Mulholland Construction Co. v. Lee Pare & Associates, Inc.

576 A.2d 1236, 1990 R.I. LEXIS 135, 1990 WL 94900
CourtSupreme Court of Rhode Island
DecidedJuly 12, 1990
Docket89-399-Appeal
StatusPublished
Cited by19 cases

This text of 576 A.2d 1236 (Mulholland Construction Co. v. Lee Pare & Associates, Inc.) is published on Counsel Stack Legal Research, covering Supreme Court of Rhode Island primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Mulholland Construction Co. v. Lee Pare & Associates, Inc., 576 A.2d 1236, 1990 R.I. LEXIS 135, 1990 WL 94900 (R.I. 1990).

Opinion

OPINION

WEISBERGER, Justice.

This case comes before us on an appeal by the plaintiff, Mulholland Construction Co. (Mulholland), from a summary judgment entered in the Superior Court in favor of the defendant, Lee Pare & Associates, Inc. (Pare). We affirm. The facts of the case insofar as pertinent to this appeal are as follows.

Mulholland entered into a contract with the town of Narragansett for construction of the Scarborough Wastewater Treatment Facility Ocean Outfall on March 12, 1984. This construction agreement required Mul-holland to dig a trench a minimum of eight feet below the ocean floor for the placement of a 2,200-foot outfall pipe for a sewage-treatment plant. The design and engineering studies for the project were prepared by Pare, a firm specializing in engineering design. One of the activities undertaken by Pare was a preliminary study of the seabed wherein the trench was to be prepared. Apparently Pare, instead of making its own test borings, relied upon a prior survey for another contract that had been accomplished through test bor- *1237 ings in 1962 by American Drilling Co. In any event, the information provided during the bidding process indicated to Mulholland that the seabed consisted of sand, silt, and fine gravel. When Mulholland began the excavation, it soon discovered that the seabed consisted of cobbles and boulders, which made excavation much more difficult and expensive.

Consequently, Mulholland sought modifications in the contract for additional compensation based not only upon the nature of the seabed but also upon the depth of water encountered over the area of excavation. The request for equitable adjustment was rejected. Arbitrators later found that the rejection of the requested equitable adjustment was due to the hard-line position taken by the Department of Environmental Management (DEM) and the Federal authorities who were overseeing and sponsoring the project. The arbitrators indicated that the town of Narragansett and Pare did not object to equitable adjustment. Nevertheless, since agreement could not be reached concerning the requested adjustment, the parties proceeded to arbitration. The town appointed one arbitrator, Mulhol-land appointed another arbitrator, and the two arbitrators appointed a third arbitrator.

The parties gave the arbitrators a series of issues to determine, but the arbitrators proceeded to accept evidence and litigate on the merits the entire range of disputes between the parties. A majority of the arbitrators issued findings that were favorable to Mulholland in June of 1985. Thereafter, the case was submitted to the Superi- or Court on Mulholland’s request for further arbitration. The Superior Court remanded the matter to the arbitrators on August 2, 1985, for further findings, inter alia, on all questions regarding damages and necessary contract interpretations.

In conformity to this order the arbitrators again assembled and issued further findings that awarded $509,822.98 to Mul-holland for total damages for additional costs to the date of the findings (December 1985) and $222,325 for additional estimated costs necessary to complete the contract. It is most significant to note that the arbitrators awarded compensation for trench excavation, additional job overhead, markup on additional costs, statutory interest at the rate of 12 percent, but rejected certain other claims, including the cost of arbitration and punitive damages. One arbitrator would have awarded $50,000 for the cost of arbitration; two arbitrators would have awarded nothing. One arbitrator would have awarded punitive damages but agreed with the other two arbitrators that there was insufficient evidence to establish such an award.

In support of and in opposition to this appeal, the parties raise three issues that will be considered in the order in which they are set forth in the parties’ briefs.

