Athey Creek Christian Fellowship v. Clackamas County

CourtDistrict Court, D. Oregon
DecidedJuly 30, 2024
Docket3:22-cv-01717
StatusUnknown

This text of Athey Creek Christian Fellowship v. Clackamas County (Athey Creek Christian Fellowship v. Clackamas County) is published on Counsel Stack Legal Research, covering District Court, D. Oregon primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Athey Creek Christian Fellowship v. Clackamas County, (D. Or. 2024).

Opinion

UNITED STATES DISTRICT COURT DISTRICT OF OREGON PORTLAND DIVISION

ATHEY CREEK CHRISTIAN FELLOWSHIP,

Plaintiff, Case No. 3:22-cv-01717-YY v. OPINION AND ORDER CLACKAMAS COUNTY, Defendant. YOU, Magistrate Judge. In 2006, plaintiff Athey Creek Christian Fellowship secured a conditional use permit (“CUP”) to build a large church building on its property in West Linn, Oregon. For various reasons, plaintiff was unable to build the entire project at the outset, and instead constructed a smaller “phase 1” building sometime around 2013. In 2022, plaintiff was ready to build “phase 2”, i.e., the remainder of the project, and attempted to acquire the required building permits from defendant Clackamas County. The County refused to issue the permits on the basis that the 2006 CUP had expired because plaintiff had failed to acquire the building permits for phase 2 or seek an extension of the 2006 CUP during the two-year time period for which the 2006 CUP was valid. Plaintiff then sued the County alleging that the County’s zoning scheme—which at the time required churches, but not some other types of secular uses, to obtain a conditional use permit in the zoning category applicable to plaintiff’s property—and refusal to issue building permits under the 2006 CUP violated plaintiff’s rights under the Religious Land Use and Institutionalized Persons Act of 2000 (“RLUIPA”), and its constitutional right to freely exercise its religious beliefs. Plaintiff also asserts that the County should be estopped from now preventing plaintiff from building phase 2 because it initially told plaintiff that building in phases

was “fine” and allowed plaintiff to build phase 1 in 2013. Currently pending is the County’s motion for summary judgment on all of plaintiff’s claims. ECF 43. Plaintiff has also moved for summary judgment on its RLUIPA substantial burden claim. ECF 42. As explained more fully below, plaintiff is not entitled to equitable estoppel because the alleged statements from the County regarding building in phases and allowing plaintiff to build phase 1 in 2013 were not material misstatements of facts upon which plaintiff could have reasonably relied to believe that the conditions in the 2006 CUP would not be enforced. Plaintiff did not challenge the zoning scheme or the conditions in the 2006 CUP when the County initially approved the entire project back in 2006, and the unsatisfied condition of the 2006 CUP at the heart of this case—that plaintiff had two years to obtain the necessary permits or to seek an

extension of the 2006 CUP—were not oppressive. At bottom, plaintiff indisputably failed to satisfy this straight-forward condition through no fault of the County, and there is no evidence suggesting that the County’s actions in enforcing this condition is arbitrary, pretextual, or otherwise unfairly targeted at plaintiff’s religious use. Any future claim based on the County’s recently amended zoning scheme that allows “places of worship” as a primary rather than a conditional use is not ripe until plaintiff engages in that process by filing a new application. The County’s motion is granted as to all of plaintiff’s claims, and plaintiff’s motion is denied. // // I. Background The factual history that follows is necessarily detailed and complex to describe the background that led to the current dispute and to resolve the parties’ currently pending motions. Plaintiff bought a property in West Linn, Oregon, in 2005 with the goal of building a new church for its growing congregation.1 The property was zoned RRFF-5, and under the Clackamas

County’s Zoning and Development Ordinance (“ZDO”) in place at the time, a church located in RRFF-5 district needed a conditional use permit before building and operating.2 In 2006, plaintiff began the process of seeking a conditional use permit to allow it to construct a church on the property.3 Plaintiff emailed a County staffer, Clay Glasgow, with a question about seeking a conditional use permit while “phasing” the project: Hi Clay . . . We are helping put together the CUP application for the Athey Creek Community Fellowship, which I think you have discussed in one or more meetings. I have a question for you on phasing. The Church would prefer to build out the entire project in a single phase, and this is how we have based our planning so far. However, there is a possibility that for financial reasons they may need to phase some of the site work (IE, parking), and perhaps have the multipurpose building and some of the interior work in the main building constructed as need and funding dictate. If we go in as a single phase, in both the CUP and Design Review processes, is there any reason why staging the permits and construction would be a problem later?4 Glasgow replied: Depending on the level of detail you have for the final build-out portion, I would suggest getting the whole thing approved from the get go. Phasing would be fine. Remember though, in order to get

