Bailey v. Lund-Ross Constructors Co.

657 N.W.2d 916, 265 Neb. 539, 2003 Neb. LEXIS 45
CourtNebraska Supreme Court
DecidedMarch 21, 2003
DocketS-02-174
StatusPublished
Cited by92 cases

This text of 657 N.W.2d 916 (Bailey v. Lund-Ross Constructors Co.) is published on Counsel Stack Legal Research, covering Nebraska Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Bailey v. Lund-Ross Constructors Co., 657 N.W.2d 916, 265 Neb. 539, 2003 Neb. LEXIS 45 (Neb. 2003).

Opinion

Hendry, C.J.

INTRODUCTION

Lund-Ross Constructors Co. (Lund-Ross) appeals the district court’s order overruling its motion for leave to file a cross-claim against Merrimac Stone Co. (Merrimac). Lund-Ross sought to assert a cross-claim against Merrimac to proportionately diminish its liability to Lance D. Bailey, if any, by the percentage of contributory negligence attributable to Merrimac pursuant to Neb. Rev. Stat. § 25-21,185.10 (Reissue 1995). Lund-Ross appealed after the district court entered a “final judgment” pursuant to Neb. Rev. Stat. § 25-1315(1) (Cum. Supp. 2002). We moved the case to our docket pursuant to our authority to regulate the caseloads of this court and the Nebraska Court of Appeals. See Neb. Rev. Stat. § 24-1106(3) (Reissue 1995).

FACTUAL BACKGROUND

Bailey filed a petition naming both Lund-Ross and Merrimac as defendants. In his petition, Bailey alleged that Lund-Ross, as the general contractor of a building under constmction in Omaha, Nebraska, entered into a contract with Merrimac to “perform, as sub-contractor, certain stone masonry services in connection with the construction of the aforementioned building.” Bailey further alleged that in August 2000, he was employed by Merrimac and, during the course of his employment, assisted in placing stone masonry on the side of the building under constmction while on scaffolding approximately 40 feet above ground level. Bailey asserted that as a direct and proximate result of Lund-Ross’ negligent failure to safely construct and monitor the scaffolding, the scaffolding collapsed, causing him to fall and sustain injuries.

Bailey named Merrimac as a defendant “solely for the purpose of determining [Merrimac’s] subrogation rights under the *541 Nebraska Workers’ Compensation Law.” Bailey prayed for both a determination of Merrimac’s “rights and liabilities under the Workers’ Compensation Act” and for a judgment against LundRoss for general and special damages.

Merrimac filed an answer in which it admitted all the allegations contained in Bailey’s petition. Merrimac additionally alleged that it had paid workers’ compensation benefits in the amount of $2,675 to Bailey for the injury Bailey suffered during the course of his employment with Merrimac. Merrimac asserted that pursuant to Neb. Rev. Stat. § 48-118 (Cum. Supp. 2002), it was entitled to recover from Lund-Ross “its workers’ compensation subrogation interest” in the amount of $2,675.

Lund-Ross filed an answer admitting that it had entered into a contract with Merrimac to perform stone masonry services and that Bailey “fell from scaffolding” and “sustained some injuries” while working for Merrimac on the building under construction. Lund-Ross denied that its negligence either caused the scaffolding to collapse or caused Bailey to suffer injuries. Additionally, Lund-Ross alleged as an affirmative defense, inter alia, that Bailey was contributorily negligent in a percentage sufficient to bar his recovery. Lund-Ross prayed that Bailey’s petition be dismissed.

After filing its answer, Lund-Ross filed an amended motion for leave to file a cross-claim against Merrimac on the following grounds: “1. [Lund-Ross] is entitled to a determination by the jury of the relative negligence or fault of Merrimack [sic] Stone Company; and 2. Evidence as to the negligence of Merrimack [sic] Stone will come into evidence, in any event, as to the issue of proximate causation.” Lund-Ross attached a proposed cross-claim to its amended motion alleging that its liability to Bailey, if any, should be reduced by the extent of contributory negligence apportioned to Merrimac pursuant to § 25-21,185.10.

In an order dated January 9, 2002, the district court overruled Lund-Ross’ amended motion for leave to file its proposed cross-claim. In response, Lund-Ross filed a “Motion for Determination of Final Judgment,” in which it requested the court to determine that (1) the January 9 order overruling Lund-Ross’ motion for leave to file a cross-claim was a final judgment and (2) there was *542 no just reason for delay of the entry of judgment so that LundRoss could immediately pursue an appeal.

