Balest v. Simmons

411 S.E.2d 576, 201 Ga. App. 605, 1991 Ga. App. LEXIS 1509
CourtCourt of Appeals of Georgia
DecidedOctober 23, 1991
DocketA91A1304
StatusPublished
Cited by15 cases

This text of 411 S.E.2d 576 (Balest v. Simmons) is published on Counsel Stack Legal Research, covering Court of Appeals of Georgia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Balest v. Simmons, 411 S.E.2d 576, 201 Ga. App. 605, 1991 Ga. App. LEXIS 1509 (Ga. Ct. App. 1991).

Opinions

Sognier, Chief Judge.

Tony Balest d/b/a Balest Construction Company brought suit against Kelvin J. Simmons and Audrey C. Simmons to recover a sum allegedly owed under a residential construction contract. The trial court granted summary judgment to the Simmonses on the ground that Balest executed an affidavit of final payment and therefore was precluded from recovering any additional payments. Balest appeals.

The contract at issue, executed on July 11, 1988, by appellant as contractor and appellees as owner, provided that appellant would construct a house for appellees in exchange for payment for all labor and materials (“estimated” to total $96,996) plus $15,000. The contract also obligated appellant to provide lien waivers from all subcontractors and suppliers prior to receipt of final payment.

During the course of construction, appellees paid appellant $110,600. A certificate of occupancy was issued on December 21, 1988. Appellant testified by deposition that a few days before the closing of appellees’ permanent loan, he informed them that he was owed approximately $18,000 for extra work performed pursuant to change orders issued during the project. At the January 4, 1989 closing, appellant executed a “Construction Loan Contractor’s Affidavit of Completion” which provided, inter alia, that appellant agreed “that all improvements on [appellees’] real estate are fully completed”; that “there are no unpaid bills of any nature for any improvements ... or any other work, labor or materials [provided to the project] at the direction of [appellant] or any agent of [appellant] except as disclosed below” (and nothing was disclosed in the space provided); and that “[appellant] makes this affidavit for the purpose of inducing [appellees’ lender] to disburse the balance of the loan heretofore granted to [appellees] . . . and for the purpose of inducing [appellees] to pay to [appellant] the balance due upon the contract price.” The lender then issued to appellees a check for $1,396 denominated as “final construction proceeds,” which appellees endorsed to appellant.

Two months later, appellant filed a claim of lien against appellees’ property and, within the statutory time limit, filed suit seeking to recover damages for breach of contract and to foreclose on the lien. The trial court granted appellees’ motion for summary judgment, ruling that appellant, by executing the affidavit providing that no bills remained unpaid without indicating that any additional payment was due and by receiving a check represented as final payment, waived [606]*606any right to recover under the statutory lien provisions.

1. In his first enumeration of error, appellant maintains the trial court erred by concluding that appellant, by executing the affidavit of payment, waived or dissolved his statutory lien rights. OCGA § 44-14-361 (a) (2) grants to general contractors a special lien on the real estate for which they furnish labor, services, or materials. This special lien may be dissolved under OCGA § 44-14-361.2, which provides in pertinent part:

(a) The special lien specified in [OCGA § 44-14-361 (a)] shall be dissolved if the owner, purchaser from owner, or lender providing construction or purchase money or any other loan secured by real estate shows that:
(1) The lien has been waived in writing by lien claimant; or
(2) (A) They or any of them have obtained the sworn written statement of the contractor . . . that the agreed price or reasonable value of the labor, services, or materials have [sic] been paid or waived in writing by the lien claimant; and
(B) When the sworn written statement was obtained or given as a part of a transaction:
(i) Involving a conveyance of title in a bona fide sale;
(ii) Involving a loan in which the real estate is to secure repayment of the loan; or
(iii) Where final disbursement of the contract price is made by the owner to the contractor
there was not of record, at the time of the settlement of the transaction a valid preliminary notice or claim of lien which had not been previously canceled, dissolved, or expired.

