Atlanta Gas Light Co. v. Georgia Public Service Commission

262 S.E.2d 628, 152 Ga. App. 366, 1979 Ga. App. LEXIS 2931
Court of Appeals of Georgia·Decided November 16, 1979·No. 58397·Published·Cited by 4 cases

Opinion

Deen, Chief Judge.

1. There was in the record considerable evidence introduced in an effort to show that the use of natural gas *370 as a chemical used, in the manufacture of fertilizer and other products serving the food industry was in its own way as important to the health of consumers generally as its use in the conventional line of supplying heating and energy requirements. There was also considerable evidence indicating that while the rates at issue here would in the first instance apply only to CNC and Nipro, there were other industrial consumers extant and still others on the horizon who might be eligible for whatever rate schedule was set, and that such rate schedule should therefore be so tailored as to be available to others in substantially the same category. This, however, still pinpoints the rates at issue narrowly within only a part of one of the nine categories to which the rates are applied. As is pointed out in Ga. Power Co. v. Ga. Public Serv. Comm., 231 Ga. 339, 344 (201 SE2d 423) (1973) the appellate courts are not in the ratemaking business. That case involved a petition for a general rate increase, as to which the standards of constitutional substantive due process demand that the utility be allowed to earn an amount to compensate its investors, maintain its credit, and attract necessary capital as well as to maintain the requisite level of services. Id., p. 341. The appellant here urges that although the testimony in the case indicated that it would be entitled to a return on its investment of 9.57%, it has for the last two years stayed materially under this figure, from which it argues that even if the rate set for these particular users comports with reimbursement for services to other customers (which Atlanta Gas says it does not) it would fail to bring in 9.57% revenue on the percentage of the company investment which (apparently based on the ratio of the number of therms used by CNC and Nipro to the total therms used by all customers during the same period) would "carry its own weight” of allocated costs and return on the investment. We agree that this might be a consideration if the issue before the commission had been a general rate increase. But it appears that Atlanta Gas Light has proposed rate figures which would boost the rate base presently used (which is the same rate base used in the last general rate increase for all consumers) above that of the other consumers in order to ensure that the return from these two customers would *371 give the desired percentage of profit regardless of the general rate structure as it presently exists. We agree with the appellees that if the utility feels that its rate of return generally is insufficient its remedy is to ask for a general rate increase, but, as is generally held, an attempt to bolster rates piecemeal results in havoc. "If by pleading excessive rate of return parties could... have a complete review of rate structure on every occasion that a matter relating to rate arises, the reasonable regulation of rates would be impossible.” State v. Carolinas Committee for Industrial Power Rates, 257 N. C. 560 (126 SE2d 325) (1962). The same rule applies to the plea that the rate of return is generally insufficient. We do not find the arguments relating to the overall rate of return on the utility’s investment relevant to setting the rate of a single class of customers. It should also be noted that the contract here in dispute arises following a Federal Power Commission case in 1976 involving the amount of additional gas requirements sought by CNC and Nipro the settlement of which provided for increased gas feedstock supplies, followed by lengthy negotiations between the corporations and the utility and a failure of the parties to agree on the formula for supplying the increased demands, but in a close perusal of the record we find nothing by way of either agreement or court order specifying that the new allocation should be bottomed on a rate base different from that generally applicable in the rate structure approved at that time.

2. There was filed with the Public Service Commission’s order in this case and forwarded with the record to the superior court the affidavit of James Crudup, director of utilities engineering of the commission, and three exhibits attached thereto, representing the current rate schedules N-9 (industrial interruptible service) and N-15 (preferred interruptible service) (being two other categories of the nine referred to above) and certain arithmetical calculations designed to show the effect in dollars of proposed rate adjustments, all for the year 1976, showing revenues of CNC and Nipro as of the test year (Docket 2943-U), of the last docketed general rate proceeding. These latter included CNC and Nipro rates effective October 18, 1974, and September 30, 1977, *372 respectively (matters necessarily known to the appellant and to these two corporations) plus the statement of new requirements agreed upon between the parties, plus the multiplication of the number of therms of supplemental supplies by the price per therm. This, by the process of addition of new and supplemental requirements at the stated therm price, yielded the total new revenue in dollars. No new facts were thereby added to the record.

Code § 3A-114 (a) (8) (G) of the Administrative Procedure Act provides that in all contested cases the record shall include all staff memoranda or data submitted to the hearing officer or members of the agency in connection with their consideration of the case. Code § 3A-116 (d) provides: "Official notice may be taken of judicially recognizable facts. In addition, official notice may be taken of technical or scientific facts within the agency’s specialized knowledge. Parties shall be notified either before or during the hearing, by reference in preliminary reports or otherwise, of the material noticed, including any staff memoranda or data, and they shall be afforded an opportunity to contest the material so noticed. The agency’s experience, technical competence, and specialized knowledge may be utilized in the evaluation of the evidence.”

Free access — add to your briefcase to read the full text and ask questions with AI

Atlanta Gas Light Co. v. Georgia Public Service Commission, 262 S.E.2d 628, 152 Ga. App. 366, 1979 Ga. App. LEXIS 2931 (Ga. Ct. App. 1979).

262 S.E.2d 628 (Atlanta Gas Light Co. v. Georgia Public Service Commission) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Thebaut v. Georgia Board of Dentistry
509 S.E.2d 125 (Court of Appeals of Georgia, 1998)
Lasseter v. Georgia Public Service Commission
319 S.E.2d 824 (Supreme Court of Georgia, 1984)
GEORGIA RETAIL ASSOCIATION v. Georgia Public Service Commission
300 S.E.2d 544 (Court of Appeals of Georgia, 1983)