B & a Associates v. L.A. Young Sons Construction Co.

796 P.2d 692, 139 Utah Adv. Rep. 10, 1990 Utah LEXIS 60, 1990 WL 124145
CourtUtah Supreme Court
DecidedJuly 23, 1990
Docket880239
StatusPublished
Cited by3 cases

This text of 796 P.2d 692 (B & a Associates v. L.A. Young Sons Construction Co.) is published on Counsel Stack Legal Research, covering Utah Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
B & a Associates v. L.A. Young Sons Construction Co., 796 P.2d 692, 139 Utah Adv. Rep. 10, 1990 Utah LEXIS 60, 1990 WL 124145 (Utah 1990).

Opinion

HALL, Chief Justice:

This case involves only Reliance Insurance Company (Reliance) as appellee and Utah Department of Transportation (UDOT) as appellant and is on appeal from a grant of a partial summary judgment in favor of Reliance in the Third Judicial District Court, Salt Lake County. The trial court held that no genuine issues of material fact existed with respect to a supplemental agreement between Reliance’s assignor, L.A. Young Sons Construction Company (Young), and UDOT compensating Young for fixed costs and overhead incurred by a 63.9 percent underrun on a UDOT project.

FACTS

On April 23, 1985, UDOT began accepting bids on a project to reconstruct a portion of Interstate 80. near Black Rock in Tooele County, Utah (the project). On May 13, 1985, Young was awarded the bid and contracted with UDOT to perform all construction work on the project for the approximate sum of $9,940,893.25.

Reliance furnished both payment and performance bonds for Young on the project. In addition, Young entered into continuing agreements of indemnity with Reliance pursuant to which Reliance is assigned any claims or causes of action Young may have in connection with the project.

Included in Young’s bid was a cost estimate for the placement of 226,200 tons of “riprap.” Young initially subcontracted the riprap work to B & A, which bid $5 per ton to Young. Young in turn bid only $4 per ton on its master bid schedule. The bid was based on a quantity estimate supplied by UDOT engineers and relied upon by all contractors who submitted bids.

Also included in Young’s bid was' a cost estimate for “clearing and grubbing” that was well in excess of UDOT’s estimate. While UDOT estimated $5,000 for clearing and grubbing and the average bid submitted by contractors was $38,052, Young’s bid was $832,420. This inflated bid was attributed to “unbalanced bidding,” a practice whereby contractors attempt to mask or hide their cost structure from competitors by overbidding some aspects of the project and underbidding others. Unbalanced bidding is also utilized to attempt to meet increased funding needs at particular intervals in the project.

Young was awarded the bid under condition that Young accept payment for the clearing and grubbing in stages. After Young accepted this condition, UDOT sought approval to award the unbalanced contract from the Federal Highway Administration (FHWA), which administered the federal highway funds used in the project. FHWA raised some concerns about the quantity of riprap specified by the UDOT engineers, but after receiving verification from UDOT’s district director, FHWA concurred in the bid award to Young as proposed by UDOT.

*694 As the project continued, it became obvious that the quantity of riprap was grossly overestimated and that instead of the initial 226,200 tons, only 81,724.8 tons were necessary to complete the project. The actual amount of 81,724.8 represents a 63.9 percent underrun.

Section 104.02 of UDOT’s standard specifications provides for an adjustment in compensation to the contractor when there is an underrun in excess of 25 percent. The purpose of this section is to compensate contractors for overhead and other fixed costs associated with an underrun. Pursuant to section 104.02, Young submitted a claim for the riprap work.

On August 29, 1986, UDOT’s project engineer, John Nye, determined that Young was entitled to a supplemental agreement to compensate for the underrun of riprap. “Supplemental Agreement # 11” (S.A. # 11) was prepared and submitted for approval to compensate Young in the amount of $274,104.98 based upon payroll, equipment, and actual costs associated with the riprap item. S.A. # 11 was signed by all necessary state parties to the agreement but was not delivered to Young.

Supplemental agreements on federal aid projects require concurrence by FHWA as a precondition to securing federal aid funding. When S.A. #11 was submitted for concurrence, FHWA notified Bert Taylor, UDOT’s chief construction officer, that it would not participate in the cost of S.A. # 11 because of the previous concerns it had expressed regarding the riprap quantity and UDOT’s apparent negligence in estimation.

Following FHWA’s refusal to participate in S.A. # 11, Taylor realized the possible connection between the inflated bid for “clearing and grubbing” and the underrun in the riprap. Taylor notified John Nye that S.A. # 11 would not be implemented; hence, it was never delivered to Young.

John Nye subsequently drafted S.A. # 14, which was essentially the same as S.A. # 11, except that it credited $226,200 against the amount due under S.A. # 11. The $226,200 figure was reached because the original quantity estimate for riprap was 226,200 tons and Young underbid its subcontractor’s bid by $1 per ton. UDOT perceived that at least part of the unbalancing of the clearing and grubbing bid item accounted for the fact that Young was able to bid $4 per ton on the riprap even though its subcontractor, B & A, had submitted a bid for $5 per ton. The result of S.A. # 14 was to supplement Young in the amount of $47,907.08, instead of $274,-104.98 under S.A. # 11. S.A. # 14 was never implemented because Taylor believed Young had already been overpaid.

Young brought an action against UDOT to recover the amount it asserted was due under the UDOT specifications for under-runs and to enforce S.A. # 11. UDOT claimed that it was justified in its offset of the underrun because of the perceived overpayment for clearing and grubbing and argued for equitable relief because of the unbalanced bid. In addition, UDOT asserted the defense of unilateral mistake in that when Mr. Taylor realized his mistake in signing S.A. # 11 before he recognized the connection in the unbalanced bidding, he immediately rescinded S.A. # 11. The trial court granted summary judgment to Reliance, which is the assignee of Young, and ordered that S.A. # 11 be enforced.

Summary judgment is granted when no genuine issue of material fact exists and the moving party is entitled to judgment as a matter of law. 1 Where there is a material issue of fact, however, summary judgment is inappropriate. 2

I. VALIDITY OF S.A. # 11

UDOT first claims that an issue of fact exists with regard to whether S.A. # 11 is a valid and binding contract. It is undisputed that all of the necessary UDOT signatures were affixed to S.A. # 11 and that the document itself was never physi *695 cally delivered to Young. It is also undisputed that S.A. # 11 states: “Signing this agreement settles any and all claims on Contract Item No. 9, Mechanically Placed /Rip Rap.”

In Aspen Acres Association v. Seven Associates, Inc., 3 a contract for transfer of water rights and a water system was in dispute. In reversing the trial court’s determination that the contract was binding, we held:

[T]he mere affixing of the signatures to the document did not conclusively prove that there was a binding contract.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Mostrong v. Jackson
866 P.2d 573 (Court of Appeals of Utah, 1993)
Grahn v. Gregory
800 P.2d 320 (Court of Appeals of Utah, 1990)

Cite This Page — Counsel Stack

Bluebook (online)
796 P.2d 692, 139 Utah Adv. Rep. 10, 1990 Utah LEXIS 60, 1990 WL 124145, Counsel Stack Legal Research, https://law.counselstack.com/opinion/b-a-associates-v-la-young-sons-construction-co-utah-1990.