Askew v. Joachim Memorial Home

234 N.W.2d 226, 1975 N.D. LEXIS 125
CourtNorth Dakota Supreme Court
DecidedOctober 6, 1975
DocketCiv. 9113
StatusPublished
Cited by43 cases

This text of 234 N.W.2d 226 (Askew v. Joachim Memorial Home) is published on Counsel Stack Legal Research, covering North Dakota Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Askew v. Joachim Memorial Home, 234 N.W.2d 226, 1975 N.D. LEXIS 125 (N.D. 1975).

Opinion

PAULSON, Judge.

This is an appeal from an order and judgment of the Mercer County District Court dismissing the counterclaim of the defendant and appellant, Joachim Memorial Home, and granting the motion for a directed verdict of the plaintiff and appellee, Jack G. Askew, doing business as Leonhard & Askew, Architects. Judgment was entered against the defendant for the sum of $17,-850.27, which sum includes the plaintiff’s claim, plus interest and costs.

This suit results from a claim by Askew that the Joachim Memorial Home is liable to him for $15,915.20, plus interest and costs, as the final payment of an architect’s fee of $27,915.20. The fee was calculated pursuant to the terms of a written agreement signed on June 23, 1968, by Edward Schulz and H. M. Leonhard, under which the architectural firm of Leonhard & Askew, Architects, was to provide certain architectural services to the Joachim Memorial Home in connection with a planned building project.

Schulz is purported to have acted as the agent for the Rev. Joachim Memorial Association [hereinafter “Association”], which operates the Joachim Memorial Home in Beulah as a retirement home for elderly persons. Schulz, in 1968, was president of the Association’s board of directors [hereinafter “Board”].

Leonhard, in signing the agreement with Schulz on June 23, 1968, is purported to have acted as an agent for Askew, who was at that time operating his professional firm under the assumed name of Leonhard & Askew, Architects. Leonhard and Askew had been partners in the firm of Leonhard & Askew, Architects, from 1955 until January 1, 1968, when the partnership was dissolved. After January 1, 1968, Leonhard continued until his death on January 23, 1974, to be associated with the firm, Leon-hard & Askew, Architects, as an employee of Askew.

Beginning in June 1968, Askew, through Leonhard and other employees, began providing architectural services to the Association. On July 18, 1968, the Board discussed the preliminary plans for the building and was told that an architect had been hired. It was during this initial planning phase that the plaintiff first estimated that the cost of construction would be approximately $394,000.

The Association’s minutes show that planning for the construction of a new *231 building continued during the next two years. The minutes of the January 21, 1969, annual meeting of the Association state, in pertinent part:

“Much discussion was had as to the building of a new Joachim Memorial Home. It was decided at this meeting by everyone present that the Board of the Joa-chim Memorial should do everything in there [sic] power to build a new Home.”

One year later, the minutes of the Association again reflect the continued involvement of the Association in planning for the construction of a new building. The minutes of the January 20, 1970, annual meeting of the Association state, in pertinent part:

“President Schulz reported that the building project is still under way at this time.”

The next action reflected in the Board’s minutes is a report at the March 2, 1970, Board meeting. At such meeting the Board was told that the architect was drawing up a new set of plans based on earlier discussions to reflect proposed changes.

By September 1970, more complete plans for the structure had been completed and Askew had met with representatives of the Board, as well as with other interested persons in Beulah. At the September 27,1970, meeting of the Board, details of the building were explained and Askew gave as a verbal cost estimate the figure of $440,000.

In April 1971, Board President Edward Schulz, Board Secretary Helmuth Hilz, and H. M. Leonhard of the architectural firm, met with officials of the Bank of North Dakota to discuss financing the project. The Bank of North Dakota was not willing to commit itself to the project at that time, but suggested that the Board obtain firm bids on the proposal and return to discuss the project after bids had been received.

Bids for the project were let on July 15, 1971. The low construction bid was $471,-550.

After receiving bids, the Association continued its efforts to secure financing for the project but was unable to do so. As late as April 20, 1972, the minutes of the Board show that the Association was continuing its search for financial backing to construct the building and that the contractors had agreed to hold open their bids for an unspecified period of time. Finally, however, the Board was forced to conclude, during the summer of 1972, that financing would not be available. The project was then abandoned.

