Nathaniel Shipping, Inc. v. General Electric Co.

920 F.2d 1256, 1991 WL 42
CourtCourt of Appeals for the Fifth Circuit
DecidedJanuary 15, 1991
DocketNos. 88-3277, 88-3817
StatusPublished
Cited by12 cases

This text of 920 F.2d 1256 (Nathaniel Shipping, Inc. v. General Electric Co.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fifth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Nathaniel Shipping, Inc. v. General Electric Co., 920 F.2d 1256, 1991 WL 42 (5th Cir. 1991).

Opinion

JOHN R. BROWN, Circuit Judge:

Foreword

As the Court is divided on at least one significant, decisive issue, this opinion1 is constructed sharply to delineate the differences together with specific determinations as to the outcome of the appeal.

The Court is together on Part I. In Part II, the Court parts company. Judge Brown, in what is essentially a dissent to the Court’s holding in Part III, is of the view that East River does not cut off G.E.’s liability to Nathaniel Shipping. Judges Reavley and Higginbotham, whose views are articulated in Part III, are of the contrary view which prevails to require reversal of the District Court’s judgment in favor of Nathaniel Shipping. All agree on Part IV interpretation and application of the Red Letter Clause. All agree as to Part V affirming G.E.’s liability to LGS for [1258]*1258the costs ($27,373.59) incurred by it in effecting warranty reconditioning due by G.E. We agree as to Part VI on all items, some of which will have little consequence in view of the reversal in Part III, but which also reverses the award of attorney’s fees to both Nathaniel Shipping and LGS.

* * sj: * * *

The principal issue in this case is whether a shipowner’s claim against the subcontractor with whom it has no contractual relationship or privity for substantial damage caused by the subcontractor’s improper performance of the subcontract is barred by the Supreme Court’s decision in East River.2 The other issue concerns the efficacy of a limitation of liability clause, often called a “red letter clause,” printed on the back of a standard form contract. First, is the clause valid against a claim for economic damages by a third party, with whom the defendant is not in privity, for negligent performance of a service contract? Second, is the clause valid to limit recovery by the prime contractor for costs incurred in remedying the defendant’s negligence, when the small print also contained a warranty to repair or remedy any deficiency in the performance of the contract? The district court answered both of these questions in the negative. The Court’s answers are set forth in Parts III, IV, V and VI.

I. The Pliable Template

The following facts, found by the district court, are undisputed. On March 19, 1984, the thrust block on the main engine of the SERENA fractured during a voyage to New Orleans. The thrust block is that part of the shaft assembly that absorbs the thrust from the vessel’s propeller. It consists of a large steel block which measures approximately 8 to 9 feet across by 4 to 5 feet high by 3 to 4 feet deep. It is fastened to the aft facing of the engine bed plate by a series of bolts, and secured by thrust pads to cushion the force received. Nathaniel Shipping, Inc., the owner of the SERENA, contracted with Louisiana Gulf Shipyards, Inc. (LGS), to repair the thrust block. Nathaniel ordered a new block from the original manufacturer, without bolt holes, because Nathaniel and LGS decided to use the old thrust block as a guide to exactly match the placement of the bolt holes on the new block.

LGS subcontracted the drilling of the holes in the new thrust block to General Electric Company (G.E.) at a cost of $4400. LGS and G.E. discussed the purpose of the work and the means by which G.E. was to perform the drilling, and G.E. understood that it was to match the holes in the new block as closely as possible to the alignment in the old block. However, when the old block was delivered to G.E.’s workshop, its machinist fashioned a template from steam gasketing material, which is pliable, rather than from a less flexible material, such as steel. In the process of making the template and transferring it to the new block, the measurement of the holes became distorted, and hence the holes G.E. drilled in the new block were not properly aligned. The result was that extensive repair measures were required, involving additional expenditures by both Nathaniel and LGS, including a loss to the vessel which the district court calculated to be 56 days’ time.

The parties then filed various complaints against each other, all of which were settled before trial, save Nathaniel’s and LGS’s claims against G.E. After a bench trial, the district court found that G.E. had negligently drilled the bolt holes, and awarded damages, including attorney’s fees, to both Nathaniel and LGS. The district court also made the following legal conclusions regarding the red letter clause, contained in paragraph 8 of the proverbial small print on the back of G.E.’s contract with LGS.3 First, the clause was inapplicable to Nathaniel because Nathaniel was not a party to the contract. Second, the costs incurred by LGS were recoverable under paragraph 1 of the contract, in which G.E. warranted to repair, rebuild or modify its [1259]*1259work if it was not of the kind or quality specified in the contract. Third, the clause was invalid as vague, as well as void as against public policy because the amount of the limitation of damages, $4400, was an insufficient deterrent to negligence by G.E.

In this appeal, G.E. does not contest the district court’s factual findings or computation of damages. But it challenges the district court’s legal interpretation and the validity and scope of the red letter clause, as applied to both Nathaniel’s and LGS’s claims, G.E. specifically challenges liability under East River for Nathaniel’s damages. Nathaniel cross-appeals on the amount of damages awarded to it by the district court.

II. Of Red Letters and Foreseeable Plaintiffs: Another Round in the Struggle Between Tort and Contract

The assault on the citadel of commercial tort law proceeds these days apace.4 As aptly summarized in the title of Professor William Jones’s recent scholarly survey of the field, Product Defects Causing Commercial Loss: The Ascendancy of Contract over Tort,5 the modern trend is to permit commercial parties to freely allocate, via contract, the risk of purely economic loss stemming from defective products.6 However, for the reasons explained below, I do not think that the principles underlying this theory of contractual freedom extend so far as to bar Nathaniel’s claim for damages, nor can the contract at issue be read to bar LGS’s claims for damages.

Nathaniel’s Claim: Steering Clear of East River

G.E.’s argument on appeal relies on the Supreme Court’s recent admiralty decision, East River S.S. Corp. v. Transamerica Delaval,7 which held that “a manufacturer in a commercial relationship has no duty under either a negligence or strict products-liability theory to prevent a product from injuring itself.”8 This preference for contract law over tort was extended beyond the precise scope of the UCC by this circuit in Employers Insurance of Wausau v. Suwanee River Spa Lines,9 which held that “a plaintiff may not recover purely economic losses on a theory of negligent performance of a contract for professional services when the services were rendered as a part of the manufacture or construction of a product.”10

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
920 F.2d 1256, 1991 WL 42, Counsel Stack Legal Research, https://law.counselstack.com/opinion/nathaniel-shipping-inc-v-general-electric-co-ca5-1991.