Baker-Smith Sheet Metal, Inc. v. Building Erection Services Co.

49 S.W.3d 712, 2001 Mo. App. LEXIS 917, 2001 WL 603482
CourtMissouri Court of Appeals
DecidedJune 5, 2001
DocketNo. WD 58946
StatusPublished
Cited by9 cases

This text of 49 S.W.3d 712 (Baker-Smith Sheet Metal, Inc. v. Building Erection Services Co.) is published on Counsel Stack Legal Research, covering Missouri Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Baker-Smith Sheet Metal, Inc. v. Building Erection Services Co., 49 S.W.3d 712, 2001 Mo. App. LEXIS 917, 2001 WL 603482 (Mo. Ct. App. 2001).

Opinion

HOWARD, Judge.

Building Erection Services Company, Inc. (“BESCO”) appeals from a judgment in favor of Baker-Smith Sheet Metal, Inc. (“Baker-Smith”) and against BESCO. BESCO contends the trial court erred in denying its motion for judgment notwithstanding the verdict or, in the alternative, for new trial, because 1) it was entitled to judgment as a matter of law, in that Baker-Smith executed a general release waiving and releasing BESCO from the claims at issue in this case; 2) Baker-Smith failed to make a submissible case on its claim for quantum meruit, in that Baker-Smith performed no work outside the scope of the parties’ contract, and its recovery is limited to the contract price, for which BESCO paid Baker-Smith in full; and 3) Baker-Smith failed to make a submissible case on its claim on account, in that Baker-Smith sought to recover damages for insulated metal panels that were pre-existing consideration for the parties’ contract, for which BESCO paid Baker-Smith in full.

We reverse.

Facts

BESCO is a corporation engaged in the installation and erection of construction materials, including steel and precast concrete, on construction projects. Baker-Smith, a corporation, furnished BESCO certain construction materials to be installed on a construction project, specifically, the FAA Control Tower at Kansas City International Airport (“the project”).

On or about January 24, 1995, Baker-Smith and BESCO entered into a contract pursuant to which Baker-Smith agreed to furnish BESCO with insulated metal panels according to the plans and specifications for the construction of the project. BESCO agreed to pay Baker-Smith $67,159 for the insulated metal panels. The insulated metal panels were to be installed by BESCO at the top of the FAA Tower.

Baker-Smith created shop drawings for the project. On June 10, 1995, John Scheerer, a BESCO employee, approved the shop drawings provided by Baker-Smith as correct for the project and correct in dimensions.

In June 1995, Baker-Smith furnished BESCO the insulated metal panels according to the shop drawings. The panels, however, were too short. On July 17, 1995, Baker-Smith quoted a price of $10,555 for a second set of insulated metal [714]*714panels that were the needed length. On July 24, 1995, BESCO ordered from Baker-Smith the second set of insulated metal panels. The second set of insulated metal panels was delivered to the project on or before August 15,1995.

BESCO paid Baker-Smith the full contract price of $67,159 for conforming insulated metal panels. On October 19, 1995, Baker-Smith’s then vice-president, Gerald S. Schaefer, executed a written waiver and release. The waiver and release acknowledged that Baker-Smith had been paid in full by BESCO for all work, services, labor, equipment and materials furnished in connection with the construction of the project through the date of September 20, 1995. The waiver and release further waived and released any and all rights, demands, and claims for materials that Baker-Smith furnished to the project on or before September 20,1995.

On April 30, 1999, Baker-Smith filed suit against BESCO in the Associate Circuit Court of Jackson County, Missouri, for quantum meruit and on account, seeking damages for the conforming insulated metal panels Baker-Smith furnished to BESCO on or before August 15, 1995. Upon BESCO’s demand for jury trial, the lawsuit was transferred to the Circuit Court of Jackson County, Missouri.

Prior to trial, BESCO filed a motion for summary judgment, asserting that BES-CO was entitled to judgment as a matter of law because the undisputed facts showed that Baker-Smith executed a waiver and release that waived its claims against BESCO that are at issue in the lawsuit. At the close of Baker-Smith’s evidence, BESCO filed a motion for directed verdict based on its previously filed motion for summary judgment and also on the basis that Baker-Smith could not sustain its claims for quantum meruit and on account because the damages sought by Baker-Smith were part of the original consideration of the parties’ contract, which BESCO paid Baker-Smith in full. At the close of all evidence, BESCO renewed its motion for directed verdict.

