmanship during which time Potter & Carrier was obligated to make all repairs.

Although Potter & Carrier used GAF materials in installing the roof on the Colt building, as noted previously, neither the architectural plans nor Potter & Carrier’s contract with Muller called for GAF products. Muller, in fact, testified that there were “several” different kinds of twenty year bonded roofs.

In regard to the date when Potter & Carrier installed the roof, Henry Beckenstein testified that he believed that the roof was completed prior to the end of 1968, and that Colt moved in by the end of 1968 or the beginning of 1969.2 Muller, the plaintiffs’ superintendent for the project, testified that the building was occupied by the end of 1968. The plaintiffs also introduced into evidence five bills submitted to them by Potter & Carrier. The first bill was dated August 21, 1968, and indicated that the roof was 85 percent complete. There was also a bill dated September 18,1968, and two that [154]*154were dated January 27, 1969. The final bill was dated March 26, 1969. The amount of this last bill was only $93.25.

The defendants introduced two certificates of occupancy issued by the building department of the town of Rocky Hill. The first certificate was a temporary certificate and restricted Colt to installing “machinery and/or other equipment.” This certificate was dated November 12, 1968. The second certificate was dated January 24, 1969, and stated that the building was “completed.”

Finally, the plaintiffs introduced the bond issued by GAF for the building. It stated that the date of completion was March 10,1970. Henry Beckenstein testified, however, that the bond was received after the roof was completed and that March 10 was not the same date as when it was completed.

Henry Beckenstein testified that “[t]he roof started to leak almost immediately after the building was done. And they were plaguing us every time it rained.” The plaintiffs called Potter & Carrier a number of times to try and get it repaired, but “[t]he next rain we had the same calls all over again. We called [Potter & Carrier]. [They] came again. That continued and continued and continued.” Muller testified that the first winter, i.e., early 1969, after the roof was completed he went up on the roof and “saw many blisters and cracks. Two cracks, I believe. And what I saw I never seen before was that the cant [a triangle-like piece of wood that goes along the perimeter of the building] had pulled in.” Beckenstein also testified that he had a discussion with a representative from GAF, William H. Barnett, and that the “gist” of their conversation was that they “discussed the fallacies of the roof. . . . Mr. Barnett was telling us that the roof was not applied properly . . . .’’He was also on the roof when Barnett had [155]*155Potter & Carrier cut core samples out of the roof. The plaintiffs then introduced two letters sent by Barnett to Potter & Carrier dated April 30, 1971, and September 9,1971, in which Barnett stated that the problems were “not normal” but that he did not know what exactly was causing the problems. He also suggested possible steps that could be taken to determine the cause.

Free access — add to your briefcase to read the full text and ask questions with AI

Beckenstein v. Potter & Carrier, Inc., 464 A.2d 18, 191 Conn. 150, 37 U.C.C. Rep. Serv. (West) 158, 1983 Conn. LEXIS 587 (Colo. 1983).

464 A.2d 18 (Beckenstein v. Potter & Carrier, Inc.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Ammar I. v. Evelyn W.
227 Conn. App. 827 (Connecticut Appellate Court, 2024)
Flannery v. Singer Asset Finance Co., LLC
Supreme Court of Connecticut, 2014
Tayco Corp. v. Planning & Zoning Commission
986 A.2d 290 (Supreme Court of Connecticut, 2010)
RBC Nice Bearings, Inc. v. PEER BEARING COMPANY
676 F. Supp. 2d 9 (D. Connecticut, 2009)
Michaud Estate v. Beckman, No. Cv99-0268302s (May 15, 2002)
2002 Conn. Super. Ct. 6570 (Connecticut Superior Court, 2002)
Gazza v. Bandit Industries, Inc., No. X03 Cv 99 0499931 S (Aug. 31, 2001)
2001 Conn. Super. Ct. 12103 (Connecticut Superior Court, 2001)
Torringford Farms v. City of Torrington, No. Cv99-0081120 (Aug. 15, 2001)
2001 Conn. Super. Ct. 10997 (Connecticut Superior Court, 2001)
Gazza v. Bandit Industries, Inc., No. X03 Cv 99 0499931 S (May 11, 2001)
2001 Conn. Super. Ct. 6107 (Connecticut Superior Court, 2001)
Calabrese v. Finno Development, No. Cv99-0151991s (May 11, 2001)
2001 Conn. Super. Ct. 6165 (Connecticut Superior Court, 2001)
Amoco Oil Co. v. Liberty Auto Elec., No. X06-Cv96-0160065s (May 9, 2001)
2001 Conn. Super. Ct. 6543 (Connecticut Superior Court, 2001)
Schilberg Integrated v. Con. Cas., No. X03 Cv 98 0499554 S (Apr. 17, 2001)
2001 Conn. Super. Ct. 5348 (Connecticut Superior Court, 2001)
Cofinante v. First Natl. Supermarkets, No. Cv96 33 01 31 S (Mar. 27, 2001)
2001 Conn. Super. Ct. 4229 (Connecticut Superior Court, 2001)
Palacios v. Hohl, Jr., No. Cv 98-0580157 (Jan. 3, 2001)
2001 Conn. Super. Ct. 317 (Connecticut Superior Court, 2001)
People's Savings Bank v. T.R. Paul, Inc., No. Cv 97-0571700 (Nov. 27, 2000)
2000 Conn. Super. Ct. 14895 (Connecticut Superior Court, 2000)
Franco v. Mediplex Construction, Inc., No. Cv 96-390458s (Aug. 25, 2000)
2000 Conn. Super. Ct. 9957 (Connecticut Superior Court, 2000)
Candlewood Vil. Condo. v. Leaska Condo., No. Cv 98 0581117s (Jul. 13, 2000)
2000 Conn. Super. Ct. 8496 (Connecticut Superior Court, 2000)
Mayo v. Northeast Conn. Council of Govs., No. Cv 99 9969743 S (May 31, 2000)
2000 Conn. Super. Ct. 6481 (Connecticut Superior Court, 2000)
Altfeter v. Borough of Naugatuck, No. Cv 96 0136342 (Dec. 9, 1999)
1999 Conn. Super. Ct. 15949 (Connecticut Superior Court, 1999)