Balestrieri v. Bell Asbestos Mines, Ltd.

544 F. Supp. 528, 1982 U.S. Dist. LEXIS 13891
CourtDistrict Court, E.D. Pennsylvania
DecidedJuly 27, 1982
DocketCiv. A. 82-1480
StatusPublished
Cited by27 cases

This text of 544 F. Supp. 528 (Balestrieri v. Bell Asbestos Mines, Ltd.) is published on Counsel Stack Legal Research, covering District Court, E.D. Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Balestrieri v. Bell Asbestos Mines, Ltd., 544 F. Supp. 528, 1982 U.S. Dist. LEXIS 13891 (E.D. Pa. 1982).

Opinion

MEMORANDUM AND ORDER

SHAPIRO, District Judge.

BACKGROUND

Plaintiffs instituted this action in the Court of Common Pleas, Montgomery County, Pennsylvania, on January 29, 1982. The complaint charged the defendants with tortious conduct which caused plaintiff, Americo A. Balestrieri, to contract a disease resulting from exposure to asbestos.

The complaint was served on defendants on these dates:

1) GAF Corporation 2/18/82
2) Johns-Manville Corporation 2/19/82
3) The Celotex Corporation 2/19/82
4) Manville Corporation 2/19/82
5) Johns-Manville Sales Corporation 2/26/82
6) Bell Asbestos Mines, Ltd. 3/ 3/82
7) Asbestos Corporation, Ltd. 3/ 3/82
8) Johns-Manville Andante Canada, Inc. 3/ 3/82
9) Carey Canada, Inc. 3/ 3/82

Bell Asbestos Mines, Ltd. (“Bell”), filed a petition for removal to federal court on April 1, 1982, 29 days after service but 42 days after the first defendant, GAF Corporation (“GAF”) was served. All defendants joined in the April 1, 1982 removal petition and the case was removed to this court.

On April 9, 1982, plaintiffs filed a motion to remand under 28 U.S.C. § 1447(c), on the ground that the removal petition was untimely because it was not filed within 30 days of service on GAF, even though all defendants subsequently consented to removal.

Defendants have responded that GAF’s failure to timely remove within 30 days was merely a technical defect cured when it consented to Bell’s petition, and not ground for remand.

DISCUSSION

The time limit for removal of civil cases to federal district court is found in 28 U.S.C. § 1446(b), which provides that:

[t]he petition for removal of a civil action or proceeding shall be filed within thirty days after the receipt by the defendant, through service or otherwise, of a copy of the initial pleading setting forth the claim for relief upon which such action or proceeding is based, [emphasis added]

Crompton v. Park Ward Motors, Inc., 477 F.Supp. 699, 701 (E.D.Pa.1977). This 30-day limitation is mandatory and cannot be extended by the court. Furthermore, this provision has consistently been interpreted to require all served defendants, unless nominal parties only, to join in the removal petition within the 30-day period. Anuzelli v. Carey Canadian Mines, Ltd., et al., No. 81-115 (E.D.Pa. June 4, 1981); Royster v. Carey Canadian Mines, Ltd., et al., No. 80-121 (E.D.Pa. February 26, 1981); Crompton, supra; Sun Oil Company of Pennsylvania v. Department of Labor and Industry, 365 F.Supp. 1403 (E.D.Pa.1973).

Where all defendants have not timely joined in a petition to remove in other asbestosis suits before this court, the cases have been remanded to state court, Mustacchio v. Bell Asbestos Mines, Ltd., No. 81-4282 (E.D.Pa. January 27, 1982, Ditter, J.); Anuzelli, supra (Luongo, J.); Stella Dolewa v. Carey Canadian Mines, Ltd., et al., No. 81-4171 (E.D.Pa. January 29, 1982, Becker, J.); Smith v. Carey Canadian Mines, Ltd., et al., No. 80-4988 (E.D.Pa. May 27, 1981), and Pierce v. Carey Canadian Mines, Ltd., et al., No. 81-120 (E.D.Pa. May 27, 1981, Bechtle, J.), except when plaintiff has waived the defect in the manner of removal by affirmatively invoking federal jurisdiction. Monaco v. Carey Canadian Mines, Ltd., 514 F.Supp. 357 (E.D.Pa.1981). See also, Intercoastal Refining Co., Inc. v. Jalil, 487 F.Supp. 606 (S.D.Tex.1980); Friedrich v. Whittaker Corp., 467 F.Supp. 1012 (S.D.Tex.1979); Sun Oil Co., supra at 1407. There has been no waiver in this case.

