Bainbridge St. Elmo v. White Flint

Court of Appeals of Maryland·Decided July 18, 2017·No. 30/16·Published

Opinion

Bainbridge St. Elmo Bethesda Apartments, LLC v. White Flint Express Realty Group Limited Partnership, LLLP, No. 30, September Term, 2016, Opinion by Raker, J.

CONTRACT LAW – INDEMNIFICATION – FIRST-PARTY FEE SHIFTING: Maryland follows the common law American Rule, which states that, generally, a prevailing party is not awarded attorney’s fees. Maryland law draws a distinction between the recovery of attorney’s fees incurred in defending against a third-party claim and those expended in prosecuting a claim against the indemnitor. There are four exceptions to the American Rule where a prevailing party may be awarded attorney’s fees, including that the parties have an agreement to that effect. The scope of indemnification is a matter of contract interpretation, where a court looks to the terms of the contract to decide whether the parties agreed expressly that attorney’s fees would be recoverable in a first-party action. The contract between the parties in this case, specifically Article 19, provides expressly for the payment of “attorney’s fees;” and it ties payment of those fees expressly to an action for “breach” of the contract. Therefore, the Easement Agreement contains sufficient language to authorize first-party fee shifting, and subsequently White Flint is entitled to recover attorney’s fees.

Circuit Court for Montgomery County IN THE COURT OF APPEALS Case No. 362334-V OF MARYLAND

Argued: December 6, 2016

No. 30

September Term, 2016

BAINBRIDGE ST. ELMO BETHESDA APARTMENTS, LLC

v.

WHITE FLINT EXPRESS REALTY GROUP LIMITED PARTNERSHIP, LLLP

Barbera, C.J.

Greene

Adkins

McDonald

Hotten

Getty

Raker, Irma S. (Senior Judge, Specially Assigned),

JJ.

Opinion by Raker, J.

Filed: July 18, 2017

This dispute concerns the award of attorney’s fees in a construction contract dispute.

At the heart of this appeal is whether White Flint Express Realty Group Limited Partnership, LLLP (“White Flint”), respondent, was entitled to recover attorney’s fees expended in connection with an action to enforce the contract between White Flint and Bainbridge St. Elmo Bethesda Apartments, LLC (“Bainbridge”), petitioner. The Court of Special Appeals held that the contract provided expressly for attorney’s fees to be recovered in a first-party indemnification action. Bainbridge St. Elmo Bethesda Apartments, LLC v. White Flint Express Realty Grp. Ltd. P’ship, LLLP, No. 0376 SEPT. TERM 2014, 2016 WL 1321205, at *6 (Md. Ct. Spec. App. Apr. 5, 2016), cert. granted sub nom. Bainbridge St. Elmo Bethesda v. White Flint Express Realty Grp. Ltd. P’ship, LLLP, 449 Md. 408, 144 A.3d 704 (2016). We granted Bainbridge’s petition for writ of certiorari to address the following question:

“Did the CSA undermine the clarity provided by this Court in Nova Research[,] [Inc.] v. Penske Truck Leasing Co., 405 Md.

435 (2008), concerning the limited circumstances under which a contractual indemnity provision can be read as a first-party fee shifting provision overriding the American Rule that each party bears its own attorneys’ fees?”

Petition for Writ of Cert., Bainbridge St. Elmo Bethesda Apartments, LLC v. White Flint Express Realty Grp. Ltd. P’ship, LLLP, No. 162. We shall affirm the judgment of the Court of Special Appeals, and hold that the contract contains express provisions authorizing first-party fee shifting, entitling White Flint to attorney’s fees.

I.

Bainbridge, an entity formed by the Bainbridge Companies to manage the construction and operation of a new 17-story high rise apartment building in Bethesda, owns the property immediately adjacent to 4905 and 4909 Fairmont Avenue (“the Fairmont Properties”). Located on the Fairmont Properties were two one-story concrete buildings owned by White Flint that were leased to a restaurant and a children’s dance studio. Bainbridge engaged sub-contractor Turner to build the 17-story apartment building on its property for an estimated cost of $45,000,000. The construction project required excavation of a 50-foot-deep hole on the property, to be held open by steel cables protruding under and onto White Flint’s property1 to prevent soil and sub-surface structures from moving toward or into the excavation area. Bainbridge sought an easement from White Flint for access to the space “under, over, across and on the Fairmont Properties.” Bainbridge also wanted additional easements to swing a crane and extend scaffolding above the Fairmont properties.

