Baker v. R & R Construction, Inc.

662 N.E.2d 661, 1996 Ind. App. LEXIS 298, 1996 WL 118065
CourtIndiana Court of Appeals
DecidedMarch 15, 1996
Docket79A02-9410-CV-655
StatusPublished
Cited by12 cases

This text of 662 N.E.2d 661 (Baker v. R & R Construction, Inc.) is published on Counsel Stack Legal Research, covering Indiana Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Baker v. R & R Construction, Inc., 662 N.E.2d 661, 1996 Ind. App. LEXIS 298, 1996 WL 118065 (Ind. Ct. App. 1996).

Opinion

OPINION

ROBERTSON, Judge.

This dispute arose out of the construction of a new home. The parties are 1) the homeowners, Appellants Timothy S. and Beverly J. Baker [the Bakers], 2) the building contractor, Appellee R & R Construction, Inc. [Builder], and 3) the bank that financed the project, Appellee First Bank of Lafayette [Bank]. Ultimately, two lawsuits were consolidated into this one and all claims and counterclaims were tried to the bench. The trial court awarded judgment in favor of the Builder and against the Bakers in the following amounts: 1) $3,261.01 on a mechanie's lien, 2) $50,001.20 representing twice the amount of certain checks drawn on the Bank which the Bakers had ordered the Bank to stop payment on (recovered under the remedy provided for damages for property loss caused by a criminal act as provided under Ind.Code 34-4-30-1), and 3) approximately $10,000.00 in attorney fees. The trial court ruled against the Bakers on their claims against the Builder and the Bank. This appeal ensued.

On appeal, the Bakers have filed a 75 page brief in which they raise twenty issues including subparts. Also, they have filed a 56 page appendix to their brief which includes a substantial amount of additional argument along with a great deal of documentary evidence including various lists, transaction itemizations, inspections reports, construction estimates, and logs of accounting journal entries. 1 The record in this case consists of *664 almost 3000 pages bound in twelve volumes. We restate, consolidate, and reorganize the Bakers' concerns into five issues. We reverse the judgment based upon I.C. 34-4-30-1. In all other respects, we affirm.

FACTS

The facts in the light most favorable to the trial court's judgment reveal that the Bakers wished to build a home on some land they owned. The Bakers contracted with Builder to build the home for a fixed price of $170,-000.00. The Bakers obtained a construction loan from the Bank in the amount of $175,-000.00. The construction loan proceeds were to be disbursed in proportion to the Bank's inspection reports of the progress made on the construction. The checks issued from the Bank under the construction loan agreement were made payable to the Bakers (and thus required the endorsement of one of the Bakers) in addition to the Builder or the various subcontractors who were to be paid.

On April 6, 1992, construction of the home began. The Bakers were closely involved in the construction of their home and were present at the site nearly every day. Almost immediately, the project experienced some set backs. Unusually wet weather and soil made the construction of the road to the property much more costly than expected. Also, the size of the Bakers' lot could not accommodate the septic system called for in the construction contract necessitating a change order authorized by the Bakers.

On April 16, 1992, the Builder requested the first draw upon the construction loan in an amount totaling approximately $31,000.00. The Bank inspected the construction and reported the project to be 7% complete. The checks were issued, endorsed by one of the Bakers, and distributed to the Builder and the various subcontractors and suppliers.

On May 3, 1992, the Builder requested the second draw in the amount of $44,000.00. The Bank's inspection ultimately reported the project 14% completed at that point. The checks were issued as before, one of the Bakers endorsed them, and they were distributed to the various payees.

The present dispute arose out of the third draw upon the construction loan requested by the Builder. On May 25, 1992, the Builder requested the third draw in the amount of $25,000.60. The Bank's inspector reported the construction to be 51.5% completed at that point. The checks were issued, endorsed by one of the Bakers, and distributed to the Builder and seven other payees. However, the Bakers had become concerned over some perceived discrepancies in the Builder's documentation which caused them to lose confidence in the Builder. The Bakers ordered the Bank to stop payment on all the checks issued under the third draw request. Thus, payment was stopped on 8 checks totaling $25,000.60. The Bakers notified all the payees that they had ordered the Bank to stop payment on the checks.