In a February 5, 2002, order, the court granted Lund-Ross’ motion. The court determined with respect to its January 9 order that

pursuant to Neb. Rev. Stat. § 25-1315 . . . there is no just reason for delay of such final judgment and [the court] hereby expressly directs the entry of a final judgment denying Defendant’s Amended Motion for Leave to File a Cross-Claim against Defendant Merrimac Stone Company and related entities....
... [T]he issues presented by the proposed Cross-Claim are issues that affect a substantial right of Defendant LundRoss Constructors Co.

Lund-Ross appeals the district court’s denial of its motion for leave to file its proposed cross-claim.

ASSIGNMENTS OF ERROR

Lund-Ross assigns that the district court erred in (1) overruling its amended motion for leave to file a cross-claim; (2) “ruling that a cross-claim against [Bailey’s] employer, in order to permit the trier of fact to apportion negligence pursuant to Neb. Rev. Stat. § 25-21,185.07 et seq.. would violate the ‘exclusivity provision’ of Neb. Rev. Stat. § 48-148”; and (3) “finding that the negligent employer’s subrogation claim could not be reduced by its percentage of negligence.”

STANDARD OF REVIEW

A jurisdictional question which does not involve a factual dispute is determined by an appellate court as a matter of law. Slaymaker v. Breyer, 258 Neb. 942, 607 N.W.2d 506 (2000); In re Application of SID No. 384, 256 Neb. 299, 589 N.W.2d 542 (1999).

ANALYSIS

Before reaching the assignments of error asserted by Lund-Ross, this court must first determine whether it has jurisdiction. It is the power and duty of an appellate court to determine whether it has jurisdiction over the matter before it, irrespective of whether the issue is raised by the parties. Vopalka v. *543 Abraham, 260 Neb. 737, 619 N.W.2d 594 (2000).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Mann v. Mann
978 N.W.2d 606 (Nebraska Supreme Court, 2022)
TDP Phase One v. The Club at the Yard
307 Neb. 795 (Nebraska Supreme Court, 2020)
McEwen v. Nebraska State College Sys.
303 Neb. 552 (Nebraska Supreme Court, 2019)
Cattle Nat. Bank & Trust Co. v. Watson
880 N.W.2d 906 (Nebraska Supreme Court, 2016)
Pinnacle Enters. v. City of Papillion
836 N.W.2d 588 (Nebraska Supreme Court, 2013)
State v. Poindexter
766 N.W.2d 391 (Nebraska Supreme Court, 2009)
Poppert v. Dicke
747 N.W.2d 629 (Nebraska Supreme Court, 2008)
Cerny v. Todco Barricade Co.
733 N.W.2d 877 (Nebraska Supreme Court, 2007)
State v. Hudson
727 N.W.2d 219 (Nebraska Supreme Court, 2007)
Harper v. Clarke
713 N.W.2d 502 (Nebraska Court of Appeals, 2006)
Malolepszy v. State
699 N.W.2d 387 (Nebraska Supreme Court, 2005)
Weeder v. Central Community College
691 N.W.2d 508 (Nebraska Supreme Court, 2005)
State v. Bao
690 N.W.2d 618 (Nebraska Supreme Court, 2005)
Kellogg v. Nebraska Department of Correctional Services
690 N.W.2d 574 (Nebraska Supreme Court, 2005)
Blue Cross & Blue Shield of Nebraska, Inc. v. Dailey
687 N.W.2d 689 (Nebraska Supreme Court, 2004)
Pioneer Chemical Co. v. City of North Platte
685 N.W.2d 505 (Nebraska Court of Appeals, 2004)
Smith v. Lincoln Meadows Homeowners Ass'n
678 N.W.2d 726 (Nebraska Supreme Court, 2004)
Pennfield Oil Co. v. Winstrom
673 N.W.2d 558 (Nebraska Supreme Court, 2004)
Lyle v. Drivers Management, Inc.
673 N.W.2d 237 (Nebraska Court of Appeals, 2004)
Mumin v. Dees
663 N.W.2d 125 (Nebraska Supreme Court, 2003)

Cite This Page — Counsel Stack

Bluebook (online)
657 N.W.2d 916, 265 Neb. 539, 2003 Neb. LEXIS 45, Counsel Stack Legal Research, https://law.counselstack.com/opinion/bailey-v-lund-ross-constructors-co-neb-2003.