Artco-Bell Corp. v. City of Temple

616 S.W.2d 190, 24 Tex. Sup. Ct. J. 416, 1981 Tex. LEXIS 319
CourtTexas Supreme Court
DecidedMay 20, 1981
DocketB-9810
StatusPublished
Cited by30 cases

This text of 616 S.W.2d 190 (Artco-Bell Corp. v. City of Temple) is published on Counsel Stack Legal Research, covering Texas Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Artco-Bell Corp. v. City of Temple, 616 S.W.2d 190, 24 Tex. Sup. Ct. J. 416, 1981 Tex. LEXIS 319 (Tex. 1981).

Opinion

WALLACE, Justice.

This is an appeal from a summary judgment. Plaintiff in the trial court was Art-co-Bell Corporation (Artco-Bell) and defendant was the City of Temple, Texas (City). The trial court granted City’s motion for summary judgment which alleged that Artco-Bell’s notice of claim to the City was not “duly verified” as required by the City Charter and that the City was not given written notice of the alleged dangerous condition giving rise to the loss in question ten days prior to the accident in question. The court of civil appeals affirmed. 603 S.W.2d 384. We reverse the judgment of the court of civil appeals and remand the cause to the district court for trial.

Artco-Bell’s truck was damaged on April 16, 1979, in a collision with a low-hanging tree limb which extended over a city street. Artco-Bell mailed an unverified notice of claim to the City on April 24. The City Attorney responded by letter stating that the City was not liable and that “upon receipt of the claim in proper form I will place your request before the City Commission for its consideration.” Enclosed with the letter was a copy of Article III, Section 13, of the City Charter which set out the requirements of a notice of claim. On June 12, Artco-Bell mailed a second notice letter which complied with all requirements of the City Charter except that it was not verified. Artco-Bell filed suit on July 11, and City answer on July 20, setting out for the first time its contention that the notice of claim was insufficient because it was not verified and that the City had not been given ten days’ notice of the alleged dangerous condition of the street. Artco-Bell contends that there exists a fact issue as to whether the City waived verification of the notice; whether the City is estopped from denying the sufficiency of the notice; whether Art-co-Bell gave the City sufficient notice of the claim; that Article III, Section 13 of the City Charter is unconstitutional in that it violates Artco-Bell’s right of due process; that the court of civil appeals erred in not ruling on the constitutionality of the ten days’ notice requirement contained in Article III, Section 12 of the City Charter; and the court of civil appeals erred in not ruling on whether Article III, Section 12 of the City Charter applies to property damage. 1

We will first discuss Artco-Bell’s contention that it substantially complied with the required notice of claim. In order to fully discuss this point it is necessary that we first refer to the statutory authority for the City’s notice requirements. Temple is a home-rule city and its powers are derived from Article 1175, Vernon’s Texas Statutes

*192 Annotated. 2 Paragraph 6 of Article 1175 is the source of the City's authority to place limitations upon actions against the City for damages arising from a proprietary wrong committed by the City. McCrary v. City of Odessa, 482 S.W.2d 151, 153 (Tex.1972). See Hughes, “Notice of Claim” as a Condition Precedent to Suit: Is the Proprietary-Governmental Distinction Important? 31 Baylor L.Rev. 427 (1979). That Article states:

Article 1175.
Cities adopting the charter or amendment hereunder shall have full power of local self-government, and among the other powers that may be exercised by any such city the following are hereby enumerated for greater certainty:
6. To provide for the exemption from liability on account of any claim for any damages to any person or property, or to fix such rules and regulations governing the city’s liability as may be deemed advisable.