1 Compl. ¶ 27, ECF 1. The complaint is verified, and some facts are pulled from it. See Compl. 21, ECF 1; Schroeder v. McDonald, 55 F.3d 454, 460 (9th Cir. 1995). 2 Compl. ¶¶ 8–9, ECF 1. 3 Id. ¶ 10. 4 Munns Decl., Ex. B at 1, ECF 48-2 (missing space edited). approval for all phases you will need complete detail on all of those phases. Worst case scenario with such a submittal is that the CU would be approved for the total development, but each phase would need to come in for specific Design Review. The more detail you have on the end phases the better, and we may just be able to approve, completely, the CU and DR in one shot.5 On May 6, 2006, plaintiff applied for a conditional use permit to build a church totaling 123,400 square feet on the site that included a 105,00 square-foot church building, a 16,000 square-foot multi-use building, a 2,400 square-foot maintenance building, and 900 parking spaces.6 The Clackamas County Land Board held a hearing on plaintiff’s application on July 13, 2006.7 After receiving testimony and making various findings (such as whether the property was a “suitable location” for a church, or whether the application was subject to the Rural Section of the Land Use Chapter of the Comprehensive Plan), the hearings officer approved plaintiff’s CUP “subject to [certain] conditions[.]”8 Condition 29 of the 2006 CUP is particularly important to this dispute, and it provides: This approval is valid for a period of two years from the date of final written decision. If the proposed use has not been established within that time, the approval shall expire unless a timely application for extension of the permit is filed with the County under ZOO Section 1203.03 and the application is approved. The conditional use approval is implemented when all necessary permits for the development have been secured and are maintained.9 After it received the 2006 CUP, plaintiff decided to build the project in phases “[d]ue to economic and financial circumstances during the mid-2000s.”10 The first phase of this project was a smaller portion of the original proposed church building, totaling about 44,000 square

5 Id. 6 Munns Decl., Ex. A at 1, ECF 48-1. 7 Id. at 1–2. 8 Id. (hereinafter the “2006 CUP”). 9 Munns Decl., Ex. A at 41, ECF 44-3. 10 Compl. ¶ 11, ECF 1. feet.11 In May of 2007, plaintiff obtained an engineering permit for on-site and off-site parking and transportation improvements (Permit No. SC005207); a building permit for “NEW BLDG” (Permit No. B0217507); a mechanical permit for “NEW BLDG PHASE 1” (Permit No. B0217707); and a plumbing permit for “PHASE 1 EXTERIOR” (P0120907).12 Plaintiff then

obtained an electrical permit for “NEW BLDG PHASE 1” (Permit No.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Midrash Sephardi, Inc. v. Town of Surfside
366 F.3d 1214 (Eleventh Circuit, 2004)
Abbott Laboratories v. Gardner
387 U.S. 136 (Supreme Court, 1967)
Guatay Christian Fellowship v. County of San Diego
670 F.3d 957 (Ninth Circuit, 2011)
SCHROEDER v. McDONALD
55 F.3d 454 (Ninth Circuit, 1995)
Petra Presbyterian Church v. Village of Northbrook
489 F.3d 846 (Seventh Circuit, 2007)
Fortress Bible Church v. Feiner
694 F.3d 208 (Second Circuit, 2012)
Employment Division v. Rogue Valley Youth for Christ
770 P.2d 588 (Oregon Supreme Court, 1989)
Coos County v. State
734 P.2d 1348 (Oregon Supreme Court, 1987)
Employment Division v. Western Graphics Corp.
710 P.2d 788 (Court of Appeals of Oregon, 1985)
Westchester Day School v. Village of Mamaroneck
504 F.3d 338 (Second Circuit, 2007)
Grace Church of North County v. City of San Diego
555 F. Supp. 2d 1126 (S.D. California, 2008)
Fortress Bible Church v. Feiner
734 F. Supp. 2d 409 (S.D. New York, 2010)
United States v. Maui County
298 F. Supp. 2d 1010 (D. Hawaii, 2003)

Cite This Page — Counsel Stack

Bluebook (online)
Athey Creek Christian Fellowship v. Clackamas County, Counsel Stack Legal Research, https://law.counselstack.com/opinion/athey-creek-christian-fellowship-v-clackamas-county-ord-2024.