(a) OCGA § 44-14-361.2 authorizes an owner, seller, or lender to dissolve a lien upon showing either that (1) the contractor gave a written lien waiver; or (2) the contractor provided a sworn statement that the agreed price or reasonable value was paid or waived in writing, and at the time such a statement was given in connection with any of the transactions listed in (a) (2) (B) (i)-(iii) the contractor had not previously filed a valid preliminary notice or claim of lien. Accord Star Mfg. v. Edenfield, 191 Ga. App. 665-667 (2) (382 SE2d 706) (1989) (contractor’s affidavit held sufficient to dissolve subcontractor’s lien because affidavit had been given in conjunction with contractor’s receipt of final payment (OCGA § 44-14-361.2 (a) (2) (B) (iii)) and no lien had been filed at the time of payment to contractor). This court’s recent decision in Drywall Supply &c. v. Diversified Shelter &c., 198 Ga. App. 549, 550-551 (2) (402 SE2d 321) (1991) incorrectly construed [607]*607OCGA § 44-14-361.2 (a) (2) (B) to apply only “when the [contractor’s] affidavit is given in connection with the three transactions enumerated” in subparagraphs (2) (B) (i)-(iii). The panel held that since none of the enumerated transactions had occurred the requirement in (2) (B) of no prior recorded liens was not applicable, and the lien could be dissolved solely upon a showing of the requirements in (2) (A) even though the affidavit was made by the owner/contractor in response to a summary judgment motion and filed two years after the claim of lien was recorded.

This construction improperly ignored the word “and” that appears at the end of subparagraph (a) (2) (A) in derogation of the basic rule that a statute should be construed to “make all its parts harmonize and to give a sensible and intelligent effect to each part[, as i]t is not presumed that the legislature intended that any part would be without meaning. [Cit.]” Houston v. Lowes of Savannah, 235 Ga. 201, 203 (219 SE2d 115) (1975). The interpretation in Drywall Supply also is inconsistent with the obvious legislative intent of the 1983 amendments to the statutory lien laws, Ga. Laws 1983, pp. 1450, 1455-1456, which enacted a new Code section, OCGA § 44-14-361.2, incorporating a variation of former OCGA § 44-14-361 (b) into paragraph (a) (2) (A) of the new Code section and adding new language denominated as paragraph (a) (2) (B).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hart v. State
Supreme Court of Georgia, 2025
Vintson v. Lichtenberg
568 S.E.2d 795 (Court of Appeals of Georgia, 2002)
Tench v. Galaxy Appliance & Furniture Sales, Inc.
567 S.E.2d 53 (Court of Appeals of Georgia, 2002)
Focus Healthcare Medical Center, Inc. v. O’neal
558 S.E.2d 818 (Court of Appeals of Georgia, 2002)
Weatherbed v. State
524 S.E.2d 452 (Supreme Court of Georgia, 1999)
Davis v. Kaiser Foundation Health Plan of Georgia, Inc.
521 S.E.2d 815 (Supreme Court of Georgia, 1999)
White v. Cauthen
509 S.E.2d 140 (Court of Appeals of Georgia, 1998)
Davis v. Kaiser Foundation Health Plan of Georgia, Inc.
508 S.E.2d 431 (Court of Appeals of Georgia, 1998)
Southern Concrete Construction Co. v. Hall
422 S.E.2d 663 (Court of Appeals of Georgia, 1992)
Freeman v. Fulton Concrete Co.
419 S.E.2d 536 (Court of Appeals of Georgia, 1992)
Balest v. Simmons
411 S.E.2d 576 (Court of Appeals of Georgia, 1991)

Cite This Page — Counsel Stack

Bluebook (online)
411 S.E.2d 576, 201 Ga. App. 605, 1991 Ga. App. LEXIS 1509, Counsel Stack Legal Research, https://law.counselstack.com/opinion/balest-v-simmons-gactapp-1991.