Barnes v. . Brown

29 N.E. 760, 130 N.Y. 372, 42 N.Y. St. Rep. 536, 85 Sickels 372, 1892 N.Y. LEXIS 939
CourtNew York Court of Appeals
DecidedJanuary 20, 1892
StatusPublished
Cited by24 cases

This text of 29 N.E. 760 (Barnes v. . Brown) is published on Counsel Stack Legal Research, covering New York Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Barnes v. . Brown, 29 N.E. 760, 130 N.Y. 372, 42 N.Y. St. Rep. 536, 85 Sickels 372, 1892 N.Y. LEXIS 939 (N.Y. 1892).

Opinion

Bradley, J.

The main controversy has relation to the rule or measure of damages applicable to the breach of the contract upon which this action was founded. "While the plaintiff claims that damages cannot be less than two hundred thousand dollars and interest, it is insisted on the part of the defense that they were only nominal. Before proceeding to the consideration of the question in that respect,, reference may properly be made to the facts out of which the alleged claim arose. The Hew York City Central Underground Bailway Company was organized under an act incorporating it and *379 authorizing the company to construct and operate an underground railway in the city of Hew York, passed in 1868 and amended in 1869. The authorized capital stock of the company was ten millions dollars. At the time the contract of March 26, 1872, was made, the plaintiff was president of the company. He then had some claims against it; and only one hundred and seventeen shares of capital stock had been issued, of which he held sixty-three shares. By the transfer of the sixty shares to Brown and Seligman, they took the control of the organization of the company. The amendments to the charter then pending in the legislature did not become a law, and consequently it was optional with them to either retain their purchase and pay, or surrender what they had received and put an end to the contract. They, however, concluded to treat it as effectual and assumed the undertaking to perform, and afterwards did pay to the plaintiff the twenty-seven thousand and five hundred dollars, and did deliver to the plaintiff certificates of two thousand shares of the capital stock of the company. This was, apparently, full performance, but in fact was not, because that so delivered was not paid stock. And when this was discovered by the plaintiff he offered to return the certificates and demanded such as he was entitled to. Further performance was refused, and this action followed. The only question as against the defendant Brown was one of damages, and the referee found that at the time when he and Seligman undertook to deliver the stock to plaintiff it had no actual or market value, and determined that he was entitled to recover nominal damages only. The stock certainly had no market value. Hone was in the market. This finding and conclusion were challenged by the plaintiff’s exceptions. By reference to the condition of the company it is seen that the total amount of money received by it on account of subscriptions to its stock was five thousand seven hundred dollars, and that was received in 1869 and 1871. The other credits to the capital stock account were in demand loans and special services rendered the company. The various efforts prior to 1872 were unsuccessfully made to raise money for the *380 purpose of construction of the railway, and the reason why the bonds of the company could not he negotiated was that it had been unable to obtain subscriptions to its capital stock to pay for right of way. The land and consequential damages incident to the construction of the railway were estimated at five millions dollars; and the expenditures by the company for work done towards construction and for land and land damages did not exceed four thousand dollars. The indebtedness of the company was about three hundred and fifty thousand dollars. This was in general terms the situation of the company when the contract of March 26, 1872, was made'; and it was known as well to Brown and Seligman as to the plaintiff. Whatever of value they took by the contract was in the franchise of the company, and was dependent upon the use which could be made of it by way of the construction and operation of an underground railway. While the futility of the enterprise tended to show that it never had any actual value, there evidently was hope and expectation of success entertained by Brown and Seligman when they elected to retain the benefit of the contract, and it is in that view insisted by the plaintiff that the stock then had a value which to him may at that time have been available, although later it turned out to have had none, and, therefore, he lost whatever he may have realized by its conversion if it had in due time been delivered to him. There is apparently some force in this suggestion, but it is entirely speculative, assuming that the stock then in fact had no actual value as well as no market value. There was some conflict in the expert evidence upon the subject founded upon the situation of the company. While that on the part of the defendants was that the stock had no value, that of the witnesses called by the plaintiff was to the effect that it was as the situation then appeared, worth par. It may be observed that the plaintiff held the stock represented by the certificate so delivered to him until about September 1, 1874, upon the assumption that it was full paid stock before his discovery that it was otherwise.

