Ashworth v. Charlesworth

231 P.2d 724, 119 Utah 650, 1951 Utah LEXIS 163
CourtUtah Supreme Court
DecidedMay 29, 1951
Docket7499
StatusPublished
Cited by12 cases

This text of 231 P.2d 724 (Ashworth v. Charlesworth) is published on Counsel Stack Legal Research, covering Utah Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ashworth v. Charlesworth, 231 P.2d 724, 119 Utah 650, 1951 Utah LEXIS 163 (Utah 1951).

Opinions

LATIMER, Justice.

This is an appeal by the defendants from a judgment of the lower court awarding damages, attorney’s fees and costs to plaintiffs for defendants’ breach of contract for the painting of a bridge. The parties are referred to as they appeared in the court below.

Plaintiffs are partners, engaged in erecting and constructing steel structures- doing business under the assumed name of Utah Crane and Erection Company. Their principal place of business is located in Salt Lake City, Utah. Defendants are also partners, doing business as painting contractors, with their places of business in Ogden and Salt Lake City, Utah.

In the spring of 1947, plaintiffs were awarded a subcontract by a general contractor, under the terms of which plaintiffs were to unload, deliver to site, erect, and paint all the structural steel for the Green River bridge. This was a Utah State Road Commission project and there were detailed plans and specifications for its erection and completion.

[653]*653In the fall of 1947, plaintiffs invited at least three painting firms, one of which was the defendant partnership, to submit bids on the painting of the bridge. The invitation to defendants was extended in September, 1947, by one Lyle Larsen, general superintendent of plaintiff partnership, who was supervising the construction of a hangar in Ogden for defendant Jack G. Charlesworth. At that time, Larsen told Charlesworth that plaintiffs had a contract to construct and paint the bridge at Green River and asked if defendants would be interested in submitting a bid. A few weeks later Charlesworth was in plaintiff’s office in Salt Lake City and Larsen had the blueprints of the bridge on his desk. He told Charlesworth that they were the plans for the bridge which the parties had previously discussed. According to Larsen’s testimony Jack Charlesworth then examined the plans, while Charles-worth testified that he merely glanced at them. Toward the latter part of September, 1947, Larsen called Jack Charlesworth in Ogden and asked what his price would be for the painting of the bridge. Charlesworth said he would call Larsen back and give him a price. Charlesworth then discussed the matter with his father, called Larsen, and, over the telephone, gave a price of $500 for the work. On October 3, 1947, Jack Charlesworth caused a letter to be sent to plaintiffs in which he submitted a bid for the painting of the bridge with two coats of aluminum paint, for the sum total of $500, adding that if the paint was to be furnished by the painting contractor the total sum would be $600. Plaintiffs received two other bids on the job, one in the amount of $2,000 and the other in the sum of $3,277. However, the one for $2,000 was not received by plaintiffs until after the contract with defendants had been executed.

After receipt of defendants’ telephonic bid, plaintiffs prepared a contract which was signed by Jack Charlesworth [654]*654on, October 15, 1947. The terms, insofar as pertinent here, are as follows:

“Whereas the undersigned painting contractor has examined the plans, specifications and drawing of that certain bridge being erected at Green River, Utah, by J. B. Roland and T. C. Roland, as general contractors; and
“Whereas, party of the first part, as sub-contractor has undertaken the painting of said bridge and the undersigned painting contractor has tendered his bid in the amount of $500.00 for the application of two coats of aluminum paint thereon;
“■Now, therefore, in consideration of the premises and the covenants herein contained, the undersigned painting contractor agrees to apply two coats of aluminum paint to said new bridge at Green River, Utah, in accordance with the plans, specifications and drawings thereon provided by the Utah State Road Commission, which said plans, specifications and drawings the undersigned painting contractor has examined and is familiar therewith; said paint shall be applied in the manner and at the times to be directed by the general contractor and the said general contractor shall furnish the paint to be applied thereon.
******
“In the event the work to be done by the painting contractor fails to comply with the said plans and specifications or is not done in a prompt, expeditious and good workmanlike manner thus requiring additional expenditures of labor or causing delays to the first party or the general contractor then the undersigned painting contractor shall promptly reimburse the first party for all expenditures of time and labor occasioned thereby; and in the event of any such failure on the part of the undersigned painting contractor it is agreed that they shall pay all costs, including a reasonable attorney’s fee for collection thereof.”

The erection of the bridge was completed before Christmas in 1947, and some time in February, 1948, plaintiffs advised defendants that the bridge was ready for painting and that defendants were to proceed with their contract. On one occasion during February or March, 1948, defendants sent a painting crew to the site to paint the bridge. Again in the latter part of March a crew accompanied by Jack Charlesworth went to the site of the bridge to commence the painting. On both occasions they failed to do any painting and on March 28, 1948, Jack Charlesworth advised plaintiffs that defendants would not perform the [655]*655contract. On April 2, 1948, defendants sent a letter to plaintiffs repudiating the contract. They did not assert in the letter the principal defense relied on in this court, but gave as their reasons for refusing to comply with the contract that the agreement was never approved or executed by plaintiffs; that Larsen was not authorized to make representations in behalf of plaintiffs; that Jack Charlesworth was not authorized to sign in behalf of defendants ; that Larsen fraudulently misrepresented the facts regarding the size of the bridge, in stating that the scaffolding used in the erection of the bridge would be available for the painters, in representing that the bridge could be painted before the roadway was laid across it, and in promising that the bridge would be cleaned prior to the painting; and that plaintiffs had breached the contract in that they had failed and refused to furnish paint for the bridge.

After defendants’ repudiation, plaintiffs were unsuccessful in obtaining another contractor to paint the bridge so that the work was performed by a crew employed by them at a cost of $2,196.45, resulting in a loss of $1,696.45.

In the trial court, defendants advanced several affirmative defenses, mostly involving their contentions that Larsen was guilty of fraud which induced them to execute the contract. In addition, they filed a cross-complaint in which they named Larsen as cross-defendant. They alleged in the cross-complaint that misrepresentations had been made by him as to the size and weight of the bridge, that he had assured them that the contract as prepared expressed the oral agreement of the parties, and that, relying on his statements, the contract was signed by Jack Charlesworth without checking the plans. The court found against the defendants on their cross-complaint, but no appeal has been taken from that judgment and the evidence sustains the trial court’s finding that Larsen was not guilty of fraudulent conduct. These two items [656]*656can, therefore, be eliminated from further discussions.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Grahn v. Gregory
800 P.2d 320 (Court of Appeals of Utah, 1990)
B & a Associates v. L.A. Young Sons Construction Co.
796 P.2d 692 (Utah Supreme Court, 1990)
Guardian State Bank v. Stangl
778 P.2d 1 (Utah Supreme Court, 1989)
John Call Engineering, Inc. v. Manti City Corp.
743 P.2d 1205 (Utah Supreme Court, 1987)
Briggs v. Liddell
699 P.2d 770 (Utah Supreme Court, 1985)
Davis v. Mulholland
475 P.2d 834 (Utah Supreme Court, 1970)
State Ex Rel. Road Commission v. Union Construction Co.
339 P.2d 421 (Utah Supreme Court, 1959)
Reese v. Harper
329 P.2d 410 (Utah Supreme Court, 1958)
Ashworth v. Charlesworth
231 P.2d 724 (Utah Supreme Court, 1951)

Cite This Page — Counsel Stack

Bluebook (online)
231 P.2d 724, 119 Utah 650, 1951 Utah LEXIS 163, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ashworth-v-charlesworth-utah-1951.