Battle v. McArthur

49 F. 715, 1891 U.S. App. LEXIS 1658
CourtU.S. Circuit Court for the District of Eastern Missouri
DecidedDecember 7, 1891
StatusPublished
Cited by3 cases

This text of 49 F. 715 (Battle v. McArthur) is published on Counsel Stack Legal Research, covering U.S. Circuit Court for the District of Eastern Missouri primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Battle v. McArthur, 49 F. 715, 1891 U.S. App. LEXIS 1658 (circtedmo 1891).

Opinion

Thayer, District Judge.

Two questions are presented in this base which do not arise in either of the other cases just decided, — Lewis v. Railway Co., 49 Fed. Rep. 708, and Summers v. Same, Id. 714.

[716]*7161. In the first place, the railway company contends that these plaintiffs did not bring their suit against it within the period limited by law, and that their alleged lien was for that reason lost. The court concludes that this point is well taken. So far as the railway company is concerned, the suit is simply one to enforce a lien against the property of the company located in this state, which lien exists, if at ally, by virtue of local laws. Vide article 4, c. 47, Rev. St. Mo. 1879. These plaintiffs have no lien against the property of the railway company, either at common law or in equity; nor have they any right of action against the railway company, except such as is given by the Missouri statute creating a lien. In other words, the proceeding, as against the company, is purely statutory, and, to be effectual, must have been brought in the manner and within the period prescribed by the laws of this state. The federal courts can enforce liens created by local laws, hut they will only do so where the proper steps have been taken under such laws to render them enforceable in the state courts. To entitle a railroad contractor to a lien under the laws of this state, the lien must he filed “within ninety days next after the completion of the work, or after the materials were furnished,” (section 3202, Rev. St. Mo. 1879;) and all actions to enforce such liens must be commenced “within ninety days after filing the lien, and prosecuted without unnecessary delay to final judgment,” (section 3205, Id.) . As if to render the injunction more emphatic, section 3205 further declares that “no lien shall continue to exist * * * for more than ninety days after the lien shall be filed, unless within that time an action shall be instituted thereoni * * *” Now, it cannot be admitted that a railroad contractor may file any number of liens for the same labor and materials, and against the same property, within the 90 days after his work is completed, and subsequently elect on which of the liens so filed he will bring suit. An account for work and materials, when filed with the clerk of the circuit court of any county through which the railroad runs, operates to fix a definite charge upon the property outside of as well as within the county, for the sum stated in the account. It operates as a mortgage upon the entire line of road within this state, and is even more far-reaching in its effects than a mortgage or other incumbrance. Fide section 3201, Id. In the very nature of things, successive liens for the same labor and materials cannot he filed. The filing of one account that is good and sufficient to create a lien under the statute and satisfy its requirements exhausts the contractor’s power to incumber the property. The first good and sufficient lien so filed, sets the statute of limitations in operation, and, unless suit is brought within 90 days thereafter, the lien ceases to exist by the express provisions of the statute. It is unnecessary to decide whether a lien account, when filed, may be corrected in matters of mere detail by subsequent' amendments, filed within the 90 days allowed for filing a lien, for, even if such amendments are permissible, they should obviously be filed in the same county where the original account is recorded; and, in any «vent, the time limited for bringing suit must be computed from the date of the first filing. The amendments would take effect, by relation [717]*717as of that day, if it is permissible to amend such statements of account. The construction which the court thus gives to the railroad lien law seems to he the only reasonable interpretation of the statute, and it is also the construction heretofore placed upon the local mechanic’s lieu law by the supreme court of this state. Mulloy v. Lawrence, 31 Mo. 583; Davis v. Schuler, 38 Mo. 24. It is proper to add, in this connection, that the mechanics’ lien law was passed in the year 1857, the railroad lien law in 1873, and it is a well-known fact of local history that the later law, in all of its essential features, was modeled after the former, so that it may bo safely assumed that the supreme court of the state would construe the railroad lien law as this court construes it. Inasmuch, therefore, as the record in this case shows that a good and sufficient lion account was filed by Battle & Cameron in Scotland county on June 4, 1888, and that no suit to enforce such lien was instituted until September 22,1888, the lien had ceased to exist before this action was instituted, and these plaintiffs are entitled to no relief as against the railway company.

2. McArthur Bros., (against whom there may be a recovery in this suit notwithstanding the failure of the lien,) on their part, insist that .hey have made a settlement with Battle & Cameron which is final and conclusive. The facts bearing on that issue are found to be as follows: The controversy concerning loose rock classification was one which arose early in the progress of the work, and continued to the end. Very soon after that controversy arose (certainly as early as July 1, 1887) these plaintiffs, as well as other subcontractors, became aware of the mariner in which the amount of loose rock was being estimated by the engineers; that is to say, they knew that the amount was being estimated on the percentage theory, and that the engineers regarded the plowing test as applicable to hardpan, cemented gravel, etc. The court cannot conceive it to be possible, in view of all the facts and circumstances of the case, that they did not have such information for some months prior to January 1, 1888. Those plaintiffs made numerous complaints after May, 1887, with respect to the quantity of loose rock allowed in the various monthly estimates. They appear, on one occasion at least, to have distinctly made the claim that hardpan should be estimated as loose rook without reference to the plowing test, although, as a rule, their complaints seem to have been directed rather to the amount of the allowance than to the method of estimation. Such complaints as Battle & Cameron addressed to McArthur Bros, the latter firm likewise made to the railway company, sometimes in even more forcible language. McArthur Bros, were equally interested in securing a more liberal classification, and they seem to have made an honest effort on all occasions to accomplish that result. Thus matters stood until the work was practically concluded. It admits of no doubt that a conference was held between Battle & Cameron and McArthur Bros., after the work was. about finished, with a view of ascertaining what percentage of loose rock in the classification of certain cuts on the line of plaintiffs’ work would be satisfactory to them, or would bo accepted as a settlement of the existing controversy. There can be no doubt, I think, that Battle & Cameron at [718]*718that conference' agreed to a certain classification’, which was put in the form, of a tabulated statement, showing the percentage of loose rock claimed in the several cuts, and this statement was undoubtedly forwarded to the chief engineer of the railway company by McArthur Bros. The percentage of loose-rock classification thus demanded was not allowed, but it caused the chief engineer to raise the classification some 20 per cent., and that increase entered into the final estimate. When the final estimate was received, McArthur Bros, exhibited it to the plaintiffs. The latter were not satisfied, and disputed its accuracy.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Schwarz & Gottlieb, Inc. v. Marcuse
165 P. 1015 (California Supreme Court, 1917)
Clarke v. Heylman
80 N.Y.S. 794 (Appellate Division of the Supreme Court of New York, 1903)
Chicago, M. & St. P. Ry. Co. v. Clark
92 F. 968 (Second Circuit, 1899)

Cite This Page — Counsel Stack

Bluebook (online)
49 F. 715, 1891 U.S. App. LEXIS 1658, Counsel Stack Legal Research, https://law.counselstack.com/opinion/battle-v-mcarthur-circtedmo-1891.