The finding of the referee that the stock had neither actual *381 nor market value was supported by evidence, and for the purpose of this review must be deemed conclusive. But it is, insisted by the learned counsel for the plaintiff that the plaintiff should nevertheless have recovered the two hundred thousand dollars and interest upon it because he was entitled to the stock or to a sum which it would cost to obtain it. As a general rule, the damages which a party is entitled to recover against another for a breach of contract are such as will indemnify him for the loss he has suffered by the default. And it is with a view to that result that the rules for ascertaining and awarding damages have been adopted. The purpose-of the rule in that respect is to leave the party in no worse,, and place him in no better, condition than he would have been if the act or default complained of had not been committed.

It was with a view to such measure of relief, and the adoption of a rule to accomplish it, that the doctrine which gave the highest market value up to the time of the trial as the measure of damages for conversion of property of' fluctuating value, as held in Markham v. Jaudon (41 N. Y. 235) and some prior cases, was overruled in Baker v. Drake (53 N. Y. 211), and the market value for a reasonable time within which to replace the property was adopted as furnishing the guide to the proper measure of damages and the more satisfactory means of indemnity. In that case the defendants, pursuant to an arrangement with the plaintiff, had purchased stocks to hold and carry subject to his order, so long as he kept his margin good. The defendants disposed of the stock in violation of the agreement. And the court there held, substantially, that an amount sufficient to indemnify a party injured for the loss, naturally, reasonably and proximately resulting from the act complained of, and which a proper degree of prudence on the part of the complainant would not have averted, is the proper measure of recovery when punitive damages are not allowable. And that the advance in the market price of the stock, from the time of the sale up to a reasonable time to replace it after the plaintiff received notice of the sale, would afford a complete indemnity.”

*382 The principle upon which the determination of Baker v. Drake

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Gould v. Adams
264 A.D.2d 758 (Appellate Division of the Supreme Court of New York, 1999)
Butterfield v. Metal Flow Corp.
462 N.W.2d 815 (Michigan Court of Appeals, 1990)
Kenford Co. v. County of Erie
108 A.D.2d 132 (Appellate Division of the Supreme Court of New York, 1985)
Modu Craft, Inc. v. Liberatore
89 A.D.2d 776 (Appellate Division of the Supreme Court of New York, 1982)
Pacheco v. Heussler
56 A.D.2d 85 (Appellate Division of the Supreme Court of New York, 1977)
Raymond Le Chase, Inc. v. Vincent Buick, Inc.
77 Misc. 2d 1024 (New York Supreme Court, 1974)
Long Island Lighting Co. v. City of Glen Cove
64 Misc. 2d 768 (New York Supreme Court, 1970)
Georgian Press, Inc. v. Hill
180 Misc. 548 (City of New York Municipal Court, 1943)
Dallas Dome Wyoming Oil Fields Co. v. Brooder
97 P.2d 311 (Wyoming Supreme Court, 1939)
Central Hanover Bank & Trust Co. v. Vernon Estates, Inc.
238 A.D. 565 (Appellate Division of the Supreme Court of New York, 1933)
Simon v. Linden
106 Misc. 387 (City of New York Municipal Court, 1919)
Trumpf v. Shoudy
164 N.W. 454 (Wisconsin Supreme Court, 1917)
Parry v. Parry
92 Misc. 490 (New York Supreme Court, 1915)
Vos v. Child, Hulswit & Co.
137 N.W. 209 (Michigan Supreme Court, 1912)
Peek v. Steinberg
124 P. 834 (California Supreme Court, 1912)
Crichfield v. Julia
147 F. 65 (Second Circuit, 1906)
Latz v. Blumenthal
50 Misc. 407 (New York Supreme Court, 1906)
Doyle v. Burns
99 N.W. 195 (Supreme Court of Iowa, 1904)
Potts v. . Dounce
66 N.E. 4 (New York Court of Appeals, 1903)
Potts v. Baldwin
67 A.D. 434 (Appellate Division of the Supreme Court of New York, 1901)

Cite This Page — Counsel Stack

Bluebook (online)
29 N.E. 760, 130 N.Y. 372, 42 N.Y. St. Rep. 536, 85 Sickels 372, 1892 N.Y. LEXIS 939, Counsel Stack Legal Research, https://law.counselstack.com/opinion/barnes-v-brown-ny-1892.