On September 7, 2011, after several months of negotiation, and before construction began, Bainbridge and White Flint entered into a “Crane Swing, Tie Back and Swing Scaffold Easement Agreement” (“the Agreement”). Bainbridge agreed to pay White Flint $425,000 as consideration for the Agreement and the requested easements.

1 Bainbridge proposed to hold open the hole with a “sheeting and shoring system” built by placing vertical steel I-beams (“piles”) into pre-drilled holes, locked into place by “tie- backs”—long steel cables extending back from the piles into adjacent properties and welded to “brackets”—with L-shaped steel shelves extending onto and underneath the neighboring building foundations.

The Agreement recognized Bainbridge’s right to access the air space above and the ground below White Flint’s Property, and it provided White Flint a means to seek redress for any potential damage from the construction. Under Article 3, Bainbridge promised that it would not use a “pile-drive” system to secure the hole, and would follow the appended plan’s use of tie-backs and bracket piles placed into pre-drilled holes. Article 7 provided that Bainbridge would ensure that all excavation and foundation work conformed to applicable professional standards of care while minimizing the inconvenience to White Flint, would protect all individuals in and around the properties, and would not undermine the improvements on the Fairmont Properties. In Article 9 of the Agreement, Bainbridge agreed to permit White Flint to engage, at Bainbridge’s expense, consultants:

“[T]o monitor performance of the work by Bainbridge, and identify any perceived deficiencies that could result in injury to people occupying or visiting any part of the White Flint Property, or in damage to the White Flint Property.”

If White Flint’s consultants identified a Major Deficiency (over $25,000), Bainbridge had the right to have its own consultant “review and assess the perceived Major Deficiency.” Article 9 provided that if Bainbridge’s consultants did not agree with White Flint’s consultants as to a perceived Major Deficiency, the parties were obligated to “work together in good faith to find a mutually acceptable resolution.” And then if a resolution could not be reached within 60 days, the dispute would be submitted to binding arbitration. Finally, Article 9 included a fee-shifting agreement specifying that:

“The prevailing party in any arbitration shall be awarded reasonable counsel fees, expert and non-expert witness costs and expenses and all other costs and costs and expenses reasonably incurred, directly or indirectly, in connection with

said arbitration, and all costs and frees of such arbitration shall be borne exclusively by the non-prevailing party.”

Article 16 established Bainbridge’s responsibility to either repair and restore White Flint’s property to its original condition or reimburse White Flint for doing so. Article 17(a)-(b) provided that Bainbridge would pay White Flint $425,000 upon entering into the Agreement, and established an escrow account to reimburse White Flint for costs associated with negotiating and monitoring Bainbridge’s compliance with the Agreement.

Most relevant to the present appeal is Article 19, the indemnification clause of the contract, which provided as follows:

Free access — add to your briefcase to read the full text and ask questions with AI

Bainbridge St. Elmo v. White Flint, (Md. 2017).

Bainbridge St. Elmo v. White Flint (Bainbridge St. Elmo v. White Flint) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Bret Broaddus v. Kevin Shields
665 F.3d 846 (Seventh Circuit, 2011)
Anthony v. United States
935 A.2d 275 (District of Columbia Court of Appeals, 2007)
Pacific Indemnity Co. v. Interstate Fire & Casualty Co.
488 A.2d 486 (Court of Appeals of Maryland, 1985)
Nova Research, Inc. v. Penske Truck Leasing Co.
952 A.2d 275 (Court of Appeals of Maryland, 2008)
Thomas v. Gladstone
874 A.2d 434 (Court of Appeals of Maryland, 2005)
Atlantic Contracting & Material Co. v. Ulico Casualty Co.
844 A.2d 460 (Court of Appeals of Maryland, 2004)
Thomas v. Capital Medical Management Associates, LLC
985 A.2d 51 (Court of Special Appeals of Maryland, 2009)
Jones v. Calvin B. Taylor Banking Co.
253 A.2d 742 (Court of Appeals of Maryland, 1969)
Jones v. Hubbard
740 A.2d 1004 (Court of Appeals of Maryland, 1999)
Columbia Gas Transmission Corp. v. Ashleigh Heights LLC
261 F. Supp. 2d 332 (D. Maryland, 2002)
Loughrin v. United States
134 S. Ct. 2384 (Supreme Court, 2014)
Anthony Hill v. Daniel M. Tangherlini
724 F.3d 965 (Seventh Circuit, 2013)
JAMES G. DAVIS CONSTRUCTION CORPORATION v. HRGM CORPORATION
147 A.3d 332 (District of Columbia Court of Appeals, 2016)
Fortune Southfield Co. v. Kroger Co.
931 F.2d 1282 (Eighth Circuit, 1991)