Bad River Band of the Lake Superior Tribe of Chippewa Indians of the Bad River Reservation v. Enbridge Energy Company, Inc.

CourtDistrict Court, W.D. Wisconsin
DecidedJune 16, 2023
Docket3:19-cv-00602
StatusUnknown

This text of Bad River Band of the Lake Superior Tribe of Chippewa Indians of the Bad River Reservation v. Enbridge Energy Company, Inc. (Bad River Band of the Lake Superior Tribe of Chippewa Indians of the Bad River Reservation v. Enbridge Energy Company, Inc.) is published on Counsel Stack Legal Research, covering District Court, W.D. Wisconsin primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Bad River Band of the Lake Superior Tribe of Chippewa Indians of the Bad River Reservation v. Enbridge Energy Company, Inc., (W.D. Wis. 2023).

Opinion

IN THE UNITED STATES DISTRICT COURT FOR THE WESTERN DISTRICT OF WISCONSIN

BAD RIVER BAND OF THE LAKE SUPERIOR TRIBE OF CHIPPEWA INDIANS OF THE BAD RIVER RESERVATION, OPINION AND ORDER

Plaintiff and Counter Defendant, v. 19-cv-602-wmc

ENBRIDGE ENERGY COMPANY, INC., and ENBRIDGE ENERGY, L.P.,

Defendants and Counter Claimants, v.

NAOMI TILLISON,

Counter Defendant.

The Bad River Band of the Lake Superior Tribe of Chippewa Indians brought this action against Enbridge Energy to enjoin the continued operation of Enbridge’s Line 5 crude oil and natural gas liquids (“NGLs”) pipeline through the Bad River Reservation in Northern Wisconsin based on the risk of its failure constituting a public nuisance. The Band also seeks damages and injunctive relief for Enbridge’s continuing to operate Line 5 in trespass on portions of the Reservation for which certain, longstanding rights of way have now expired. At summary judgment, the court: decided that Enbridge was in trespass and unjustly enriched by operating the pipeline on 12 land parcels owned in whole or in part by the Band for which the rights of way had expired; and dismissed Enbridge’s counterclaims for breach of contract. (Dkt. #360.) However, the court concluded that there were genuine disputes of material fact relating to the Band’s public nuisance claim and request for injunctive relief, leaving four, primary factual disputes to be decided at trial: (1) whether Enbridge’s operation of Line 5 on the Reservation constitutes a public nuisance at its crossing of a meander on the Bad River, where the greatest risk of a pipe

failure currently exists within the Band’s tribal territory; (2) if so, what form of injunctive relief, if any, should be imposed to abate that nuisance and address Enbridge’s trespass; (3) what additional remedies, if any, should be imposed on Enbridge based on the court’s findings as to liability; and (4) whether Enbridge was entitled to any relief on its remaining counterclaims.

After reviewing relevant expert reports, deposition designations and other voluminous, additional written submissions by the parties, the court held a six-day bench trial in October 2022 on these remaining issues. Shortly after the trial, the court issued an opinion and order: (1) denying Enbridge’s request for declaratory and injunctive relief on its remaining counterclaims; and (2) directing the parties to meet and confer on specific issues relating to the Band’s public nuisance claim, including attempting to agree on a

shutoff and purge plan for Line 5 at the Bad River meander. (Dkt. #612.) The parties submitted alternative shutoff and purge proposals and more recently, provided an update regarding conditions at the Bad River meander as of May 2023. Specifically, as to the latter, the Band filed an Emergency Motion for Injunctive Relief (dkt. #628), indicating that recent erosion during spring flooding at the Bad River meander was so substantial that the threat of a Line 5 rupture is significantly greater than it was at the time of trial, and if

it was not before, is now at risk of an “imminent,” catastrophic rupture, requiring an immediate shutdown. After giving Enbridge a few days to marshal a response, the court held an in-person, evidentiary hearing on May 18, 2023, to address the changing conditions at the meander. Having reviewed the parties’ shutoff and purge plans, as well as the additional

evidence and arguments provided by the parties in writing and at the May 18 hearing, the court renders the following opinion and order on the remaining issues before it. As explained in this opinion, the court concludes that a rupture of Line 5 at the Bad River meander would unquestionably be a public nuisance, and that the current conditions at the meander create a real and unreasonable risk of that nuisance occurring such that

