Barletta Heavy Division, Inc. v. Erie Interstate Contractors, Inc.

778 F. Supp. 2d 109, 2011 U.S. Dist. LEXIS 7871, 2011 WL 309664
CourtDistrict Court, D. Massachusetts
DecidedJanuary 27, 2011
DocketCivil Action 09-10143-NMG
StatusPublished
Cited by2 cases

This text of 778 F. Supp. 2d 109 (Barletta Heavy Division, Inc. v. Erie Interstate Contractors, Inc.) is published on Counsel Stack Legal Research, covering District Court, D. Massachusetts primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Barletta Heavy Division, Inc. v. Erie Interstate Contractors, Inc., 778 F. Supp. 2d 109, 2011 U.S. Dist. LEXIS 7871, 2011 WL 309664 (D. Mass. 2011).

Opinion

MEMORANDUM & ORDER

GORTON, District Judge.

This is a breach of contract action arising out of two related contracts. Plaintiff Barletta Heavy Division, Inc. (“Barletta”) brought suit against defendants Erie Interstate Contractors, Inc. (“Erie”), Phoenix Development and Construction, Inc. (“Phoenix”), Gregory Zafirakis (“Gregory”), Steven Zafirakis (“Steven”), Steven Moutsastos (“Moutsastos”), Markos Bahas (“Bahas”) and Erie Painting and Maintenance, Inc. (“EPM”). 1 Gregory and Bahas are the Chief Executive Officers of Erie. Gregory’s son, Steven, is the principal owner of Phoenix and Moutsastos is the President of Phoenix.

Plaintiff seeks a declaratory judgment that it is entitled to retain equipment owned by the defendants pursuant to a security agreement (Count I) and that the defendants are liable for breach of a subcontract (Count II), unjust enrichment (Count III), violation of the Massachusetts Consumer Protection Act (Mass. Gen. Laws ch. 93A) (Count IV) and breach of the security agreement (Count V). Before the Court are the parties’ motions for summary judgment, the defendant’s motion for a hearing and the plaintiffs assented-to motion to strike its own jury demand.

1. Factual Background

Barletta was the general contractor on a project for Massport known as the “Pier Rehabilitation Project” in South Boston, Massachusetts (“the Project”). Barletta hired Erie as a subcontractor for the Project to provide labor, material and equipment to clean, prepare and paint a new and existing under-deck structural steel support system. Barletta and Erie entered into a subcontract agreement (“the Subcontract”) on July 21, 2006, by which Erie agreed to perform specified work and Barletta agreed to pay $2,211,515.

Erie began work on the Project in August, 2006 but soon experienced financial difficulty. Because of that difficulty and because Erie was behind schedule on its work, Barletta paid a number of Erie’s Project-related costs and taxes between January and September, 2007. Barletta maintains that it did so to keep the Project on track and to avoid a liquidated damages claim by Massport but that it never told Erie that it would not back charge for those payments. Erie responds that Barletta never indicated that it would impose back charges.

In late 2007, Erie’s Chairman, Gregory, made several requests to Barletta seeking additional cash that would allow Erie to continue work on the Project. After one such request, Barletta agreed to lend Phoenix, a related company, $150,000 pursuant to a Revolving Credit Promissory Note and a Security Agreement (“the Security Agreement”). The Security Agreement was entered into by Erie, Phoenix, and, in their individual capacities, Gregory, Steven, Moutsastos and Bahas (collectively “the Debtors”). 2 The Security Agreement provided Barletta with a blanket security interest in all of the Debtors’ assets as *112 collateral for any debts the Debtors owe to Barletta. Although the $150,000 loan to Phoenix was repaid in January, 2008, Barletta did not release the Debtors from their obligations under the Security Agreement at that time.

A few months later, Erie again informed Barletta that it was having financial difficulties. Barletta alleges that on March 20, 2008, Erie suspended all work on the Project because Barletta refused to pay Project-related costs incurred by Erie. In response to the work suspension, Barletta sent Erie a letter on March 24, 2008 terminating the Subcontract for non-performance and for failing to pay all debts for materials, labor and other items as required by the Subcontract. Barletta locked Erie out of the job site, retained Erie’s equipment and hired another company to complete the Project.

Barletta then brought this lawsuit seeking reimbursement for the costs and labor that it paid on Erie’s behalf. Barletta claims that Erie owes it $1,250,927 in back charges and additional Project costs chargeable to Erie because of Erie’s breach. The defendants respond that Erie and Barletta had a verbal agreement providing that Erie would complete the project so long as Barletta paid for all expenses related to the project including payroll, taxes, insurance, materials and supplies.

II. Procedural History

Barletta filed its complaint on January 30, 2009, along with a motion for a preliminary injunction prohibiting the defendants from transferring or disposing of any assets covered by the Security Agreement. At an initial hearing on March 6, 2009, the Court allowed the motion. After defendants later stated that they did not oppose its continuation, the preliminary injunction was extended for the duration of this litigation.

The defendants subsequently filed a counterclaim against Barletta, seeking a declaratory judgment stating that the Security Agreement is unenforceable and that Barletta did not have the right to seize their equipment. Furthermore, they allege 1) breach of the covenant of good faith and fair dealing, 2) conversion of the defendants’ equipment and assets, 3) a Chapter 93A violation, 4) breach of contract and 5) estoppel. The defendants also moved for a preliminary injunction seeking the return of unspecified equipment allegedly in the custody of Barletta. After the parties reported that they could not resolve the matter on their own, the Court issued a Memorandum and Order on May 15, 2009, 620 F.Supp.2d 158 (D.Mass.2009), denying the motion.

The defendants next moved to dismiss pursuant to a forum selection clause in the Subcontract. On December 29, 2009, 677 F.Supp.2d 373 (D.Mass.2009), the Court issued a Memorandum and Order denying that motion. In January, 2010, the plaintiff filed an emergency motion to modify the preliminary injunction, which the Court denied.

In June, 2010, the Court referred the case to alternative dispute resolution before Magistrate Judge Marianne B. Bowler but the parties were unable to resolve their differences. Thus, on October 26, 2010, the plaintiff moved for summary judgment, seeking judgment on liability on all counts. The defendants opposed the motion and filed a limited cross-motion for summary judgment. The defendants also move for a hearing on the plaintiffs motion.

On November 17, 2010, the plaintiff and EPM agreed to a partial stipulation of dismissal as to the claims and counterclaims asserted between them. On that *113 same day, the plaintiff filed an assented-to motion to strike and/or set aside jury demands because the parties have signed jury waivers.

III. Motion for Summary Judgment

A. Legal Standard

The role of summary judgment is “to pierce the pleadings and to assess the proof in order to see whether there is a genuine need for trial.” Mesnick v. Gen. Elec. Co., 950 F.2d 816, 822 (1st Cir.1991) (citation omitted). The burden is on the moving party to show, based upon the pleadings, discovery and affidavits, “that there is no genuine issue as to any material fact and that the moving party is entitled to judgment as a matter of law.” Fed.R.Civ.P.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
778 F. Supp. 2d 109, 2011 U.S. Dist. LEXIS 7871, 2011 WL 309664, Counsel Stack Legal Research, https://law.counselstack.com/opinion/barletta-heavy-division-inc-v-erie-interstate-contractors-inc-mad-2011.