Barletta Heavy Division, Inc. v. Erie Interstate Contractors, Inc.

677 F. Supp. 2d 373, 2009 U.S. Dist. LEXIS 122073, 2009 WL 5201732
District Court, D. Massachusetts·Decided December 29, 2009·No. Civil Action 09-10143-NMG·Published·Cited by 9 cases

Opinion

MEMORANDUM & ORDER

GORTON, District Judge.

This is a breach of contract action arising out of two related contracts. Plaintiff Barletta Heavy Division, Inc. (“Barletta”) brought suit against defendants Erie Interstate Contractors, Inc. (“Erie”), Phoenix Development and Construction, Inc. (“Phoenix”), Gregory Zafirakis (“Gregory”), Steven Zafirakis (“Steven”), Steven Moutsastos (“Moutsastos”), Markos Bahas (“Bahas”) and Erie Painting and Maintenance, Inc. (“EPM”). 1 Plaintiff seeks a declaratory judgment that it is entitled to repossess defendants’ equipment pursuant to a security agreement (Count I) and that the defendants are liable to it for breach of a subcontract (Count II), unjust enrichment (Count III), violation of the Massachusetts Consumer Protection Act (M.G.L. c. 93A) (Count IV) and breach of the security agreement (Count V). Various cross claims and counterclaims have also been filed. Before the Court is a motion to dismiss filed by all defendants except EPM (“the moving defendants”) based upon a forum selection clause in the subcontract.

I. Background

Barletta was the general contractor on a project for Massport known as the “Pier Rehabilitation Project” in Boston, Massachusetts (“the Project”). Barletta hired Erie as a subcontractor for the Project to provide labor, material and equipment to clean, prepare and paint a new and existing “under deck structural steel support system.” Barletta and Erie entered into a subcontract agreement (“the Subcontract”) on July 21, 2006, whereby Erie agreed to perform specified work and Barletta eventually agreed to pay $2,211,515.

Erie began work on the Project in August, 2006 but soon experienced financial difficulty. Because of that difficulty and because Erie was behind schedule on its work, Barletta paid a number of Erie’s Project-related costs and taxes between January and September, 2007. Barletta maintains that it did so to keep the Project on track and to avoid a liquidated damages claim by Massport but that it never told Erie that it would not back charge for *375 those payments. Erie responds that Barletta never indicated that it would so back charge.

In late 2007, Erie’s Chairman, Gregory, made several requests to Barletta seeking additional financing that would allow Erie to continue work on the Project. After one such request, Barletta agreed to lend Phoenix, a related company, $150,000 pursuant to a Revolving Credit Promissory Note and a Security Agreement (“the Security Agreement”). The Security Agreement was entered into by Erie, Phoenix and, in their individual capacities, Gregory, Steven, Moutsastos and Bahas (collectively “the Debtors”). 2 Because the Security Agreement provided Barletta with a blanket security interest in all of the Debtors’ assets, Barletta’s Subcontract with Erie became secured by all of those assets.

The $150,000 loan to Phoenix was apparently repaid in January, 2008 but Barletta did not release the Debtors from their obligations under the Security Agreement at that time. A few months later, Erie again informed Barletta that it was having financial difficulties. Barletta asserts that on March 20, 2008, Erie suspended all work on the Project allegedly because Barletta had reneged on its promise to pay Project-related costs incurred by Erie. Erie responds that it suspended work because of extreme high tides and the impending Easter Holiday. It also maintains that it informed Barletta that it would return to the project on March 25, 2008. On March 24, 2008, however, Barletta notified Erie by letter that it was terminating the Subcontract for non-performance.

II. Procedural History

Barletta filed its complaint on January 30, 2009, along with a motion for a preliminary injunction to prohibit the defendants from transferring or disposing of any assets covered by the Security Agreement. At an initial hearing on March 6, 2009, the Court allowed the motion. An injunction was entered on March 11, 2009, against the moving defendants and, after those defendants stated that they did not oppose its continuation, it was extended through the duration of this litigation.

In the meantime, the Court held two additional hearings related to preliminary injunction motions. On March 20, 2009, the moving defendants filed their own motion for a preliminary injunction, seeking the return of unspecified equipment allegedly in the custody of Barletta. The Court heard oral argument on the day the motion was filed and again on April 10, 2009. After the parties reported that they could not resolve the matter on their own, the Court issued a Memorandum and Order on May 15, 2009, denying the moving defendants’ motion for a preliminary injunction.

At the April 10 hearing, the Court also set various “fast-track” scheduling deadlines culminating in trial to start on February 1, 2010. On October 13, 2009, prior counsel for the moving defendants moved to withdraw, citing an irretrievable breakdown in the attorney-client relationship. Current counsel filed a notice of appearance on October 23, 2009, and the pending motion to dismiss four days later. Plaintiff filed its opposition on November 9, 2009. 3

*376 III. Analysis

A. Legal Standard

The moving defendants filed a motion to dismiss pursuant to the following forum selection clause in the Subcontract:

Any and all claims or disputes not specifically covered elsewhere in this Agreement arising out of or relating to this Agreement or breach thereof shall be decided, at the sole discretion of [Barletta], either by submission to (1) arbitration ... or (2) judicial decision by the Suffolk Superior Court in the Commonwealth of Massachusetts....

Because this provision refers to both arbitration and judicial involvement, it implicates potentially conflicting doctrines pertaining to the enforcement of forum selection clauses and arbitration rights. Those doctrines are considered in turn.

1. Forum Selection Clauses

Under First Circuit law, a motion to dismiss based upon a forum selection clause is treated as one alleging a failure to state a claim under Fed.R.Civ.P. 12(b)(6). Silva v. Encyclopedia Britannica, Inc., 239 F.3d 385, 387 (1st Cir.2001). Accordingly, such a defense can be raised at any time before disposition on the merits and it is preserved against waiver prior to that time. Id. at 388; 5C Charles A. Wright & Arthur R. Miller, Federal Practice & Procedure § 1392 (3d ed. 2009).

Free access — add to your briefcase to read the full text and ask questions with AI

Barletta Heavy Division, Inc. v. Erie Interstate Contractors, Inc., 677 F. Supp. 2d 373, 2009 U.S. Dist. LEXIS 122073, 2009 WL 5201732 (D. Mass. 2009).

677 F. Supp. 2d 373 (Barletta Heavy Division, Inc. v. Erie Interstate Contractors, Inc.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related