I

The Applicability of Res Judicata or Collateral Estoppel

There is no question that summary judgment is a drastic remedy and should be awarded only in the event that a plaintiff or a defendant is entitled to judgment as a matter of law and that there is no question of material fact outstanding between the parties. Ludwig v. Kowal, 419 A.2d 297, 301 (R.I.1980). The question of issue preclusion raised under the doctrines of res judicata or collateral estoppel generally presents to the court an issue of law. Corrado v. Providence Redevelopment Agency, 113 R.I. 274, 320 A.2d 331 (1974); Providence Teachers Union v. McGovern, 113 R.I. 169, 319 A.2d 358 (1974); Perez v. Pawtucket Redevelopment Agency, 111 R.I. 327, 302 A.2d 785 (1973).

In the case at bar the arbitration award was ultimately confirmed after the additional findings by a judgment entered in the Superior Court on April 30, 1986. We have held that an arbitration award that is confirmed by the Superior Court is equivalent to a final judgment in an action at law. Paola v. Commercial Union Assurance Companies, 461 A.2d 935, 937 (R.I.1983). Consequently the question before this court is whether the judgment entered pursuant to the arbitration award *1238 precludes further litigation between Mullholland and Pare. We pointed out in the case of Providence Teachers Union v. McGovern, supra, that the doctrine of res judicata precludes relitigation between the parties to a prior action or their privies of matters that either were litigated or might have been litigated in a prior action. We further pointed out that, under the general doctrine of res judicata, a subsidiary doctrine known as collateral estoppel would preclude a party from relitigating issues with a party or those in privity with him that had actually been litigated in a prior case.

It has been held in Associated Construction Co. v. Camp, Dresser & McKee, Inc., 646 F.Supp. 1574 (D.Conn.1986), that a design engineer was in privity with the city of New Haven, which had been the owner in a contract for construction between the city and the construction company based upon negligent preparatory surveying work, design, and supervision carried out by the engineers. The court in that case held that after the construction company had litigated the question of damages with the city in an arbitration proceeding, it would be precluded from proceeding against the engineer for damages that had already been awarded in the arbitration proceeding arising out of its conduct in respect to the performance of the contract.

We are not entirely persuaded that an engineer and a contracting owner will always be in perfect privity in respect to the type of damages that may be awarded in respect to each party. The plaintiff argues, for example, that its action against Pare is in tort for negligence, as well as for breach of contract.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Masse v. City of Providence
D. Rhode Island, 2020
Monteiro v. Town of Middletown
Superior Court of Rhode Island, 2011
Greenwich Northeast v. E.W. Burman
Superior Court of Rhode Island, 2011
Ballard v. State
983 A.2d 264 (Supreme Court of Rhode Island, 2009)
Foster-Glocester Regional School Committee v. Board of Review
854 A.2d 1008 (Supreme Court of Rhode Island, 2004)
Casco Indemnity Co. v. O'Connor
755 A.2d 779 (Supreme Court of Rhode Island, 2000)
City of Providence v. Employee Retirement Board
749 A.2d 1088 (Supreme Court of Rhode Island, 2000)
Fleet Construction Co. v. Aetna Life & Casualty Co.
746 A.2d 1247 (Supreme Court of Rhode Island, 2000)
Ferguson v. Marshall Contractors, Inc.
745 A.2d 147 (Supreme Court of Rhode Island, 2000)
Commercial Union Insurance v. Pelchat
727 A.2d 676 (Supreme Court of Rhode Island, 1999)
Eigabri v. Lekas
681 A.2d 271 (Supreme Court of Rhode Island, 1996)
DEPARTMENT OF CORRECTION OF STATE OF RI v. Tucker
657 A.2d 546 (Supreme Court of Rhode Island, 1995)
E.W. Audet & Sons, Inc. v. Fireman's Fund Insurace Co. of Newark
635 A.2d 1181 (Supreme Court of Rhode Island, 1994)
Daam v. Daam, 91-5171 (1992)
Superior Court of Rhode Island, 1992

Cite This Page — Counsel Stack

Bluebook (online)
576 A.2d 1236, 1990 R.I. LEXIS 135, 1990 WL 94900, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mulholland-construction-co-v-lee-pare-associates-inc-ri-1990.