Arrow Concrete Co. v. Sheppard

645 N.E.2d 1310, 96 Ohio App. 3d 747, 1994 Ohio App. LEXIS 4121
CourtOhio Court of Appeals
DecidedSeptember 8, 1994
DocketNo. 93CA29.
StatusPublished
Cited by13 cases

This text of 645 N.E.2d 1310 (Arrow Concrete Co. v. Sheppard) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Arrow Concrete Co. v. Sheppard, 645 N.E.2d 1310, 96 Ohio App. 3d 747, 1994 Ohio App. LEXIS 4121 (Ohio Ct. App. 1994).

Opinions

Harsha, Presiding Judge.

Plaintiffs, Arrow Concrete Company and Arrow Industries Corporation (“Arrow”), appeal the trial court’s decision awarding damages to defendant Jason Sheppard for injury caused to his building. Arrow alleges the following assignments of error:

“I. Whether the trial court erred by using damages based upon contract in a tort action.

*749 “II. Whether the award of damages in the amount of $17,464.00 was excessive where testimony indicated Defendant had incurred actual damages in a lesser amount.

“III. Whether the trial court erred in bifurcating the issue of liability and damages where there was no finding by the trial court that the two issues were totally unrelated and the Plaintiffs case was prejudiced.”

This appeal arises from the following facts. On May 15, 1991, appellee Jason H. Sheppard ordered concrete from Arrow for a building he was constructing. While delivering the concrete, the agent for Arrow negligently backed into the partially constructed building, causing various damage to the structure. The parties failed to settle their dispute, and Arrow eventually filed suit to recover $2,171.08 for the unpaid delivery of the concrete. Sheppard counterclaimed against Arrow, alleging $23,835 in damages to his building. 1

On November 15,1992, a trial was held on the issue of liability only. The trial court bifurcated the hearing, with no objection from either party, finding it would be more expedient to decide first whether Arrow had caused any damage to the structure, and then decide later the amount of appropriate compensation. On September 18, 1992, a journal entry was filed finding Arrow had caused damage to the building, and further ordering a structural engineer to view the building before taking testimony on damages.

The hearing regarding damages was held before a different judge on October 8, 1993. The trial court vacated the previous journal entry to the extent that it required a structural engineer to view the building, and simply heard testimony on the issue of damages. The trial judge found that Arrow had caused $17,464 worth of damages to Sheppard’s building, and then offset that amount by the $2,171.08 Sheppard owed Arrow for the concrete. Arrow now appeals this award.

*750 Arrow’s first two assignments of error challenge the court’s findings regarding damages. Damage awards will not be overturned if supported by some competent, credible evidence. See Oak Hill Invest. Co. v. Jablonski (1992), 78 Ohio App.3d 643, 649-650, 605 N.E.2d 998, 1002, citing Seasons Coal Co. v. Cleveland (1984), 10 Ohio St.3d 77, 10 OBR 408, 461 N.E.2d 1273; Baum v. Augenstein (1983), 10 Ohio App.3d 106, 10 OBR 129, 460 N.E.2d 701.

Further, the measure of damages generally awarded in cases involving injury to real property has been set forth by the Ohio Supreme Court:

“[T]he measure of damages is the reasonable cost of restoration, plus the reasonable value of the' loss of the use of the property between the time of the injury and the restoration, unless such cost of restoration exceeds the difference in the market value of the property as a whole before and after the injury, in which case the difference in the market value before and after the injury becomes the measure.” Ohio Collieries Co. v. Cocke (1923), 107 Ohio St. 238, 140 N.E. 356, paragraph five of the syllabus.

Consequently, Ohio courts have recognized that in cases such as this, in which the party has been able to repair injury to a building, the proper measure of damages will usually be the reasonable costs necessary to restore the structure. See, e.g., Platner v. Herwald (1984), 20 Ohio App.3d 341, 20 OBR 445, 486 N.E.2d 202; Adcock v. Rollins Protective Serv. Co. (1981), 1 Ohio App.3d 160,1 OBR 471, 440 N.E.2d 548; Florea v. Nationwide Mut. Ins. Co. (Jan. 28, 1983), Montgomery App. No. 7908, unreported, 1983 WL 5030. We must now determine whether the trial judge’s award was in accordance with the law and supported by the evidence.

The trial judge found with regard to damages as follows:

“1. First, the repair of the truss and the resulting concrete damage. The Court finds that the testimony supports this claim. The architect’s testimony indicated that this was the only method to make the repair from this damage. Further, Plaintiffs’ witness confirms this. Thus, the Court finds this item of damage in the amount of $12,464.00.

“2. Secondly, the building needed to be brought into square. The Court finds for the Defendant in the amount of $5,000.00. This figure includes the concrete block that needed to be removed and replaced.

“3. The third item of damage is construction delay. The Court finds that this claim is not meritorious. In any contract the Defendant has an obligation of mitigating damage. The court does not find from the evidence in this case that the Defendant was delayed in this matter by Plaintiffs.

*751 “Thus, the Court finds that the Defendant is entitled to the sum of $17,464.00 as to damage in this case. The parties agreed that the Plaintiff was entitled to a setoff of $2,171.08 and the lien is to be canceled. The amount of judgment the Defendant is entitled to is $15,292.92.”

Appellants’ first assignment of error claims that the court used the wrong measure of damages because the court, at one point in the judgment entry, referred to the action in terms of breach of contract rather than negligence. However, it is obvious that the court attempted to give the appellee the reasonable costs to repair the damage done to his building. As a result, we find no legal error in the measure of damages used by the trial court, and overrule appellants’ first assignment of error.

Appellants’ second assignment of error claims that the trial court overcompensated appellee based on the evidence produced at trial. In support of this assertion, appellants point to the fact that appellee testified that he had incurred only $10,000 to $11,000 in out-of-pocket expenses. Appellee also admitted that for those repairs he performed himself, he measured his damages by multiplying the hours he worked by $60, the amount he would have been paid by a third person for similar labor. However, although appellee charged $60 an hour when he did such repairs for others, he testified that when he did his own repairs, he only paid one or two employees $5 to $10 per hour. 2

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Estie Invest. Co. v. Braff
2018 Ohio 4378 (Ohio Court of Appeals, 2018)
Spinner v. Barger
2017 Ohio 1489 (Ohio Court of Appeals, 2017)
Short v. Greenfield Meadows Assoc., 07ca14 (6-24-2008)
2008 Ohio 3311 (Ohio Court of Appeals, 2008)
Whitestone Co. v. Stittsworth, Unpublished Decision (1-23-2007)
2007 Ohio 233 (Ohio Court of Appeals, 2007)
Prawdzik v. II Enterprises, Inc., Unpublished Decision (6-24-2004)
2004 Ohio 3318 (Ohio Court of Appeals, 2004)
Curtis v. Vazquez, Unpublished Decision (11-21-2003)
2003 Ohio 6224 (Ohio Court of Appeals, 2003)
Dawn Court Associates v. Cristia
761 N.E.2d 705 (Medina County Court of Common Pleas, 2001)
Mapco Express, Inc. v. Faulk
24 P.3d 531 (Alaska Supreme Court, 2001)

Cite This Page — Counsel Stack

Bluebook (online)
645 N.E.2d 1310, 96 Ohio App. 3d 747, 1994 Ohio App. LEXIS 4121, Counsel Stack Legal Research, https://law.counselstack.com/opinion/arrow-concrete-co-v-sheppard-ohioctapp-1994.