Attorney General v. Michigan Public Service Commission

316 N.W.2d 187, 412 Mich. 385, 1982 Mich. LEXIS 501
CourtMichigan Supreme Court
DecidedJanuary 27, 1982
DocketDocket Nos. 67938, 67944, and 67945. (Calendar Nos. 23, 24, and 25)
StatusPublished
Cited by20 cases

This text of 316 N.W.2d 187 (Attorney General v. Michigan Public Service Commission) is published on Counsel Stack Legal Research, covering Michigan Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Attorney General v. Michigan Public Service Commission, 316 N.W.2d 187, 412 Mich. 385, 1982 Mich. LEXIS 501 (Mich. 1982).

Opinion

Levin, J.

The question presented concerns the scope of inquiry by the Michigan Public Service Commission when a public utility requests authorization to issue securities. We are persuaded, upon examination of the language of this state’s utility securities act, 1 Michigan cases construing the act, cases construing similar statutes in other jurisdictions, and Michigan’s utility regulation scheme, that the scope of inquiry in a securities issue proceeding does not extend to the wisdom of the *392 project which a utility seeks to fund through the issuance of long-term securities.

I

Three cases have been consolidated in this appeal, each presenting the same issue. 2

In No. 67944 ("Edison I”), the utility, in July 1979, sought approval pursuant to the act for the issuance of $625 million in securities, 3 part of which would finance the continued construction of the Enrico Fermi 2 nuclear generating plant and the Belle River coal-fired generating plants and part of which would retire maturing short-term and long-term debt. At the commission hearing, the Attorney General and Michigan Citizens Lobby (MCL) intervened, contending that the plants were unnecessary and unreasonably costly. Specifically, the intervenors criticized the utility’s 15-year forecast of energy needs, termed the utility’s planned "reserve margins” (capacity in excess of anticipated peak demand) unjustifiably large, asserted that a nuclear generating plant is considerably more expensive than a coal-fired unit of similar capacity, and argued that continual cost *393 overruns indicated that Fermi 2, if completed, would prove far more expensive than the utility had originally calculated. On April 1, 1980, the commission authorized issuance of the securities. Declining to consider the evidence pertaining to ongoing plant construction presented to the hearing officer, the commission found construction of the plants a lawful purpose of the utility and found the issuance of securities reasonably required to provide funds for the construction of the plants. 4 On May 9, 1981, the Attorney General and MCL filed a delayed application for leave to appeal in the Court of Appeals, which was denied on June 11, 1980. On May 11, 1981, this Court remanded the cause to the Court of Appeals for consideration as on leave granted. 5

In No. 67945 CEdison II”), the utility sought authorization in July 1980 to issue an additional $1,996 billion in securities, 6 primarily to finance continued construction of the power plants and to retire short-term and long-term debt already incurred. Again the Attorney General and MCL intervened, challenging the issuance of the securities insofar as the proceeds would be used in respect to the construction of the power plants, which the intervenors claimed was unreasonable. *394 On July 7, 1981, the commission approved the issuance of the securities, and declared that "[evidence relating to electric load forecasting and generating plant alternatives is irrelevant and immaterial in carrying out the intent of 1909 PA 144 [the utility securities act]”. 7 On August 6, 1981, the Court of Appeals stayed the commission’s order approving issuance of the securities. This Court denied an emergency application for leave to appeal the stay. 8

In No. 67938 ("Consumers Power”), the utility sought permission in December 1979 to issue $564 million in securities, 9 primarily to finance the continued construction of the Midland nuclear generating plant and to retire maturing short-term and long-term debt. The Attorney General and MCL intervened in this proceeding as well, arguing that the Midland nuclear plant had far exceeded original cost projections and that continued construction was unjustified. The commission approved the issuance of the securities on August 4, 1981, and again declared that a securities issue proceeding was an inappropriate time to inquire into the utility’s construction program. 10 On Sep *395 tember 14, 1981, the Court of Appeals granted the intervenors’ application for leave to appeal, but denied a request for a stay of the commission’s order authorizing issuance of the securities.

On September 15, this Court, in Consumers Power, granted a stay of the commission’s order and bypass of the Court of Appeals, granted bypass on its own initiative in Edison I and II, and ordered all three cases consolidated for argument. 11

Following oral argument, this Court, on October 16, 1981, lifted the stays in Edison II and Consumers Power. 12

II

The Attorney General and MCL contend that the utility securities act requires the commission to determine that projects to be funded by the issuance of securities are reasonable. The commission and the utilities contend that the act grants the commission broad discretion in determining the scope of inquiry in a securities issue proceeding and does not mandate an inquiry into the reasonableness of a project.

We conclude that the utility securities act does not provide for an inquiry into the reasonableness of a project. Because such an inquiry is not material in a proceeding under the utility securities act, the commission has no discretion in such a *396 proceeding to inquire into the reasonableness of a project.

The Michigan cases cited by the Attorney General and MCL do not hold that the commission must investigate the wisdom of underlying projects; those cases indicate that the concern of the act is more limited. The cases from other jurisdictions cited by the Attorney General and MCL provide limited guidance.

We hold that, in a proceeding under the utility securities act, the inquiry is limited to whether there is need to issue securities to obtain funds for a lawful purpose of the utility and does not extend to whether, to accomplish that purpose, there is need for the project to which the funds will be devoted. The inquiry is whether funds are required to construct the project — the need for the funds, not the need for the project.

A

The utility securities act, as amended, is set forth in the margin. 13 Subsection (1) provides that *398 a utility may issue long-term securities only if authorized by the commission.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Leggett v. Duke Energy Corp.
308 S.W.3d 843 (Tennessee Supreme Court, 2010)
Abate v. PSC
527 N.W.2d 533 (Michigan Court of Appeals, 1994)
Attorney General v. Public Service Commission
472 N.W.2d 53 (Michigan Court of Appeals, 1991)
Ass'n of Businesses Advocating Tariff Equity v. Public Service Commission
173 Mich. App. 647 (Michigan Court of Appeals, 1988)
Union Carbide Corp. v. Public Service Commission
428 N.W.2d 322 (Michigan Supreme Court, 1988)
Schneidewind v. ANR Pipeline Co.
485 U.S. 293 (Supreme Court, 1988)
ANR Pipeline Co. v. Schneidewind
627 F. Supp. 923 (W.D. Michigan, 1985)
Fitchburg Gas & Electric Light Co. v. Department of Public Utilities
477 N.E.2d 372 (Massachusetts Supreme Judicial Court, 1985)
Iowa-Illinois Gas & Electric Co. v. Iowa State Commerce Commission
347 N.W.2d 423 (Supreme Court of Iowa, 1984)
Western Union Telegraph Co. v. Public Service Commission
338 N.W.2d 731 (Michigan Court of Appeals, 1983)
Pennsylvania Public Utility Commission v. Philadelphia Electric Co.
460 A.2d 734 (Supreme Court of Pennsylvania, 1983)
Pennsylvania Pub. Util. v. Phil. Elec.
460 A.2d 734 (Supreme Court of Pennsylvania, 1983)
Philadelphia Electric Co. v. Pennsylvania Public Utility Commission
455 A.2d 1244 (Commonwealth Court of Pennsylvania, 1983)
Soap & Detergent Ass'n v. Natural Resources Commission
330 N.W.2d 346 (Michigan Supreme Court, 1982)

Cite This Page — Counsel Stack

Bluebook (online)
316 N.W.2d 187, 412 Mich. 385, 1982 Mich. LEXIS 501, Counsel Stack Legal Research, https://law.counselstack.com/opinion/attorney-general-v-michigan-public-service-commission-mich-1982.