The purpose of the notice requirement is to provide the municipality with an opportunity to investigate an accident while facts are fresh and conditions remain substantially the same, thereby enabling the City to guard against unfounded claims and to settle claims and to prepare for trial. City of Austin v. Selter, 415 S.W.2d 489 (Tex.Civ.App.—Austin 1967, writ ref’d n. r. e.); City of Houston v. Holden, 336 S.W.2d 193 (Tex.Civ.App.—Eastland 1960, writ ref’d n. r. e.). It has been stated that notice provisions are to be regarded as in aid of the management and control of the City’s finances and property. City of El Paso v. Nicholson, 361 S.W.2d 415, 417 (Tex.Civ.App.—El Paso 1962, writ ref’d n. r. e.). The apparent purpose of the verification requirement is to afford the City protection against spurious and unfounded claims. See City of San Antonio v. Ramundo, 411 S.W.2d 428, 430 (Tex.Civ.App.—San Antonio 1966), writ ref’d n. r. e., 416 S.W.2d 395 (Tex.1967); City of Waco v. Landingham, 158 S.W.2d 79, 80 (Tex.Civ.App.—Waco 1940, writ ref’d).

Based upon the above statute the City adopted its charter and particularly Article III, Section 13 of its charter which states:

ARTICLE III
Section 13. LIMITATION ON LIABILITY FOR DAMAGES: Before the City of Temple shall be liable for damages for personal injuries of any kind, or for injuries to or destruction of property of any kind, the person injured, or the owner of the property injured or destroyed, or someone in his behalf, shall give the City Manager notice in writing of such injury or destruction, duly verified, within sixty (60) days after the same has been sustained, stating in such written notice when, where and how the injury or destruction occurred, and the apparent extent thereof, the amount of damage sustained, the amount for which claimant will settle, the actual residence of the claimant by street and number at the time the claim is presented, and the actual residence of such claimant for six (6) months immediately preceding the occurrence of such injuries or destruction, and the names and addresses of the witnesses upon whom he relies to establish his claim, and, further, that suit be filed thereon within six (6) months from the date such injuries were received or destruction suffered; ...

Free access — add to your briefcase to read the full text and ask questions with AI

Related

City of San Antonio v. Tenorio ex rel. Tenorio
543 S.W.3d 772 (Texas Supreme Court, 2018)
City of Austin v. Liberty Mutual Insurance
431 S.W.3d 817 (Court of Appeals of Texas, 2014)
Roccaforte v. Jefferson County
341 S.W.3d 919 (Texas Supreme Court, 2011)
Colquitt v. Brazoria County
324 S.W.3d 539 (Texas Supreme Court, 2010)
Ballesteros v. Nueces County
286 S.W.3d 566 (Court of Appeals of Texas, 2009)
Dallas County v. Coskey
247 S.W.3d 753 (Court of Appeals of Texas, 2008)
Moreno v. City of El Paso
71 S.W.3d 898 (Court of Appeals of Texas, 2002)
Reuben T. Press v. Willie Elizabeth Press
Court of Appeals of Texas, 1998
Borne v. City of Garland
718 S.W.2d 22 (Court of Appeals of Texas, 1986)
Schautteet v. City of San Antonio
702 S.W.2d 680 (Court of Appeals of Texas, 1986)
Fitts v. City of Beaumont
688 S.W.2d 182 (Court of Appeals of Texas, 1985)
County of El Paso v. El Paso County Sheriffs' Deputies Ass'n
678 S.W.2d 122 (Court of Appeals of Texas, 1984)
Castro v. Harris County
663 S.W.2d 502 (Court of Appeals of Texas, 1983)
Lubbock Mortgage & Investment Co. v. Thomas
626 S.W.2d 611 (Court of Appeals of Texas, 1981)
City of Houston v. Torres
621 S.W.2d 588 (Texas Supreme Court, 1981)

Cite This Page — Counsel Stack

Bluebook (online)
616 S.W.2d 190, 24 Tex. Sup. Ct. J. 416, 1981 Tex. LEXIS 319, Counsel Stack Legal Research, https://law.counselstack.com/opinion/artco-bell-corp-v-city-of-temple-tex-1981.