Aspic Engineering & Construction Co. v. ECC Centcom Constructors, LLC

268 F. Supp. 3d 1053
CourtDistrict Court, N.D. California
DecidedJuly 18, 2017
DocketCase No. 17-cv-00224-YGR
StatusPublished
Cited by2 cases

This text of 268 F. Supp. 3d 1053 (Aspic Engineering & Construction Co. v. ECC Centcom Constructors, LLC) is published on Counsel Stack Legal Research, covering District Court, N.D. California primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Aspic Engineering & Construction Co. v. ECC Centcom Constructors, LLC, 268 F. Supp. 3d 1053 (N.D. Cal. 2017).

Opinion

Order Granting Defendants’ Motion to Vacate Final Arbitration Award Pursuant to 9 U.S.C. § 10; Denying Plaintiff’s Motion to Confirm and Correct the Arbitration Award

Hon. Yvonne Gonzalez Rogers, United States District Court Judge

Defendants ECC International, LLC and ECC CENTCOM Constructors, LLC (collectively “ECC”) bring this motion to vacate a final arbitration award (the “Arbitration Award”) entered against them and in favor of plaintiff Aspic Engineering and Construction Company (“Aspic”) on the ground that the arbitrator exceeded his authority. (Dkt. No. 19.) Plaintiff Aspic opposes defendants’ motion and moves to confirm and correct the award to include Aspic’s attorney’s fees. (Dkt, No. 17 at 20; Dkt. No. 26.) While considerable deference to an arbitrator exists under Ninth Circuit law, the Court finds here rare circumstances warranting vacatur.

I. Relevant Background

ECC is an employee-owned engineering and construction firm located in Bur-lingame, California. ECC performs work on various commercial and government construction projects, including as a prime contractor to the U.S. Army Corp of Engineers (“USACE”) supporting two reconstruction projects for police training facilities in Sheberghan and Badghis, Afghanistan (the “Projects”). (Dkt. No. 20-2, ECC Prehearing Brief at 3.) The prime contracts between USACE and ECC incorporated Federal Acquisition Regulations (“FAR”) Sections 49.206 and 52.249-2, which allowed USACE to terminate the Projects “for convenience” and provided for ECC’s recovery of costs and profits in the event of such a termination.1

[1056]*1056A. • The Subcontracts

ECC awarded subcontracts for the Projects (the “Subcontracts’') to plaintiff Aspic, an Afghan 'engineering and* contracting firm.. (Dkt. No 20-10, Sheber-ghan Subcontract; Dkt. No. 20-11, Badghis Subcontract.) The Subcontracts are -lengthy and provide detailed descriptions of termination rights, recovery of costs, and dispute resolution procedures. (Id.) For example, the Badghis Subcontract is 90 pages and incorporates, more than 100 FARs. The Sheberghan Subcontract is even larger, totaling 450 pages and incorporating more than 250 FARs. Each Subcontract was signed by Aspic Vice President and" co-owner Omar Ir-shad, who apparently had experience in contracting with the U.S. government and a ‘familiarity - with U.S. Government requirements including FAR clauses. (She-berghan Subcontract ' ECC-000132; Badghis Subcontract at ECC-000002; Dkt. No. 14, Certification of Interested Entitles or Persons of Petitioner/Plaintiff Aspic at 1; Dkt. No. 20-4 at 8.)

' After ECC and Aspic had partially performed under the prime and Subcontracts, respectively, USACE issued a notice of termination for convenience Which ended the Projects in their entirety: (Dkt. No. 20-2, ECC Prehearing Brief at 4, 6.) On September 26, 2015, Aspic brought an arbitration claim against EEC seeking roughly $2,3 million for certain'-costs, lost profits, and attorneys’ fees. (Dkt. No. 20^4, ECC Posthearing Brief' at 23; Dkt, No. 20-3, Aspic Posthearing Brief at 6; Dkt. No. 20-5, Aspic Reply Brief at 20.)

B. The Arbitration Award

An arbitration hearing was held from August 1-3, 2016 in Burlingame, California. On September 30, 2016, arbitrator Eugene M. Bass (the “Arbitrator”) issued a partial final award in favor of Aspic.in the amount of $1,072,520.90. (Dkt. No. 20-6, Partial Final Award.) The. Arbitrator stated, in relevant part:

.... The parties entered into two lengthy subcontract agreements for the two projects which were prepared by ECC and presented to ASPIC. Each subcontract included very detailed provisions relating to Federal regulations governing the work as well as pass through and 'Pay when/if Paid’ clauses. The subcontracts were somewhat onerous as to ASPIC and were clearly drafted to give every advantage to ECC. In light of the fact that the ASFIC was a local Afghanistan subcontractor that had some experience with government contracting but not nearly as extensive as that of ECC, and in view of the fact that the normal business practices and customs of subcontractors in Afghanistan were more ‘primitive’ than -those of U.S. subcontractors experienced with U.S. Government work, it was not reasonable .to'expect that Afghanistan subcontractors-would be able to conform, to the strict and detailed requirements of general contractors on U.S. Federal projects. Notwithstanding that expectation, •ECC prepared its subcontract agreements to require the same level of precision and adherence to Federal procedures from ASPIC as ECC had toWard the USACE through the pass through provisions of the agreements.
It was not reasonable that when the parties entered into the subcontract agreements, they both had the same expectations as to the performance of the agreements. ECC could not expect that ASPIC would be capable of modifying [1057]*1057their local business practices to completely and strictly conform to the US governmental contracting practices tjiat were normal to ECC. There was not a true meeting of the minds token the subeontraet agreements were entered, Hence, ÁSPJC was not held to the strict provisions of the subcontract agreements that ECC had to the USAGE. This arbitration demonstrated that ASPIC conducted its business practices in a manner normal to Afghanistan which was clearly not the same as a US subcontractor working on a Federal project in the U.S.

(Emphasis supplied.) The award was made final on November 14, 2016. (Dkt. No. 20-90

II. Legal Framework

Resolution of this matter implicates the New York Convention and the Federal Arbitration Act (“FAA”). First, the Convention on the Recognition and Enforcement of Foreign Arbitral Awards (the “New York Convention”) requires U.S. courts to recognize and enforce arbitration awards made in foreign states that have assented to the terms of the New York Convention (“contracting states”). The New York Convention applies to arbitra-tions where one of the parties is a U.S. citizen and the other is a citizen of a foreign contracting state. 9 U.S.C. § 202; LaPine v. Kyocera Corp., 2008 WL 2168914 at *3-4 (N.D. Cal. 2008). Under the New York Convention, an arbitral award in one contracting state is enforceable in any other contracting state unless enforcement would violate the “domestic law” of the country in which enforcement is sought. New York Convention Art. V.1(e), June 10,1968, 21 U.S.T. 2517.

Next, under the FAA, “[njeither erroneous legal conclusions nor unsubstantiated factual findings justify federal court review of an. arbitral, award.” Bosack v. Soward, 586 F.3d 1096, 1102 (9th Cir. 2009). Review of an arbitration award is “both limited and highly deferential.” Comedy Club, Inc. v. Improv W. Assocs., 553 F.3d 1277, 1288 (9th Cir. 2009). However, the Ninth Circuit has held that “[although an arbitrator has great freedom in determining an award, he may not dispense his own brand of industrial justice.” Garvey v. Roberts,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
268 F. Supp. 3d 1053, Counsel Stack Legal Research, https://law.counselstack.com/opinion/aspic-engineering-construction-co-v-ecc-centcom-constructors-llc-cand-2017.