Bad River Band of the Lake Superior Tribe of Chippewa Indians of the Bad River Reservation v. Enbridge Energy Company, Inc.

District Court, W.D. Wisconsin·Decided November 28, 2022·No. 3:19-cv-00602·Unknown

Opinion

IN THE UNITED STATES DISTRICT COURT FOR THE WESTERN DISTRICT OF WISCONSIN

BAD RIVER BAND OF THE LAKE SUPERIOR TRIBE OF CHIPPEWA INDIANS OF THE BAD RIVER RESERVATION, OPINION AND ORDER (Public Nuisance Claim and Plaintiff and Counterclaims) Counter Defendant, v. 19-cv-602-wmc

ENBRIDGE ENERGY COMPANY, INC., and ENBRIDGE ENERGY, L.P.,

Defendants and Counter Claimants, v.

NAOMI TILLISON,

Counter Defendant.

Concerned about a potential failure of Enbridge Energy’s Line 5 crude oil and liquid natural gas pipeline running through the Reservation of the Bad River Band of the Lake Superior Tribe of Chippewa Indians in northern Wisconsin, the Band brought this suit seeking to enjoin its continued operation under federal common law claims of public nuisance and trespass. At summary judgment, this court concluded that Enbridge had trespassed by operating the pipeline on expired rights-of-way on 12 parcels owned in whole or in part by the Band and dismissed Enbridge’s breach of contract counterclaims, but denied either side summary judgment on the Band’s public nuisance claim. (Dkt. #360.) After reviewing relevant expert reports, deposition designations and other voluminous, additional written submissions by the parties, the court held a trial to the bench on the Band’s public nuisance claim and Enbridge’s remaining counterclaims on October 24, 25 and 26, 2022.1 Before issuing a final decision on the Band’s public nuisance claim, the court will direct the parties to meet and confer on specific issues and submit a proposal to the court, as set forth below. However, the court will deny Enbridge’s request for

declaratory and injunctive relief on its counterclaims.

OPINION I. The Band’s Nuisance Claim Under federal common law, a public nuisance is a substantial and unreasonable

interference with a right common to the general public. Restatement (Second) of Torts § 821B. Where, as in this case, the nuisance is not presently occurring, a plaintiff must generally prove that the substantial and unreasonable interference “is imminent” or “certain to occur.” Michigan v. U.S. Army Corps of Eng’rs, 758 F.3d 892, 900 (7th Cir. 2014) (Asian Carp II). The Seventh Circuit has advised that this concept of “imminence” does not have a precise definition. Rather, there is “no meaningful legal difference” between

“imminent” and such arguable synonyms as “immediate,” “significant,” “real,” “unreasonable,” or “greater than a reasonable [person] would incur.” Michigan v. U.S. Army Corps of Engineers, 667 F.3d 765, 781–82 (7th Cir. 2011) (“Asian Carp I”). Thus, the ultimate question is whether a grave, irreparable harm is “sufficiently close to occurring” that the court “should order the defendants to take some new action that will be effective to abate the public nuisance.” Id.

1 At the end of this first phase of trial, the court went on to hear evidence for remedies as to Enbridge’s ongoing trespass of the Band’s territory, which will be the subject of a separate Opinion and Order. Both parties presented evidence at trial establishing that the greatest known risk of a pipeline rupture is currently located at or near the meander where Line 5 crosses the Bad River:

ates

erro ne

(Fig I: Line 5 crossing Bad River meander (Def’s Demonstrative Ex. 4).) Not only is there an actual risk of a significant rupture, but the negative impact in this area on the Bad River watershed and even Lake Superior itself could be catastrophic. Thus, the court finds that a rupture of Line 5 at the meander would be a substantial and unreasonable interference with the Band’s and the public’s rights. Indeed, the nearest, existing shutoff valves of Line 5 on either side of that meander are approximately 14 miles apart. Even if those shutoff valves were activated in time to prevent any release of additional crude oil and liquid natural gas (“NGL”), a failure of the line would likely not prevent the roughly 20,000 gallons of crude oil and NGL constantly contained in that stretch of pipe from being released into the Bad River, absent sufficient time to purge it

into a fleet of trucks before the pipe failed. 2

Still, although there are various reasons why Line 5 seems likely to fail the meander at some point, the Band has yet to prove its right to an immediate entry of injunctive relief, and particularly its right to an injunction immediately stopping the operation of Line 5 altogether. First, whether a rupture of Line 5 is “imminent” or “certain to occur” remains open to reasonable debate, as illustrated by much of the evidence at trial. There are actually three, separate ways that the pipeline might fail at the meander: Channelization

Scour =e , □□

Historical Bank Erosion

(Fig 2: Potential pipeline failure at Bad River meander (PEX. 70, at 4).) The least likely, identified as “channelization” on Figure 2 above, is that one of the

2 Enbridge offered substantial evidence of shut off and purge protocols, as well as possible mediation efforts in the event of a spill, but there remains at least some risk of a much larger spill than 20,000 gallons because the shut down and purge protocols take time to complete. While Enbridge claims to be much better prepared now, one need look no further to appreciate the potential damage than the spill of over one million gallons into the Kalamazoo River in 2010, after the failure of another of Enbridge’s pipelines, which was similarly built in the 1950s.

current flood channels through the meander’s toe could become sufficiently worn that the pipe is exposed, and eventually the area below the pipe is scoured by a perpendicular current, creating a free standing, unsupported span of pipe subject to failure by metal

fatigue and vibrations.3 The parties presented conflicting evidence as to how far that span would have to be: plaintiff’s experts suggested that the pipe would lose its ability to “flex” without causing permanent damage and a catastrophic failure at approximately 60 feet, while Enbridge’s protocol claims no substantial risk until an unsupported span reaches 90 to 100 feet. The next (and only slightly more likely) risk, identified as “scour” on Figure

2, is a similar, perpendicular scouring event at the bottom of the river bed, in which pipe now buried under the riverbed sufficiently exposed to erosion to create a substantial, unsupported span and perpendicular current. Finally, as the court found at trial following the close of evidence on the Band’s public nuisance claim, the third possibility -- horizontal erosion at the meander’s river bank closest to the pipeline (identified as “historical bank erosion” on Figure 2) -- poses the greatest current risk of rupture of Line 5 within the

Reservation. Even at this location, however, there still remains approximately 26 or 27 feet of riverbank between the Bad River shoreline and Line 5 at its nearest point, a distance that, although alarmingly significant given annual average erosion, has remained stable for three straight years as a result of below average flooding and the serendipitous formation of a

3 Under a perpendicular “channel scouring” scenario, the possibility of vibrations stressing the pipe becomes more concerning, but then the metal failure risk caused by the free span is reduced by support of the water below the pipe. small gathering of fallen trees directly upstream.

Free access — add to your briefcase to read the full text and ask questions with AI

Bad River Band of the Lake Superior Tribe of Chippewa Indians of the Bad River Reservation v. Enbridge Energy Company, Inc., (W.D. Wis. 2022).

Bad River Band of the Lake Superior Tribe of Chippewa Indians of the Bad River Reservation v. Enbridge Energy Company, Inc. (Bad River Band of the Lake Superior Tribe of Chippewa Indians of the Bad River Reservation v. Enbridge Energy Company, Inc.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

United States v. Denedo
556 U.S. 904 (Supreme Court, 2009)
State of Michigan v. United States Army Corps of En
758 F.3d 892 (Seventh Circuit, 2014)