On March 16, 2000, the jury rendered a verdict in favor of Baker-Smith, and on April 14, 2000, judgment was entered. The jury awarded Baker-Smith $10,555 plus nine percent interest from September 25, 1995, for the conforming insulated metal panels Baker-Smith furnished to BES-CO on or before August 15,1995.

On May 12, 2000, BESCO filed its motion for judgment notwithstanding the verdict or, in the alternative, for new trial. In its motion, BESCO asserted that 1) Baker-Smith executed a general release that waived and released its claims against BESCO that are at issue in this case; 2) Baker-Smith failed to make a submissible case on its claims for quantum meruit and on account against BESCO; and 3) the evidence presented at trial was insufficient to support a jury verdict in favor of Baker-Smith. The court denied BESCO’s motion. This appeal follows.

Standard of Review

In reviewing the trial court’s denial of BESCO’s motion for judgment notwithstanding the verdict, we must determine whether Baker-Smith made a submissible case. Massman Const. Co. v. Missouri Highways and Transp. Comm’n, 31 S.W.3d 109, 112 (Mo.App. W.D.2000). “In doing so, we review the evidence and all reasonable inferences in the light most favorable to the jury’s verdict and disregard contrary evidence.” Id. We will reverse the jury’s verdict for insufficient evidence only where there is a complete absence of probative fact to support the jury’s conclusion. Giddens v. Kansas City Southern Ry. Co., 29 S.W.3d 813, 818 (Mo. banc 2000), cert. de[715]*715nied, — U.S. -, 121 S.Ct. 1644, 149 L.Ed.2d 502 (2001). A motion for judgment notwithstanding the verdict should only be granted when there is no room for reasonable minds to differ as to the ultimate disposition of the case. Balke v. Central Missouri Elec. Coop., 966 S.W.2d 15, 20 (Mo.App. W.D.1997).

Point I

BESCO’s first point on appeal is that the trial court erred in denying its motion for judgment notwithstanding the verdict or, in the alternative, for new trial, because it was entitled to judgment as a matter of law, in that Baker-Smith executed a general release waiving and releasing BESCO from the claims at issue in this case.

BESCO argues that Missouri law mandates that a plain and unambiguous general release disposes of the entire subject matter or causes of action involved. BES-CO further argues that Baker-Smith executed a general release that waived and released all of its claims against BESCO for material it furnished to the project through September 20,1995.

The release provides as follows:

Payment is acknowledged from Budding Erection Services Co. Inc. in the sum of $1,344.00 ($67,159 cumulative to date), being payment for all work, services, labor, equipment and materials furnished in connection with the construction of Air Traffic Control Tower-— KCI Airport, through the date of 9/20/95, the undersigned does hereby:
1.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

AB Realty One, LLC v. Miken Technologies, Inc.
466 S.W.3d 722 (Missouri Court of Appeals, 2015)
CB3 Enterprises LLC v. Damas
415 S.W.3d 163 (Missouri Court of Appeals, 2013)
Matt Miller Co. v. Taylor-Martin Holdings, LLC
393 S.W.3d 68 (Missouri Court of Appeals, 2012)
Walley v. La Plata Volunteer Fire Department
368 S.W.3d 224 (Missouri Court of Appeals, 2012)
Board of Educ. City of St. Louis v. State
134 S.W.3d 689 (Missouri Court of Appeals, 2004)
Anderson v. Curators of the University of Missouri
103 S.W.3d 394 (Missouri Court of Appeals, 2003)
City of Kansas City v. Southwest Tracor Inc.
71 S.W.3d 211 (Missouri Court of Appeals, 2002)

Cite This Page — Counsel Stack

Bluebook (online)
49 S.W.3d 712, 2001 Mo. App. LEXIS 917, 2001 WL 603482, Counsel Stack Legal Research, https://law.counselstack.com/opinion/baker-smith-sheet-metal-inc-v-building-erection-services-co-moctapp-2001.