Bair v. City of Clearwater, Florida

196 So. 3d 577, 2016 Fla. App. LEXIS 11823, 2016 WL 4150220
CourtDistrict Court of Appeal of Florida
DecidedAugust 5, 2016
Docket2D15-1210
StatusPublished
Cited by7 cases

This text of 196 So. 3d 577 (Bair v. City of Clearwater, Florida) is published on Counsel Stack Legal Research, covering District Court of Appeal of Florida primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Bair v. City of Clearwater, Florida, 196 So. 3d 577, 2016 Fla. App. LEXIS 11823, 2016 WL 4150220 (Fla. Ct. App. 2016).

Opinion

MORRIS, Judge.

David and Aileen Bair appeal a final judgment entered against them in their complaint against the City, of Clearwater for claims of . equitable estoppel and for relief pursuant to the Bert J. Harris, Jr., Private Property Rights Protection Act (Bert Harris Act). 1 The underlying action arose after the .City issued a stop-work order relating to modifications and improvements that the Bairs were making to their home pursuant to a permit that the City had previously, issued. The stop-work order was based on the City’s determination that the cost of the modifications and improvements exceeded 50 percent market-value of the Bairs’ home and, therefore, that the Bairs were required to bring the home into compliance with current flood prevention requirements before construction could resume. Because we agree with the trial court that the equitable estoppel claim was not a cognizable stand-alone cause of action and that the City’s application of its ordinances in this case did not give rise to a cognizable Bert Harris Act claim, we affirm.

BACKGROUND

The Bairs purchased their waterfront home on Clearwater Beach' in 2008. A 2003 Flood Insurance Rate Map indidates that the property sits below the 100-year elevation in a “V” flood zone.

In 2011,. the Bairs submitted an application for a permit to remodel the home as well as to add. an addition onto the home. Because the property. was located in a flood .zone, the. Bairs were required .to comply with section 51.03 of the City of Clearwater’s Development Code .(the City Code) and relevant Federal Emergency Management Agency (FEMA) regulations *580 regarding flood damage resistance requirements for any substantial improvements made to the home. This meant that if substantial improvements were made, the structure was required to be elevated so that the bottom of the lowest horizontal part of the structure would be at or above the base flood elevation level. “Substantial improvements” as defined by the City Code and FEMA regulations are modifications or improvements to a structure made during a one-year period that equal or exceed 50 percent of the market value of the structure before the modifications or improvements- commenced. Structures are not required to be elevated at or above the base flood elevation level if the modifications or improvements are nonsubstan-tial. 2 . "

The City reviewed the Bairs’ permit application and requested that the Bairs submit an application for nonsubstantial improvements. As part of the application, the Bairs were required to obtain an appraisal to determine the market value of their home prior to any improvements being made. The purpose of the appraisal was to provide a benchmark to determine whether the Bairs’ proposed improvements could be classified as nonsubstantial, thereby excusing them from the requirement to elevate their home. The Bairs complied with the City’s request in June 2011. The Bairs’ application included an affidavit from an engineer attesting to the scope and cost of the work to be performed, a 2010 appraisal report, and a budget for the proposed improvements and addition to their home. The Bairs represented in their application that the cost of the proposed improvements and addition would not exceed 50 percent of the market value of the structure that existed before the commencement of- construction. Based on the application, the City issued the permit.

In August 2011, the Bairs began construction on their home, which included a partial demolition. However, nine, days after construction commenced, the City issued a stop-work order pursuant to chapter 51 and section 47.001 of the City Code on the basis that the partial demolition was so extensive that the City believed the improvements and addition would exceed 50 percent of the market value of the preexisting structure.

Thereafter, the Bairs engaged in conversations with the City in an effort to have the stop-work order lifted. Eventually, the Bairs submitted revised plans showing that while the cost of the project had increased, the size and scope of the project had been scaled back. The Bairs also submitted a revised appraisal which relied on a cost valuation approach; that approach was different from the market value approach used in the initial appraisal report. The new valuation methodology allowed for an increase in the Bairs’ construction budget while still allowing them to comply with the 50 percent Rule.

However, even with the revised plans and second appraisal,' the City was not convinced that the improvements and addition could be completed within the scope of the nonsubstantial improvements permit. Thus, the City refused to lift the stop-work order. The Bairs appealed to the City’s Building/Flood Board of Adjustment and Appeals which ultimately affirmed the City’s decision to leave the stop-work order in effect.

In March 2013, the Bairs filed a two-count complaint against the City. Count I sought relief pursuant to the Bert Harris Act, and count II sought damages based *581 on an equitable estoppel theory. In response, the City filed a motion to dismiss and an alternative motion for summary judgment as to the equitable estoppel claim, arguing that there was no freestanding claim for equitable estoppel but even if there was, the Bairs are precluded from seeking monetary relief. The City also sought summary judgment on the Bert Harris Act claim, arguing that because the stop-work order was predicated on the application of ordinances that were enacted on or before May 11,1995, the Bert Harris Act did not apply. The trial court ultimately granted the motion to dismiss the equitable estoppel claim as well as the motion for summary judgment on the Bert Harris Act claim. Final judgment was entered in favor of the City, and this appeal now follows.

ANALYSIS

I. The Bert Harris Act claim

We review the trial court’s order granting final summary judgment de novo. See Volusia County v. Aberdeen at Ormond Beach, L.P., 760 So.2d 126, 130 (Fla.2000). Issues involving statutory interpretation are also reviewed de novo. Borden v. East-European Ins. Co., 921 So.2d 587, 591 (Fla.2006). Summary judgment is properly entered only if there is no genuine issue of material fact and the moving party is entitled to judgment as a matter of law. Aberdeen at Ormond Beach, L.P., 760 So.2d at 130.

In interpreting a statute, we must primarily look to the plain language of the statute at issue. J.W. v. Dep’t of Children & Family Servs., 816 So.2d 1261, 1263 (Fla. 2d DCA 2002). If the statute is clear and unambiguous, we need not resort to rules of statutory interpretation; rather, we give the statute “its plain and obvious meaning.” Holly v. Auld, 450 So.2d 217, 219 (Fla.1984) (quoting A.R. Douglass, Inc. v. McRainey, 102 Fla. 1141, 137 So. 157, 159 (1931)). The Bert Harris Act contains a very narrow waiver of sovereign immunity, see § 70.001(13), and such waiver statutes are strictly construed, see Spangler v. Fla. State Turnpike Auth., 106 So.2d 421, 424 (Fla.1958).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

HEART OF ADOPTIONS, INC. v. DEPT. OF CHILDREN & FAMILIES
District Court of Appeal of Florida, 2023
ANTONIO RUIZ AND MARIA HERNANDEZ v. WENDY'S TRUCKING, L L C
District Court of Appeal of Florida, 2022
INDIAN RIVER COUNTY v. OCEAN CONCRETE, INC. and GEORGE MAIB
District Court of Appeal of Florida, 2020
Cascar, LLC v. City of Coral Gables
274 So. 3d 1231 (District Court of Appeal of Florida, 2019)
Cagwin v. Thrifty Rents, Inc.
219 So. 3d 1003 (District Court of Appeal of Florida, 2017)

Cite This Page — Counsel Stack

Bluebook (online)
196 So. 3d 577, 2016 Fla. App. LEXIS 11823, 2016 WL 4150220, Counsel Stack Legal Research, https://law.counselstack.com/opinion/bair-v-city-of-clearwater-florida-fladistctapp-2016.