B. Mifflin Hood Co. v. Lichter

106 F. Supp. 220, 1950 U.S. Dist. LEXIS 4281
CourtDistrict Court, E.D. Tennessee
DecidedNovember 22, 1950
DocketCiv. No. 550
StatusPublished
Cited by3 cases

This text of 106 F. Supp. 220 (B. Mifflin Hood Co. v. Lichter) is published on Counsel Stack Legal Research, covering District Court, E.D. Tennessee primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
B. Mifflin Hood Co. v. Lichter, 106 F. Supp. 220, 1950 U.S. Dist. LEXIS 4281 (E.D. Tenn. 1950).

Opinion

DARR, Chief Judge.

The plaintiff sues the defendant for a balance of $15,954.62 alleged to be due for concrete masonry blocks furnished by the plaintiff to the defendant as materials to be used in the construction of dwelling units at the townsite of the Clinton Engineering Works at Elza, Anderson County, Tennessee, being a part of the Oak Ridge Project. The defendant was subcontractor for the erection of the said dwelling units under the prime contractor, O’Driscoll & Groves,Inc., who was operating under a negotiated contract with the United States.

The complaint is based on orders entered by the defendant with the plaintiff on April 3, 1943 and April 14, 1943 for the manufacture, purchase and delivery of concrete building blocks, and the failure of the defendant to pay therefor in full as required.

The defendant denies that there was any order for the blocks except an order bearing date April 3, 1943 and denies that it is indebted to plaintiff in any sum. It claims credit for certain additional labor costs of $9,835.56 which it says was caused by plaintiff’s delay in furnishing materials as required and by plaintiff’s providing blocks which were condemned and which defendant was required to remove after having been put in place in the buildings. Defendant also claims a deduction of $2,156.50 for broken blocks caused in delivery by plaintiff’s agents.

The defendant, in addition, pleads accord and satisfaction by reason of the fact that on two checks issued to plaintiff there was an endorsement which amounted to an acceptance of defendant’s claims as credits, as will more fully appear hereinafter.

The defendant also filed a counterclaim for $17,092.56 for certain items of expense which it had incurred on account of the plaintiff’s delay and for breach of original contract in making timely delivery of the 8x8x16 blocks.

On July 16, 1945, the parties entered into a stipulation to the effect that the amount sued for by the plaintiff and claimed to be due it as unpaid is the sum of $12,175.20; that the defendant claims and the plaintiff disputes the allowance of

(1) $8,917.04 for additional labor charges due to plaintiff’s failure to deliver 4 x 8 x 16 and 12 x 8 x 12 and special sizes of blocks as required by the contract, said sum consists of three claims, viz.:
(a) $6,223.29 for additional labor costs account installing the blocks as a separate operation.
(b) $1,883.11 additional costs for using two blocks 8x8 x 16 instead of one 12 x 8 x 12.
(c) $810.64 ten percent overhead.
(2) $918.52 for labor and material charges for removal, tearing down and rebuilding walls, account rejection of Grey Products 2-cell blocks.
(3) $524 for breakage from August 1, 1943 to end of work.
(4) $1,632.50 breakage from beginning through July 31, 1943.
(5) $17,092.56 counterclaim of defendant for damage for delay in delivery of 8 x 8 x 16 blocks.

Item 2 is apparently reduced to $912.32 in the present claim; so that the total deductions which the defendant claims amount to $11,985.86. The balance in plaintiff’s favor would thus only be $189.34 after allowing these credits. Separate and apart from this is defendant’s counterclaim for $17,092.56.

The issues are thus limited (1) to the validity of defendant’s claims for $8,917.04 for additional labor charges, $912.32 for labor charges in connection with Grey Products 2-cell blocks, and the two claims aggregating $2,156.50 for breakage, (2) to the validity of defendant’s claim of accord and satisfaction growing out of the endorsement of the checks, and (3) the validity of defendant’s counterclaim.

The defendant’s claims of set-off under (1) above will be first discussed without [223]*223regard to the efficacy of the plea of accord and satisfaction.

The following facts are established by the weight of the evidence.

The defendant having a subcontract for the construction of eight hundred fifty houses at the Clinton Engineering Works at Elza, Tennessee, gave the following offer to plaintiff, bearing date of April 3, 1943, for the furnishing of concrete blocks for said buildings, which offer was accepted by plaintiff.

[224]

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Arcata Graphics Co. v. Heidelberg Harris, Inc.
874 S.W.2d 15 (Court of Appeals of Tennessee, 1993)
Cole v. Henderson
454 S.W.2d 374 (Court of Appeals of Tennessee, 1969)

Cite This Page — Counsel Stack

Bluebook (online)
106 F. Supp. 220, 1950 U.S. Dist. LEXIS 4281, Counsel Stack Legal Research, https://law.counselstack.com/opinion/b-mifflin-hood-co-v-lichter-tned-1950.