At a meeting of the Board held on October 11, 1971, the Board had authorized payment to Askew of the sum of $12,000, which was a partial payment of his architectural fee. Such sum had been paid after its approval by the Board; at such meeting the Board was advised that Schulz had a copy of the agreement with Askew, but the Board voted to pay such fee without knowing of all of its terms and conditions. However, once the Board discovered that Askew’s total fee was $27,915.20, they refused to pay the balance of such fee. The amount of the fee was calculated according to the terms of the agreement signed on June 23, 1968, by Edward Schulz and H. M. Leon-hard. That agreement provided for a fee of 7.4 percent of the low bid if the building was actually constructed. If not built, the fee would be a percentage of the total fee, based upon the following schedule:

Schematic Design Phase. 15%
Design Development Phase .... 35%
Construction Documents Phase 75% Bidding or Negotiation Phase . 80%
Construction Phase. 100%

This project proceeded through the “Bidding or Negotiation Phase” before the project was terminated by the Association.

After a series of meetings between Askew and the Board had failed to resolve the dispute, Askew brought this action on October 6, 1972, to recover that portion of his fee which remained unpaid. The Association answered and counterclaimed for the $12,000 it had already paid to Askew. The *232 Association claimed that the $12,000 had been paid to Askew by the Board in the mistaken belief that a valid contract existed. The Association also contended that if a valid contract did exist between Askew and the Association, the Association had received no consideration for its payment, that Askew had obtained payment by exerting undue influence on the Board, and that Askew had breached the contract by failing to “arrange financing” for the proposed construction project.

On January 17,1975, Askew moved at the close of all the evidence for a directed verdict of dismissal of the Association’s counterclaim. The trial court granted such motion. Askew also moved for a directed verdict on the complaint, but the trial court denied the motion and recessed court for the day, expecting to reconvene the next morning for submission of the case to the jury. However, later that same evening, the trial judge notified Askew’s counsel that he had decided to grant Askew’s motion for a directed verdict on the complaint.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Ebel, et al. v. Engelhart, et al.
2024 ND 168 (North Dakota Supreme Court, 2024)
Grengs v. Grengs
2023 ND 239 (North Dakota Supreme Court, 2023)
The Next Step v. Redmon
2016 ND 85 (North Dakota Supreme Court, 2016)
Johnson v. Mark
2013 ND 128 (North Dakota Supreme Court, 2013)
Westby v. Schmidt
2010 ND 44 (North Dakota Supreme Court, 2010)
Makedonsky v. North Dakota Department of Human Services
2008 ND 49 (North Dakota Supreme Court, 2008)
State v. Darby
2008 ND 43 (North Dakota Supreme Court, 2008)
Freed v. Unruh
1998 ND 34 (North Dakota Supreme Court, 1998)
Korea Deep Sea Fisheries Ass'n v. Hong
31 Am. Samoa 2d 80 (High Court of American Samoa, 1996)
Hebertson v. Willowcreek Plaza
895 P.2d 839 (Court of Appeals of Utah, 1995)
First National Bank & Trust Co. of Williston v. Scherr
467 N.W.2d 427 (North Dakota Supreme Court, 1991)
Red River Commodities, Inc. v. Eidsness
459 N.W.2d 811 (North Dakota Supreme Court, 1990)
Deichert v. Fitch
424 N.W.2d 903 (North Dakota Supreme Court, 1988)
City of Grand Forks v. Mik-Lan Recreation Ass'n, Inc.
421 N.W.2d 806 (North Dakota Supreme Court, 1988)
Weisser v. Grand Forks Federal Savings & Loan Ass'n
406 N.W.2d 696 (North Dakota Supreme Court, 1987)
Jablonsky v. Klemm
377 N.W.2d 560 (North Dakota Supreme Court, 1985)
Johnson v. Production Credit Ass'n of Fargo
345 N.W.2d 371 (North Dakota Supreme Court, 1984)
Meier v. Novak
338 N.W.2d 631 (North Dakota Supreme Court, 1983)

Cite This Page — Counsel Stack

Bluebook (online)
234 N.W.2d 226, 1975 N.D. LEXIS 125, Counsel Stack Legal Research, https://law.counselstack.com/opinion/askew-v-joachim-memorial-home-nd-1975.