B & B Schiffahrts GMBH & Co. v. American Diesel & Ship Repairs, Inc.

136 F. Supp. 2d 590, 2001 WL 301157
CourtDistrict Court, E.D. Louisiana
DecidedMarch 13, 2001
DocketCIV.A. 99-3860
StatusPublished
Cited by7 cases

This text of 136 F. Supp. 2d 590 (B & B Schiffahrts GMBH & Co. v. American Diesel & Ship Repairs, Inc.) is published on Counsel Stack Legal Research, covering District Court, E.D. Louisiana primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
B & B Schiffahrts GMBH & Co. v. American Diesel & Ship Repairs, Inc., 136 F. Supp. 2d 590, 2001 WL 301157 (E.D. La. 2001).

Opinion

FINDINGS OF FACT AND CONCLUSIONS OF LAW

BARBIER, District Judge.

This matter came on for trial before the Court, sitting without a jury, on February 12, 2001. Following the trial, the Court allowed the parties until February 15, 2001 to file any briefs on the issue of attorney’s fees, at which time the Court took the matter under submission. The parties have stipulated to many of the facts as set forth in the pre-trial order. In accordance with Federal Rule of Civil Procedure 52(a), the Court now renders its findings of fact and conclusions of law. To the extent the findings of fact are more properly classified as conclusions of law, they should be so considered; and to the extent the conclusions of law are more properly classified as findings of fact, they should be so considered.

FINDINGS OF FACT

1. Plaintiff, B & B Shiffarhts GMBH & Co. (“B & B”), is the owner of the M/V WESER, an oceangoing cargo vessel which experienced engine problems during a call in New Orleans in September, 1999. On or about September 25, 1999, a survey of the engine was conducted in the presence of, among others, a representative of the engine’s manufacturer (Walter Brede), a surveyor appointed by the vessel’s hull underwriters (Ben Haveman), and an independent surveyor for the Classification Society of the vessel (Alfred Schroeder), which revealed damage to the main engine crankshaft.

2. The crankshaft is a large, cylindrical piece of steel which connects the engine pistons _ to the tail shaft, which in turn rotates the ship’s propellor. The crankshaft is primarily made up of component parts called “crankpins” and “journals” which must be perfectly round within extremely small tolerances measured in fractions of millimeters. An engine component called a “bearing” fits over and rotates around the crankshaft and connects the engine’s pistons, which move up and down, to the crankshaft, which turns on its longitudinal axis. If the crankshaft does not function normally, the engine will break down and the ship will lose power and steerage, with ’ potentially disastrous consequences.

3. When it was removed from the engine on or about October 7, 1999, the *592 WE SER crankshaft was found to be bent (a condition called “run out”), and certain of its crankpins were found to be in an oval rather than a perfectly cylindrical shape. These problems had to be repaired before the ship could return to service.

4. B & B contacted defendant American Diesel & Ship Repairs, a New Orleans-based engine repair company, about performing the necessary work. Representatives of American Diesel inspected the crankshaft and in due course made an oral repair proposal,- which was accepted by plaintiff. This contract was not reduced to writing, which is not unusual in the industry for jobs of this size and type.

5. For a quoted price of $8,600.00, American Diesel undertook to eliminate or reduce to within acceptable tolerances the bend in the crankshaft, or “run out”, and to eliminate or reduce to within acceptable tolerances the ovality in the crankpins.

6. Because American Diesel lacked the equipment necessary to repair such a large crankshaft, American Diesel in turn subcontracted the repair work to defendant Fusion, Inc. (“Fusion”), a repair company based in Houston. Fusion agreed to charge American Diesel $6,300.00 for the work.

7. American Diesel and Fusion did not sign a contract for the subcontracted repairs.

8. On or about October 9, 1999, American Diesel transported the crankshaft by truck to Fusion’s facility in Houston and then retrieved it by truck about a week later. While at Fusion, the crankshaft pins and journals were ground with a grinding tool especially designed for this purpose. This process necessarily reduces the circumference of the crankshaft, and, if done properly by the technician, would in this case have eliminated the bend in the crankshaft and have produced pins and journals which were perfectly cylindrical, to within acceptable tolerances.

9. By industry rule, whenever a crankshaft is ground, it is ground in half-millimeter increments. This is because the engine bearings, which must fit perfectly around the crankshaft to within fractions of a millimeter, are manufactured in half-millimeter increments.

10. Following the attempted repairs by Fusion, when the crankshaft was inspected by B & B’s representative and American Diesel at American Diesel’s facilities on or about October 22, 1999, in contrast to Fusion’s post-repair measurements, American Diesel’s and B & B’s measurements, which were in agreement, showed the crankshaft to be within unacceptable manufacturer tolerances and in worse condition than pri- or to the repairs. Specifically, the shaft had more “run out”, it was tapered (that is, the journals were larger on one end than they were on the other), and the crankpins had more ovality.

11. The shaft had been transported to and from Houston on a flatbed truck and supported in a special box. There is no evidence that there was any accident, dropping of the shaft, or any other circumstance or condition which could have caused the “run out.” Upon receipt of the shaft at Fusion, Fusion did not indicate in any report, measurement, phone call, or otherwise, that the shaft had any additional “run out” or that in any respect it was in worse condition than indicated by the measurements provided by B & B and American Diesel. Furthermore, upon inspection after the repairs, there was no indication of any physical damage to the shaft which would have been present had the shaft been dropped. The Court finds that the additional “run out” was caused due to improper repairs or handling of the shaft by Fusion. Likewise, because tapering can only occur due to removal (grinding) of more material in one area than another, and prior to Fusion’s repairs the shaft was *593 not tapered, the Court finds that the tapering occurred during the grinding process at Fusion’s shop. Similarly, after the Fusion repairs, the crankpins remained oval. The Court finds Fusion improperly repaired the crankpins because it did not cure the crankpin ovality.

12. Fusion has suggested that the problems noted in the post-repair inspections were the result of mismeasurement, because American Diesel’s micrometer was not calibrated. The Court does not find this to be a credible argument.

13. At the time the shaft was first taken to American Diesel’s facilities on or about October 8, 1999, it was measured with American Diesel’s micrometer by an American Diesel representative. The measurements were witnessed by several others, including Ben Haveman, a B & B representative, a class surveyor, and/or an engine manufacturer’s representative. There was no dispute by any of these individuals regarding the measurements taken nor the operation of the micrometer.

14. After the shaft was taken to Fusion, Fusion did not dispute the measurements by American Diesel or others, which it should have and would have done immediately had there been a significant discrepancy. Instead, Fusion conducted the repairs and returned the shaft.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
136 F. Supp. 2d 590, 2001 WL 301157, Counsel Stack Legal Research, https://law.counselstack.com/opinion/b-b-schiffahrts-gmbh-co-v-american-diesel-ship-repairs-inc-laed-2001.