*530 Defendants’ argument would permit a defendant, having lost the opportunity to remove by not acting within 30 days to join in another defendant’s removal petition and thus effect a removal any time within 30 days of the date of service on the defendant last served. There is nothing in the statute to support this interpretation of § 1446(b).

Failure of a defendant to seek removal within the thirty day [sic] time limitation may not be cured retroactively by consenting to and joining a subsequently served defendant’s petition for removal.

Friedrich, supra at 1013.

If the first five defendants served in this case wished to remove, it was incumbent upon them to file a removal petition within 30 days of the time they were served. By failing to do so, they waived their ability to consent to the removal petition subsequently filed by Bell. This decision is in keeping with the strict construction to be accorded the federal removal statute. La Chemise Lacoste v. Alligator Co., Inc., 506 F.2d 339, 344 (3d Cir. 1974), citing American Fire and Casualty Co. v. Finn, 341 U.S. 6, 10, 71 S.Ct. 534, 538, 95 L.Ed. 702 (1951) (emphasizing the “restrictive policy of Congress against removal”).

Defendants rely on the possible unfairness of the result suggested in 14 Wright & Miller § 3732, 1980 pocket part:

.. . when some of the defendants are served after the first defendant served has waived the removal right by not exercising it within the statutory period, the subsequently served defendants are deprived of the opportunity to persuade the first defendant to join in the removal petition. (Emphasis added).

However, here the removing defendants Bell, Asbestos Corporation, Ltd., JohnsManville Amiante Canada, Inc., and Carey Canada, Inc., were served within 30 days of service on all other defendants. Therefore, the defendants who removed did have an opportunity to persuade all defendants to join in a timely removal petition. This removal was untimely and accordingly the motion for remand is granted.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

BROWN v. RITE AID CORPORATION
E.D. Pennsylvania, 2019
Boggs v. Harris
226 F. Supp. 3d 475 (W.D. Pennsylvania, 2016)
Bauer v. TRANSITIONAL SCHOOL DISTRICT, ST. LOUIS
88 F. Supp. 2d 999 (E.D. Missouri, 2000)
Yellow Cab Co. of Pittsburgh v. Gasper
994 F. Supp. 344 (W.D. Pennsylvania, 1998)
Luce v. Lloyd's of London
868 F. Supp. 625 (D. Vermont, 1994)
Ogletree v. Barnes
851 F. Supp. 184 (E.D. Pennsylvania, 1994)
Greensmith Co., Inc. v. Com Systems, Inc.
796 F. Supp. 812 (D. New Jersey, 1992)
Nasco, Inc. v. Norsworthy
785 F. Supp. 707 (M.D. Tennessee, 1992)
Roberson v. Orkin Exterminating Co., Inc.
770 F. Supp. 1324 (N.D. Indiana, 1991)
Mountain Ridge State Bank v. Investor Funding Corp.
763 F. Supp. 1282 (D. New Jersey, 1991)
Johnson v. Baltimore City Police Department
757 F. Supp. 677 (D. Maryland, 1991)
Collins v. American Red Cross
724 F. Supp. 353 (E.D. Pennsylvania, 1989)
McKinney v. BD. OF TRUSTEES OF MAYLAND COM. COLLEGE
713 F. Supp. 185 (W.D. North Carolina, 1989)
McKinney v. Board of Trustees of Mayland Community College
713 F. Supp. 185 (W.D. North Carolina, 1989)
Garside Ex Rel. Garside v. Osco Drug, Inc.
702 F. Supp. 19 (D. Massachusetts, 1988)
Dachenbach v. Pamida, Inc.
683 F. Supp. 1268 (S.D. Iowa, 1988)
Village Improvement Ass'n of Doylestown v. Dow Chemical Co.
655 F. Supp. 311 (E.D. Pennsylvania, 1987)
In Re Eagle Bend Development
61 B.R. 451 (W.D. Louisiana, 1986)

Cite This Page — Counsel Stack

Bluebook (online)
544 F. Supp. 528, 1982 U.S. Dist. LEXIS 13891, Counsel Stack Legal Research, https://law.counselstack.com/opinion/balestrieri-v-bell-asbestos-mines-ltd-paed-1982.