Bangor Gas Company, LLC v. H.Q. Energy Services (US) Inc.

695 F.3d 181, 180 Oil & Gas Rep. 315, 2012 WL 4373685, 2012 U.S. App. LEXIS 20218
CourtCourt of Appeals for the First Circuit
DecidedSeptember 26, 2012
Docket12-1386
StatusPublished
Cited by24 cases

This text of 695 F.3d 181 (Bangor Gas Company, LLC v. H.Q. Energy Services (US) Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals for the First Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Bangor Gas Company, LLC v. H.Q. Energy Services (US) Inc., 695 F.3d 181, 180 Oil & Gas Rep. 315, 2012 WL 4373685, 2012 U.S. App. LEXIS 20218 (1st Cir. 2012).

Opinion

BOUDIN, Circuit Judge.

A pipeline owner — Bangor Gas Company, LLC (“Bangor”) — and a natural gas supplier — H.Q. Energy Services (U.S.) Inc. (“HQUS”) — entered into a contract for the transportation of HQUS’ natural gas. The parties later became embroiled in a dispute and submitted their dispute to binding arbitration. After the arbitrators issued a decision largely favorable to HQUS, Bangor sought to vacate the decision in the district court, failed, and has now brought this appeal.

HQUS, a wholly owned American subsidiary of the Canadian government-owned utility Hydro-Quebec, sells natural gas and electricity in the United States. Bangor provides services related to the natural gas industry in Maine. In 1999, Bangor entered into an agreement with HQUS (the “Agreement”) to build and operate a Bangor pipeline, later named the Bucks-port Pipeline, to deliver HQUS’ natural gas from an international pipeline nine miles away called the Maritimes Pipeline, owned and operated by Maritimes & Northeast Pipeline, LLC (“Maritimes”), to the Bucksport Energy Facility (an energy plant that served a paper mill).

The contract provided that HQUS’ gas would be delivered over the Bucksport Pipeline for fifteen years for a fixed annual charge of $1,150,662, paid by HQUS in monthly installments. However, Bangor did not connect the origin end of the Bucksport Pipeline directly to the existing *184 Maritimes Pipeline; instead, Bangor contracted to have Maritimes build a 410-foot lateral pipeline (the “Lateral”) that connected the Maritimes Pipeline to the Bucksport Pipeline and agreed that Bangor would pay Maritimes for the Lateral’s use pursuant to a tariff filed by Maritimes with the Federal Energy Regulatory Commission (“FERC”).

Bangor’s expert later explained that this was done for technical reasons relating to proximity to electric power lines. Nonetheless, the Lateral was not mentioned in the Agreement, and the Agreement’s language may suggest that the parties to it contemplated that the Bucksport Pipeline would directly connect to the Maritimes Pipeline. It was apparently not until 2006, six years after the Bucksport Pipeline opened, that HQUS learned of the Lateral and that the Bucksport Pipeline did not connect directly to the Maritimes Pipeline.

During this six-year period, HQUS paid the agreed upon rate to Bangor; Bangor in turn compensated Maritimes for the use of the short Lateral pipeline of whose existence HQUS was ignorant. This harmonious state of affairs began to dissolve when Bangor was itself acquired by a parent company which apparently concluded that Bangor’s compensation of Maritimes might be in violation of rules or policies of the FERC, the federal agency which now regulates much of the traffic in natural gas in the United States.

Under a FERC edict known as the “shipper-must-have-title” rule, a shipper of natural gas must hold title to the gas it is shipping. The rule is not a codified regulation but was announced by FERC in an adjudication of a specific dispute. 1 The aim of the rule is to prevent big natural gas distributors from buying up pipeline capacity that they do not need for shipment of their own gas and leveraging their market power by selling the capacity to third parties at excessive prices.

Bangor concluded that, as the party who controlled the capacity of the Lateral by virtue of its lease, it would be deemed under FERC’s nomenclature “the shipper” of gas traveling over the Lateral. And, as HQUS owned gas traveling through the Lateral, Bangor might be deemed in violation of the shipper-must-have-title rule. Bangor consulted with FERC with the result that, in 2007, FERC found that Bangor had violated the shipper-must-have-title rule with respect to the Lateral (as well as another pipeline), and approved a consent agreement by which Bangor paid a $1 million fine. Bangor Gas Co., LLC, 118 FERC ¶ 61,186 (2007).