equitable relief is warranted. However, the current threat of rupture is still not so imminent that an immediate shutdown of the pipeline is necessary to prevent the nuisance. This is particularly true when viewed in light of larger public interests in avoiding a precipitous shutdown of Line 5, the Band’s own refusal to allow any remediation efforts at the meander to delay, if not avoid, a rupture and materially reduce its environmental impact, and the likelihood that a shutdown will spark at least temporary shortages and increased prices for

refined gas, propane and butane in the Upper Midwest and Eastern Canada, creating hardships, especially for the poor and other economically challenged households. Nevertheless, given the environmental risks, the court will order Enbridge to adopt a more conservative shutdown and purge plan as discussed in detail below. In addition, with respect to the Band’s trespass claim, the court will award $5,151,668 to the Band in profits-based damages for Enbridge’s past trespass. Going forward, the court will also order

Enbridge to continue paying the Band, according to the formula set forth below, for each quarter that Line 5 operates in trespass on the 12 allotment parcels. Finally, the court will enjoin Enbridge to remove its pipeline within three years from any parcel within the Band’s tribal territory on which it lacks a valid right of way and to provide reasonable remediation at those sites.

FACTS1

A. Overview Enbridge operates a network of pipelines and other infrastructure known as the “Lakehead system,” which transports light crude oil and NGLs originating in Western Canada to refineries in the United States and Eastern Canada. The specific pipeline that is the subject of this lawsuit, Line 5, is part of the Lakehead system and transports about 23 million gallons of crude oil and NGLs daily over some 450 miles originating in Superior,

Wisconsin and terminating in Sarnia, Ontario. In Northern Wisconsin, 12 miles of Line 5 runs underground through the Bad River Reservation, including through 12 allotment parcels on which Enbridge’s rights of way expired in June 2013. The Band’s identity and way of life is rooted in reliance on and stewardship for their land, and Band members have become increasingly concerned that Line 5, which is now

some 70 years old, will rupture and cause catastrophic environmental degradation to their lands and waters, particularly to the Bad River and potentially Lake Superior watersheds, concerns shared by a number of other individuals, businesses and entities dependent on

1 The court provided a detailed, factual background of this case in its summary judgment opinion (dkt. #360), as well as its most recent posttrial decision (dkt. #619). This relatively brief summary of the facts includes further findings established at trial and the subsequent evidentiary hearing in May, although additional facts relevant to the remaining issues are set out in the court’s opinion below where most pertinent to its analysis. those same resources for enjoyment and commerce.2 (Dkt. #599 (10/24/22 AM Trial Tr.) 64–126 (Band witnesses).) Indeed, the Band has designated the Bad River itself as an “outstanding tribal resource water,” which is the highest category of waters on the

Reservation and subject to the most protection under the Band’s “antidegradation policy,” as approved by the Environmental Protection Agency. (Dkt. #600 (10/25/22 AM Trial Tr.) 16 (Naomi Tillison).) The EPA has also delegated to the Band the authority to administer federal and tribal water quality standards and certifications consistent with the Clean Water Act and applicable regulations. (Id. at 12–13 (Tillison).)

As noted, the area of most concern on the Reservation is where Line 5 runs underground through a specific “meander” on the Bad River.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cayuga Indian Nation of New York v. Pataki
413 F.3d 266 (Second Circuit, 2005)
Countyof Oneida v. Oneida Indian Nation of NY
470 U.S. 226 (Supreme Court, 1985)
Amoco Production Co. v. Village of Gambell
480 U.S. 531 (Supreme Court, 1987)
City of Sherrill v. Oneida Indian Nation of NY
544 U.S. 197 (Supreme Court, 2005)
Davy Van De Sande v. Jennifer Van De Sande
431 F.3d 567 (Seventh Circuit, 2005)
Steven Olson v. Bemis Company, Incorporated
800 F.3d 296 (Seventh Circuit, 2015)
Liu v. SEC. & Exch. Comm'n
591 U.S. 71 (Supreme Court, 2020)
LAJIM, LLC v. Gen. Elec. Co.
917 F.3d 933 (Seventh Circuit, 2019)

Cite This Page — Counsel Stack

Bluebook (online)
Bad River Band of the Lake Superior Tribe of Chippewa Indians of the Bad River Reservation v. Enbridge Energy Company, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/bad-river-band-of-the-lake-superior-tribe-of-chippewa-indians-of-the-bad-wiwd-2023.