Bay Point Capital Partners II, LP v. Thomas Switch Holding, Llc

113 F.4th 1304
Court of Appeals for the Eleventh Circuit·Decided August 26, 2024·No. 23-11432·Published·Cited by 2 cases

Opinion

[PUBLISH]

In the

United States Court of Appeals For the Eleventh Circuit

No. 23-11432

In re: VIRTUAL CITADEL, INC., et al., Debtor.

BAY POINT CAPITAL PARTNERS II, LP, Plaintiff-Appellant,

versus THOMAS SWITCH HOLDING, LLC, Defendant-Appellee.

Appeal from the United States District Court for the Northern District of Georgia D.C. Docket No. 1:22-cv-00074-SEG

2 Opinion of the Court 23-11432

Before WILLIAM PRYOR, Chief Judge, and JILL PRYOR, and BRASHER, Circuit Judges. BRASHER, Circuit Judge:

This appeal requires us to decide whether a bankruptcy court erred in valuing a bitcoin mining property. In so doing, we must answer three questions: First, did the bankruptcy court clearly err in finding that the property was a special purpose property with mining bitcoin as its highest and best use? Second, considering those findings, did the bankruptcy court choose the correct method to value the property as a matter of law? And third, did the bankruptcy court clearly err in giving the tax stamp value of the property some weight in its valuation? We answer “no” to each of those questions. Accordingly, we affirm.

I.

A.

Michael Oken owned and operated two related businesses in College Park and Atlanta, Georgia. The businesses were located on two adjacent properties, one that housed a bitcoin mining operation and the other that housed a data storage center. The bitcoin mining operation is at issue in this appeal. Oken bought the nearly one-acre mining property for $50,000 and invested millions in infrastructure upgrades to mine bitcoin on the property.

23-11432 Opinion of the Court 3

Bitcoin mining requires enormous amounts of power. So, important to the operation was a Power Sales Agreement Oken entered with the City of College Park, Georgia, to receive fifteen megawatts of low-cost power for five years at the mining property. That agreement resulted in electrical savings of up to $4 million per year. It also required Oken to pay around $885,000 for infrastructure upgrades to the property, including six transformers, to accommodate the increased electrical capacity. Although Oken paid for those improvements, the city owned the transformers and could hypothetically remove them if it chose to do so. Oken also completed around $3 million in other improvements to the property to prepare it to mine bitcoin and built a 3,000 square feet metal-sided “butler building” on the property to house electrical equipment, including “antboxes”—the containers storing the machines that do the bitcoin mining.

Oken died in 2019, which led his businesses to file for Chapter 11 bankruptcy in 2020. The bankruptcy estate sold the data center business and bitcoin mining operation together for $4.9 million. The deeds transferring the properties to the purchaser contained a stamp showing $2,450 in transfer taxes paid for each property. Because Georgia law imposes a 0.1% tax on transfers of real property, a $2,450 “tax stamp” value indicates a $2.45 million purchase price for each property.

The purchaser of the operation bought the mining property because of its existing bitcoin mining infrastructure and planned to expand and continue to use the property to mine bitcoin.

4 Opinion of the Court 23-11432

Specifically, the purchaser bought the property to “bring in as many bitcoin mining machines as they could and run a bitcoin mining operation.” The purchaser negotiated a new power sales agreement with the city and continued to use the property as a bitcoin mining facility.

After the sale, two creditors sought to recover on liens on the businesses’ property. Thomas Switch Holding had loaned $545,000 that was secured by a perfected first-priority lien on the mining property. Bay Point Capital loaned money to the debtors after they filed for bankruptcy and held a perfected first-priority lien on all the other assets of the mining operation, including the data center property. The order approving the sale of the mining operation required $700,000 of the proceeds to be put in escrow pending the determination of the amount of Switch’s lien, which attached up to $700,000 of the value of the mining property. Thus, if the mining property was valued at $700,000 or higher, Switch would receive the full $700,000. If the mining property was valued at less than $700,000, Switch would receive that amount and Bay Point would receive the difference.

B.

After a bench trial, the bankruptcy court found that the value of the mining property was over $700,000 and thus Switch was due the entire amount held in escrow. In valuing the property, the bankruptcy court considered two common valuation methods —the sales comparison approach (which considers the value at sale of comparable properties) and the cost approach (which

23-11432 Opinion of the Court 5

considers the cost to replace the property). The parties did not argue for, and the bankruptcy court did not consider the income approach , another commonly used valuation method.

At the bench trial, Switch’s appraiser, Michael Easterwood, testified that the mining property’s highest and best use was as a bitcoin mining operation, it was a special purpose property, and there were no comparable properties with access to fifteen megawatts of power available on the market. Thus, Easterwood opined that the cost approach was the most appropriate method to value the property and that the mining property should be valued at $830,000. He based his opinion on the value of the land at $60,000, the butler building at $100,000, and the cost of the improvements necessary to use fifteen megawatts of power on the property at $885,000. He also added engineering costs, applied discount factors , and depreciated the property. But he did not include the value of the antboxes, other equipment on the property, or any personal property. He also did not consider the $3 million Oken invested in electrical distribution improvements because he was unaware of those improvements at the time of his appraisal. And he did not consider the tax stamp value of the property.

Bay Point’s appraiser, Jeff Miller, testified that the sales comparison approach was the most appropriate method to value the mining property and that the value of the mining property was $48,000. To support his conclusion, he considered the mining property being landlocked with the only road access being through the data center property. Although he could not identify any similar

6 Opinion of the Court 23-11432

properties that could be used to mine bitcoin that could be used for a comparison, he compared the property to other properties of a comparable size that could be put to “light industrial” use. He did not consider the infrastructure upgrades to bring power to the property.

The bankruptcy court largely agreed with Easterwood’s testimony , adopted the cost approach to value the mining property, and held that the property was worth more than $700,000. It first concluded that, although the tax stamp value was not deserving of much weight, a tax stamp value of $2.45 million weighed in favor of a total valuation greater than $700,000. It next explained that Easterwood’s calculation was the most reliable because he was the only expert to account for the property’s infrastructure improvements and electrical capacity that allowed the property to be used to mine bitcoin. The bankruptcy court thus accepted Easterwood’s conclusion that the highest and best use for the property was as a bitcoin mining operation and that the property was a special purpose property. The bankruptcy court also noted that the purchaser bought the property to use for bitcoin mining and used it for that purpose. Applying the cost approach, the bankruptcy court found that, given the significant upgrades to the property that would be required to recreate a comparable bitcoin mining property, the value of the mining property was over $700,000.

Free access — add to your briefcase to read the full text and ask questions with AI

Bay Point Capital Partners II, LP v. Thomas Switch Holding, Llc, 113 F.4th 1304 (11th Cir. 2024).

113 F.4th 1304 (Bay Point Capital Partners II, LP v. Thomas Switch Holding, Llc) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Fall Creek One, LLC
M.D. North Carolina, 2025
Untitled Case
D. Puerto Rico, 2025
Montoya v. Ferguson
Tenth Circuit, 2024