Athey Creek Christian Fellowship v. Clackamas County

District Court, D. Oregon·Decided March 16, 2023·No. 3:22-cv-01717·Unknown

Opinion

IN THE UNITED STATES DISTRICT COURT FOR THE DISTRICT OF OREGON

ATHEY CREEK CHRISTIAN Case No. 3:22-cv-01717-YY FELLOWSHIP, ORDER DENYING PLAINTIFF’S Plaintiff, MOTION FOR PRELIMINARY INJUNCTION AND DECLARATORY v. JUDGMENT

CLACKAMAS COUNTY,

Defendant.

IMMERGUT, District Judge.

Athey Creek Christian Fellowship (“Plaintiff”), filed suit against Clackamas County (“Defendant”), alleging free exercise violations stemming from the application of Defendant’s Zoning and Development Ordinance (“ZDO”) to its church building project. ECF 1. Before this Court is Plaintiff’s Motion for Preliminary Injunction and Declaratory Judgment.1 ECF 14.

1 This Court does not separately address the Motion for Declaratory Judgment as that motion is based primarily on the Preliminary Injunction Motion, which is addressed in this order. PAGE 1 – ORDER DENYING PLAINTIFF’S MOTION FOR PRELIMINARY INJUNCTION Plaintiff asks this Court to enjoin Defendant from enforcing its ZDO in a manner that allegedly treats religious assemblies and institutions on less than equal terms with nonreligious assemblies and institutions. To this end, Plaintiff requests an order enjoining Defendant from requiring Plaintiff to obtain a new or modified conditional use permit for its building project. Plaintiff also moves for a declaration that two sections of the ZDO facially violate the equal terms provision of

the Religious Land Use and Institutionalized Persons Act (“RLUIPA”), 42 U.S.C. 2000cc(b)(1). This Court heard argument on Plaintiff’s motion on March 3, 2023. ECF 30. Based on the briefing, arguments by counsel, and current record of the case, this Court DENIES Plaintiff’s Motion for Preliminary Injunction and Declaratory Judgment. This Court finds that Plaintiff has not demonstrated that it is likely to suffer irreparable harm in the absence of preliminary relief. As a result, Plaintiff has not shown that this extraordinary remedy is warranted at this time. BACKGROUND Plaintiff is a non-denominational fellowship worshipping in the Christian tradition. ECF 1 at ¶ 28. In 2005, Plaintiff acquired a twenty-nine-acre parcel (“the Property”) located in

Clackamas County, Oregon. Id. at ¶¶ 2–3, 37. Plaintiff decided to build a church building, a maintenance center, and parking on the Property. Id. at ¶¶ 4–5. Under the Clackamas County ZDO, the Property is zoned “Rural Residential Farm Forest 5-Acre” (“RRFF-5”). Id. at ¶¶ 7, 38. A place of worship in the RRFF-5 district is a conditional use under the ZDO; as such, building and operating a place of worship requires a conditional use permit (“CUP”). Id. at ¶¶ 8, 39. Other assembly uses in the RRFF-5 district requiring a CUP include: bed and breakfasts, childcare facilities, adult daycare services, farmers markets, fraternal organization lodges, government uses, recreation uses, and schools. ECF 21 at 2. A category of use labeled

PAGE 2 – ORDER DENYING PLAINTIFF’S MOTION FOR PRELIMINARY INJUNCTION “Recreational Uses, Government-Owned”—which includes amphitheaters, ball fields, community buildings and grounds, fitness and recreational facilities, swimming pools, parks, and tables and seating—constitutes a primary use, permitted as of right in the zoning district without the need for a CUP. ECF 1 at ¶¶ 40–41; ECF 1-1 at 5, 10. In 2006, Plaintiff applied for a CUP to build on the Property. ECF 1 at ¶¶ 10, 43.

Anticipating financial difficulties, Plaintiff contacted county planning official Clay Glasgow by email during the process and inquired whether the Church would be able to build in phases without needing to obtain multiple CUPs. Id. at ¶ 13. Mr. Glasgow affirmed that Plaintiff would be able to obtain the CUP for the entire project and build in phases.2 Id. at ¶ 14. Plaintiff obtained a CUP for the project in 2006. Id. at ¶ 10. The CUP contained Condition 29,3 which provided: This approval is valid for a period of two years from the date of final written decision. If the proposed use has not been established within that time, the approval shall expire unless a timely application for extension of the permit is filed with the County under ZDO Section 1203.03 and the application is approved. The conditional use approval is implemented when all necessary permits for the development have been secure[d] and are maintained.