The Builder responded immediately by removing all the installed windows and doors, including the garage door, from the Bakers' partially completed home. The Builder also collected some lumber and other materials which it returned to the suppliers for credit. The Builder paid the outstanding bills of some of the subcontractors and suppliers who had contributed to the construction of the Bakers' house. The Builder filed a me-chanie's lien against the Bakers' property in the amount of $99,500.00.

Litigation was initiated when the Builder sued to foreclose its mechanic's lien. In addition to the amount secured under its lien, the Builder claimed $42,679.48 in damages for the Bakers' breach of the construction contract and requested treble damages, costs, and attorney fees under I.C. 34-4-80-1 for the total amount of the checks that the Bakers had ordered the Bank to stop payment. The Bakers answered and counterclaimed against the Builder for, among other things, breach of the construction contract. The Bakers requested $39,000.00 in damages representing the additional, anticipated cost to complete their home. The Bakers hired another builder who completed the home.

The Bakers filed an additional lawsuit against the Bank which was docketed in the same trial court. This complaint alleged that *665 the Bank had breached certain fiduciary duties in the disbursement of funds under the construction loan. The Bakers requested judgment in the amount of $85,000.00 against the Bank.

Various pleadings were filed and discussions had among the parties regarding the consolidation of the two actions. The trial court ultimately conducted a status conference and, over the objection of the Bakers, ordered that the two lawsuits be consolidated for trial.

The trial court denied the Bakers' request for a jury trial and the entire matter was submitted to a four-day bench trial. The trial court entered judgment as outlined above along with extensive findings of fact. This appeal ensued.

DECISION

L.

Consolidation/Bench Trial

A: Consolidation

The Bakers assert that the trial court committed reversible error by denying them a jury trial reasoning that, even if they had not been entitled to a jury trial in the first lawsuit which had been initiated as a foreclosure action, they were still entitled to a jury trial in their separate lawsuit brought against the Bank. Thus, the Bakers argue, the trial court erred by consolidating the two actions without providing them a jury trial on the issues involving the Bank.

Under Ind.Trial Rule 42(A) the trial court may order the consolidation of actions which involve a common question of law or fact. When determining whether actions should be consolidated or tried separately, the trial court balances the interests of convenience and economy against the likelihood of substantial prejudice to the party objecting to consolidation. Fultz v. Cox,

Related

State v. Roberts, Unpublished Decision (12-2-2005)
2005 Ohio 6391 (Ohio Court of Appeals, 2005)
Wagner v. Spurlock
803 N.E.2d 1174 (Indiana Court of Appeals, 2004)
Wontorski v. Williamsburg Mobile Homes, Inc.
775 N.E.2d 691 (Indiana Court of Appeals, 2002)
Songer v. Civitas Bank
771 N.E.2d 61 (Indiana Supreme Court, 2002)
Manzon v. Stant Corp.
138 F. Supp. 2d 1110 (S.D. Indiana, 2001)
Dora v. State
736 N.E.2d 1254 (Indiana Court of Appeals, 2000)
Gilliana v. Paniaguas
708 N.E.2d 895 (Indiana Court of Appeals, 1999)
Nationscredit Commercial Corp. v. Grauel Enterprises, Inc.
703 N.E.2d 1072 (Indiana Court of Appeals, 1998)
Vernon v. Acton
693 N.E.2d 1345 (Indiana Court of Appeals, 1998)
Shell Oil Co. v. Meyer
684 N.E.2d 504 (Indiana Court of Appeals, 1997)

Cite This Page — Counsel Stack

Bluebook (online)
662 N.E.2d 661, 1996 Ind. App. LEXIS 298, 1996 WL 118065, Counsel Stack Legal Research, https://law.counselstack.com/opinion/baker-v-r-r-construction-inc-indctapp-1996.