Barnes v. District of Columbia

37 Ct. Cl. 342, 1902 U.S. Ct. Cl. LEXIS 89, 1900 WL 1515
CourtUnited States Court of Claims
DecidedMarch 31, 1902
DocketD. C. No. 47
StatusPublished

This text of 37 Ct. Cl. 342 (Barnes v. District of Columbia) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Barnes v. District of Columbia, 37 Ct. Cl. 342, 1902 U.S. Ct. Cl. LEXIS 89, 1900 WL 1515 (cc 1902).

Opinion

Peelle J.,

delivered the opinion of the court:

This action is founded upon the act June 22, 1880 (1 Supp. Rev. Stat., 562), known as the District of Columbia claims act, and grows out of two written contracts, Nos. 264 and 413, entered into by the claimant with the board of public works of said District, April 29 and July 23, 1872, as authorized bjr the act of February 21, 1871 (16 Stat. L., 427), and also upon verbal agreements entered into in 1874 and thereafter with the Commissioners of said District.

Prior to the execution of the contracts, to wit, September 26, 1871, the board of public works, by entry or memoranda on their records, had fixed the price of grading for old gravel [357]*357streets to a depth of 2 feet below the surface at iO cents per cubic yard; January 22, 1872, 30 cents per cubic yard for grading, including the hauling of the excavated material, not to exceed 200 feet, and for each additional 200 feet 1 cent additional per cubic yard beyond the first 200 feet.

And after the execution of said contracts, to wit, July 15, 1873, said board of public works, by like entiy, fixed the price of hauling excavated material at 1J cents per cubic yard for every 100 feet hauled over the first 200 feet since June 1, 1873; and thereafter, by like entry September 27, 1873, the board made said rate applicable to “all work done since Jan-' nary 1, 1873.”

Contract 264 was awarded to claimant by the board, as set forth in their records, at the rates so established, of which the claimant was notified; but by mistake in drafting the contract the rate of 40 cents for grading old graveled streets to a depth of 2 feet below the surface was omitted therefrom, and the board of public works and the claimant, by mutual mistake, executed the contract without observing said omission.

Though the rate of 40 cents for old graveled streets was fixed prior to the date of the execution of contract 413, and though the clerk'of the board notified claimant that said contract had been awarded to him at board rates, no entry was made by the board on their records to that effect, and as no mutual mistake is otherwise shown in that respect the claimant is not entitled to a re-formation of contract 413.

But as to contract 264, wherein the records of the board show that the same was awarded at board rates, and by mutual mistake the rate of 40 cents for old graveled streets was omitted therefrom, the claimant is entitled in that respect to a re-formation of his contract, and the same is decreed accordingly.

By the terms of the contracts aforesaid the claimant agreed to furnish at his own cost and expense all the necessary materials and labor, and among other things to grade the streets therein named, including North Carolina avenue, as stated in contract 264, at the price of 30 cents for each and every cubic yard of earth, sand, or gravel excavated and hauled a distance not exceeding 200 feet, and 1 cent additional per cubic yard for every 200 feet hauled beyond that distance, [358]*358and 40 cents per cubic yard for old graveled streets to a depth of 2 feet, as provided by said contract 264 so re-formed.

Although the rates thus fixed by the board, at 40 cents per cubic yard for old graveled streets and li cents per cubic yard for every 100 feet hauled over 200 feet, were not made a part of contract 413, the claimant was paid said rates for the work done thereunder as set forth in the counterclaim, and for the difference between the rates so paid and those specified in the original written contract the defendants interposed their counterclaim.

In the former trial of the case the controversy was as to the quantity and classification of the excavated material on North Carolina avenue, and as to whether the prices specified in the written contract should control. On the issues thus joined the.case was tried and findings of fact and conclusions of law thereon were filed, together with an opinion by the late Chief Justice Richardson, which resulted in a judgment on the counterclaim in favor of the District of Columbia for $11,264.58. (22 C. Cls. R., 366.)

On the question as to whether the court can “enforce claims founded upon these memoranda of the board of public works,” and whether the board can legally pay the rate so fixed, the court said: “In the numerous cases which have been before us under the District claims act we have uniformly and unanimously held otherwise.” The numerous authorities in support of that statement are cited.

It was further said in the opinion, “ when a statute provides how contracts by public officers shall be made, an entire or material departure from such requirements, though sufficient at common law to bind the parties, renders the proceedings void and of no effect as obligations on either side. It has been so decided by the Supreme Court in the South Boston Iron Company case (118 U. S., 37), affirming the judgment of this court (18 C. Cls. R., 165). In that case the statute passed upon by the court is in language much less mandatoiy than the one we are now considering, and there were offers and. acceptances in writing, signed separately bjr the parties, but the court held that they did not constitute a contract within the terms of the statute.”

In the findings filed at that time only 63,816 cubic yards of [359]*359grading was found to have been done on North Carolina avenue, although the four separate measurements made by the engineer officers of the District of the excavation therein as set forth in items 13, 15, 18, and 20 show that the claimant excavated 97,366 cubic yards, of which 61,573 cubic yards, as shown in finding vii, were excavated under the verbal agreement with the Commissioners of the District that the claimant should be paid the board rates therefor; and the agreement thus made was after the claimant had performed his original contract, 261, in excavating about 32,793 cubic yards to bring North Carolina avenue to its then established grade.

At the former hearing the claimant was denied the rate of 60 cents per cubic yard for the excavation of stiff clay on North Carolina avenue on the ground, as stated in the opinion of the court, that “the stiff clay, which is one kind of earth, rendered the grading in some places, no doubt, more difficult than it would have been had the earth been of a lighter material, but by the sixth article'of contract 261 it was agreed, among other things, that all loss arising out of the nature of the work to be done, or from any unforeseen obstructions or difficulties encountered in the prosecution of the same, should be sustained by the contractor.'1

That ruling was baseid on the finding then made that the stiff-clay excavation was done at the written contract rate of 30 cents per cubic yard, the contractor agreeing to sustain any unforeseen obstructions or difficulties encountered in the prosecution of the work; but as the excavation of the stiff clay was done under the verbal agreement with the Commissioners in 1871, long after the claimant had performed his original contract 261, he is entitled to the rate therefor then established and paid to other contractors for like work, as set forth in finding vm, which rate we find was reasonable and allow, as set forth in item 26, finding ix.

We have also added to the former finding of work done on North Carolina avenue the excavation under the sidewalks and carriageway, including the haul of the excavated material at li cents for every 100 feet hauled, as set forth in item 27, finding ix.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

South Boston Iron Co. v. United States
118 U.S. 37 (Supreme Court, 1886)
Barnard v. District of Columbia
127 U.S. 409 (Supreme Court, 1888)
Campbell v. District of Columbia
18 Ct. Cl. 193 (Court of Claims, 1883)
Barnes v. District of Columbia
22 Ct. Cl. 366 (Court of Claims, 1887)
Eslin v. DisTrict of Columbia
29 Ct. Cl. 370 (Court of Claims, 1894)

Cite This Page — Counsel Stack

Bluebook (online)
37 Ct. Cl. 342, 1902 U.S. Ct. Cl. LEXIS 89, 1900 WL 1515, Counsel Stack Legal Research, https://law.counselstack.com/opinion/barnes-v-district-of-columbia-cc-1902.