Beginning in 2006, Bangor sought to comply with the rule by entering into “capacity releases” with HQUS in which HQUS would replace Bangor as the party who held capacity rights in the Lateral, and thus as the “shipper” on the Lateral. In the earliest of these capacity releases HQUS did not pay the costs of using the Lateral; but HQUS began paying those costs in August 2009 after Bangor threatened to place its capacity rights on the Lateral up for competitive bidding. Whether HQUS should pay became one of the two main issues in the ensuing dispute between the two companies.

The other dispute involved the costs for heater fuel to heat the gas at two points: at the connection between the Lateral and the start of Bucksport Pipeline, and at the end of the Bucksport Pipeline as the gas enters the energy plant. The latter satisfied a contractual obligation of Bangor to *185 deliver the gas at 80°F or above. The Agreement was silent on who was to pay for heating. Bangor had been paying for the heater fuel since the inception of the agreement, but in 2009 Bangor asserted that HQUS should pay those costs.

The Agreement provided that irreconcilable disputes would be submitted to binding arbitration, and Bangor initiated arbitration on December 6, 2010. Each party selected one arbitrator, and those two arbitrators chose a third arbitrator; all three were experienced in the energy industry, and one was a former FERC Commissioner. Bangor sought to have HQUS pay both the Lateral costs and the heater fuel costs. HQUS denied responsibility and counterclaimed for a reimbursement of payments it had made for the Lateral since 2009. 2

The arbitration panel reviewed briefs, written testimony and documents submitted by the parties, and held a three-day hearing. On September 1, 2011, the panel issued a written award that was largely favorable to HQUS, deciding that Bangor was responsible for paying Maritimes for use of the Lateral. As to heater costs, the arbitrators placed the future cost burden for heating at the delivery end upon HQUS but declined to order it to pay for past heating.

On the Lateral costs issue, the arbitrators noted that the Agreement contemplated that the Bucksport Pipeline would connect to the Maritimes Pipeline, which meant that the parties thought that HQUS was purchasing for its original monthly payment transportation of gas all the way from the Maritimes Pipeline to the energy plant. The panel inferred from Bangor internal documents that the contract rate in Bangor’s bid to HQUS already accounted for the cost of transporting gas on the 410 feet that comprised the Lateral and the cost of the junction point meter installed by Maritimes, Thus, forcing HQUS to pay Maritimes in addition to paying Bangor would unjustly require HQUS to pay twice for the transportation and meter.

The panel acknowledged that the shipper-must-have-title rule posed difficulties but the panel adopted a two-part solution: (1) Bangor would continue to release its capacity on the Lateral to HQUS, and HQUS would pay Maritimes for use of the Lateral, but (2) Bangor would reimburse HQUS for the Lateral costs in the form-of a comparably reduced rate for use of the Bucksport Pipeline. In addition, the panel ordered Bangor to reimburse HQUS for costs that HQUS (under threat) had already paid to Maritimes.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Untitled Case
D. Massachusetts, 2026
James Warfield v. ICON Advisers, Inc
26 F.4th 666 (Fourth Circuit, 2022)
Ebbe v. Concorde Inv. Servs., LLC
953 F.3d 172 (First Circuit, 2020)
Ebbe v. Concorde Inv. Servs., LLC
392 F. Supp. 3d 228 (District of Columbia, 2019)
Axia Netmedia Corp. v. Mass. Tech. Park Corp.
381 F. Supp. 3d 128 (District of Columbia, 2019)
Photographic Illustrators Corp. v. Osram Sylvania, Inc.
366 F. Supp. 3d 160 (District of Columbia, 2019)
Nowak v. Pennsylvania Professional Soccer, LLC
156 F. Supp. 3d 641 (E.D. Pennsylvania, 2016)
Raymond James Financial Services, Inc. v. Fenyk
780 F.3d 59 (First Circuit, 2015)

Cite This Page — Counsel Stack

Bluebook (online)
695 F.3d 181, 180 Oil & Gas Rep. 315, 2012 WL 4373685, 2012 U.S. App. LEXIS 20218, Counsel Stack Legal Research, https://law.counselstack.com/opinion/bangor-gas-company-llc-v-hq-energy-services-us-inc-ca1-2012.