Associated Construction Co. v. Camp, Dresser & McKee, Inc.

646 F. Supp. 1574, 1986 U.S. Dist. LEXIS 17722
CourtDistrict Court, D. Connecticut
DecidedNovember 14, 1986
DocketCiv. N-83-302 (PCD)
StatusPublished
Cited by7 cases

This text of 646 F. Supp. 1574 (Associated Construction Co. v. Camp, Dresser & McKee, Inc.) is published on Counsel Stack Legal Research, covering District Court, D. Connecticut primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Associated Construction Co. v. Camp, Dresser & McKee, Inc., 646 F. Supp. 1574, 1986 U.S. Dist. LEXIS 17722 (D. Conn. 1986).

Opinion

RULING ON MOTION FOR SUMMARY JUDGMENT

DORSEY, District Judge.

Plaintiffs seek compensatory and punitive damages based on defendant’s claimed failure to act with reasonable care or in accordance with its contract with the City of New Haven (“City”) and, based on the same alleged deficiencies, for willful, intentional conduct. Plaintiffs, Associated Construction Company and DeMatteo Construction Company, formed a joint venture (the “JV”) to be the general contractor for a New Haven Sewer Treatment Facility (the “Project”). Three subcontractors, Instrumentation Contractors, Inc. (“ICI”), Holzner Electric Company (“Holzner”) and Cosgrove Construction Company (“Cos-grove”), are the remaining plaintiffs. Defendant, Camp, Dresser & McICee, Inc. (“CDM”), an engineering company, produced the plans and specifications for the Project and supervised the construction for the City. Defendant’s conduct claimed by plaintiffs to be wrongful, arises out of the contract — various preparatory surveying work, planning, design, drafting, information, inspection, testing, drawing review, and approval, coordination, progress certification, supervision, reporting obligations and procéssing claims for extra work. Plaintiffs claim economic losses suffered in their performance of the contract, allegedly caused by defendant’s wrongful conduct.

Though plaintiffs ahve not defined the issues with ideal meticulousness, the following seems to be undisputed:

(1) Cosgrove’s claims here (as compared to those made against the City), having been partially settled (Exhibit 54) or not previously totally claimed, are based on the same facts as the claims presented to the City. Plaintiffs’ Statement of Facts at 119.

(2) Holzner’s claims here (as compared to those made against the City which were paid in whole or in part as arbitration awards or a stipulation and which were claimed for only part of the entire period) were not previously specifically claimed as items of damage, though they are based on the same facts as the items which were claimed or were claimed without an award being made. Id. at ¶ 28.

(3) ICI’s claims here (as compared to those made against the City which were paid in whole or in part as arbitration awards or a stipulation — although ICI was not a party to the arbitration, its claims were presented by the JV as per the contract with the City) were not previously specifically claimed as items of damage, though they were based on the same facts *1576 as the items which were claimed, or were claimed without an award being made. Id. at ¶ 46.

(4) The JV’s claims here (as compared to those made against the City which were resolved by stipulation during arbitration and an award which, after confirmation by the Connecticut Superior Court, resulted in payment received for all or part of the claims made) are for additional items of expense based on the contract performance after the original completion date of September 16, 1979, to December 31, 1982.

A meticulous and exhaustive review of the claims originally made, their processing and resolution, has been accomplished by analyzing the record. The examples discussed below confirm the review performed and illustrate the analysis which lead to the conclusions herein. It would serve no useful purpose to discuss and compare each of the claims made against the City, including the factual basis therefor, and those made here. The claims before the court can be categorized as noted for each plaintiff in Paragraphs (1) through (4) above. In short, plaintiffs claim that defendant’s conduct in preparing and publishing the documents on which the Project was bid, the contract awarded and the Project administered, caused and necessitated much extra work and substantial delay in completing the job, obliging plaintiffs to be engaged in the performance of the contract until December 31, 1982, long beyond their estimated date of completion. Based thereon, they made claims against the City for additional payments, which they have since received, been awarded or otherwise agreed to. Now they seek additional amounts for:

(a) claims previously made but either not fully sustained or not sustained at all;
(b) interest on amounts paid as claimed;
(c) losses not previously specifically claimed but clearly based on the same facts as the previous claims; and
(d) costs of the same nature as previously claimed but for periods other than those for which claims were made.

However, the claims are now made against the engineer rather than the City. As against the City, the claims for extra expenses were based on allegedly uncontemplated facts arising in the performance of the contract. They were resolved by an arbitration procedure provided for in the contract. Now, against the engineers, consequent losses are claimed on the basis that such extra expense resulted from the engineers’ wrongful conduct in the bid, award and performance of the contract. Defendant has moved for summary judgment on the basis that the resolution of plaintiffs’ claims against the City bars the remaking of those claims here.

Discussion

On February 17, 1976, the JV contracted to construct the Project at a price of $32,-694,800. Exhibit 5. Cosgrove was the site-work subcontractor. Exhibit 22. Holzner was both an electrical subcontractor to the JV, Exhibits 1, 2 and 3, and a sub-subcontractor to ICI, Exhibit 7, the instrumentation and data logger subcontractor to the JV. Exhibit 6. The work was to be done by April 16, 1979. As of March 25, 1980, the work was 99% complete. The instrumentation and data logger systems largely delayed the completion until December 31, 1982 — the extended completion date per change orders. Extra work prompted claims for additional compensation, which, after arbitration as provided by the contract, resulted in payments to plaintiffs being increased to $35,612,542. Exhibits 25, 40, 46, 76 and 77.

Four arbitrations occurred:

1. Cosgrove’s claims were resolved by agreement with the City, which included a release by the JV and Cosgrove of all claims arising out of claim numbers 130, 348 and 32 and change order proposals 13, 20, 30 and 31, as presented for arbitration on December 15, 1977. Exhibit 54.

2. Holzner’s claim for extra work through May 31, 1980, Exhibit 21, went to arbitration, resulting in an award against the City, Exhibits 18 and 19, which was affirmed by the Connecticut Superior Court. Exhibits A and 77.

*1577 3. The JV, for itself and the subcontractors, initiated arbitration, Exhibit 20, which ended with a stipulated award of $3,395,-000, confirmed in the Connecticut Superior Court, Exhibit B, and Change Order # 90, Exhibit 76.

4. The JV asserted claims arising after June 26, 1980, when a general release, Exhibit 54, had been signed. These covered the period from June 26, 1980, to December 7, 1981, and were settled by payment of $226,226.69 to the JV for four extra work claims and $147,681 for extended performance claims.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Strazza Building & Construction, Inc. v. Harris
Supreme Court of Connecticut, 2023
Girolametti v. Michael Horton Assocs., Inc.
208 A.3d 1223 (Supreme Court of Connecticut, 2019)
TLT Construction Corp. v. A. Anthony Tappe & Associates, Inc.
716 N.E.2d 1044 (Massachusetts Appeals Court, 1999)
Stulberg v. Intermedics Orthopedics, Inc.
997 F. Supp. 1060 (N.D. Illinois, 1998)
Fromson v. United States
32 Fed. Cl. 1 (Federal Claims, 1994)
Mulholland Construction Co. v. Lee Pare & Associates, Inc.
576 A.2d 1236 (Supreme Court of Rhode Island, 1990)

Cite This Page — Counsel Stack

Bluebook (online)
646 F. Supp. 1574, 1986 U.S. Dist. LEXIS 17722, Counsel Stack Legal Research, https://law.counselstack.com/opinion/associated-construction-co-v-camp-dresser-mckee-inc-ctd-1986.