ECF 1-1, Ex. C, at 64; ECF 21 at 2.

2 In a declaration submitted in support of Defendant’s response to Plaintiff’s Motion for Preliminary Injunction, Mr. Glasgow agrees that he stated that “phasing would be fine” and that “[w]orst case scenario with such a submittal is that [Plaintiff] would be approved for the total development, but each phase would need to come in for specific Design Review.” ECF 24 at ¶ 14. However, Mr. Glasgow also maintains that the phasing would “still require the Church to comply with all of the conditions of the CUP including [C]ondition 29” and that “if the Church had secured and maintained all permits necessary for all of the proposed development permitted in the 2006 CUP[,] each phase would only need to be subject to design review.” Id. at ¶¶ 15–16. 3 Condition 29 was based on a Clackamas County land use provision that was repealed in 2011. ECF 21 at 3. The time limitation is now contained in ZDO 1203.05, which states that “approval of a conditional use is valid for four years from the date of the final decision.” Id.; ECF 22-8 at 2.

PAGE 3 – ORDER DENYING PLAINTIFF’S MOTION FOR PRELIMINARY INJUNCTION After the CUP approval, Plaintiff commenced construction on the first phase of its building plan. ECF 1 at ¶¶ 15, 51. Plaintiff obtained and maintained the development permits necessary to construct this phase of development. ECF 21 at 3. Plaintiff alleges that county officials confirmed for Plaintiff that its CUP was still active in 2013. ECF 1 at ¶¶ 56–58; see ECF 1-1, Ex. E, at 72, 74. In 2015, Plaintiff completed the first phase of building, which

included its current church building. ECF 1 at ¶ 54. Although it is unclear exactly when Plaintiff decided to initiate the second phase of building, correspondence suggests Plaintiff contacted Defendant regarding this phase in or around July of 2022. ECF 1-1, Ex. F, at 85. This second phase would expand the current church building from 43,933 square feet to approximately 123,400 square feet. ECF 1 at ¶¶ 16, 59, 61. When Plaintiff informed Defendant of its intention to start the second phase of building, Defendant asserted that Plaintiff had to obtain a new or modified CUP to do so. Id. at ¶¶ 17, 64, 68. Defendant maintains that prior approval under the 2006 CUP has expired and that Plaintiff has not applied for the permits necessary for further development since the initial CUP approval.

ECF 21 at 3; ECF 24 at ¶¶ 12, 13. Plaintiff has not applied for a new or modified CUP, citing the process’s length, expense, and uncertainty. See ECF 24 at ¶ 13; ECF 1 at ¶¶ 18–19. Plaintiff alleges in its complaint that, due to a growing congregation, it has been forced to conduct many duplicate worship services to accommodate all who wish to come, ECF 1 at ¶ 34, and that it “is unable to offer more services due to staff and logistical limitations as well as the desire to follow the biblical mandate of gathering as much of the congregation together as possible for worship and fellowship,” id. at ¶ 36.

PAGE 4 – ORDER DENYING PLAINTIFF’S MOTION FOR PRELIMINARY INJUNCTION LEGAL STANDARD “A preliminary injunction is an extraordinary remedy that may be awarded only if the plaintiff clearly shows entitlement to such relief.” Am. Beverage Ass’n v. City & Cnty. Of San Francisco, 916 F.3d 749, 754 (9th Cir. 2019) (quoting Winter v. Nat. Res. Def.

Free access — add to your briefcase to read the full text and ask questions with AI

Athey Creek Christian Fellowship v. Clackamas County, (D. Or. 2023).

Athey Creek Christian Fellowship v. Clackamas County (Athey Creek Christian Fellowship v. Clackamas County) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

City of Los Angeles v. Lyons
461 U.S. 95 (Supreme Court, 1983)
Mazurek v. Armstrong
520 U.S. 968 (Supreme Court, 1997)
Arizona Dream Act Coalition v. Janice Brewer
757 F.3d 1053 (Ninth Circuit, 2014)