Armand v. Territorial Construction, Inc

322 N.W.2d 924, 414 Mich. 21
CourtMichigan Supreme Court
DecidedAugust 23, 1982
DocketDocket 63499
StatusPublished
Cited by4 cases

This text of 322 N.W.2d 924 (Armand v. Territorial Construction, Inc) is published on Counsel Stack Legal Research, covering Michigan Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Armand v. Territorial Construction, Inc, 322 N.W.2d 924, 414 Mich. 21 (Mich. 1982).

Opinion

Per Curiam.

In Camelot Excavating Co, Inc v St Paul Fire & Marine Ins Co, 410 Mich 118; 301 NW2d 275 (1981), we upheld the enforceability against a subcontractor of a contractual one-year period of limitation on suit in a labor and materials payment bond. In the instant case, we are asked to decide whether a provision in such a bond which prohibits a subcontractor from suing for 90 days after having last furnished labor or materials tolls the limitation period.

We hold that it does not.

I

In this case, Territorial Construction, Inc., was the general contractor on a development project in Independence Township, Oakland County, owned by John C. Helveston. To protect Helveston against mechanics’ lien claims, Territorial obtained a labor and materials payment bond from Sentry Insurance. The bond named Territorial as principal and Sentry as surety, and contained the following pertinent provisions:

"2. The above-named Principal and Surety hereby jointly and severally agree with the Owner that every claimant as herein defined, who has not been paid in full before the expiration of a period of ninety (90) days *23 after the date on which the last of such claimant’s work for labor was done or performed, or materials were furnished by such claimant, may sue on this bond for use of such claimant, prosecute the suit to final judgment for such sum or sums as may be justly due claimant, and have execution thereon. The Owner shall not be liable for the payment of any costs or expenses of any such suit.
"3. No suit or action shall be commenced hereunder by any claimant:
"(b) After the expiration of one (1) year following the date on which Principal ceased work on said Contract, it being understood, however, that if any limitation embodied in this bond is prohibited by any law controlling the construction hereof such limitation shall be deemed to be amended so as to be equal to the minimum period of limitation permitted by such law.”

W. R. Armand, doing business as Armand Drilling & Dewatering Co., was employed by Territorial to perform dewatering services on the project. On November 5, 1974, both Armand and Territorial ceased work. On November 18, 1975, Armand filed the instant suit, claiming nonpayment for its services and seeking recovery on the labor and materials payment bond.

Sentry’s motion for accelerated judgment on the basis of the expiration of the contractual one-year limitation period was granted by the trial court. The Court of Appeals reversed, holding that the provision in the bond which prohibited the claimant from suing for a 90-day period after having last furnished labor or materials tolled the limitation period. 90 Mich App 491; 282 NW2d 365 (1979).

Sentry has applied to this Court for leave to appeal.

*24 II

In reversing, the Court of Appeals relied on our decision in The Tom Thomas Organization, Inc v Reliance Ins Co, 396 Mich 588; 242 NW2d 396 (1976). In that case, we construed facially similar provisions in an inland marine insurance policy. A limitation provision in the policy gave the insured 12 months in which to bring suit. 1 Other provisions gave the insured 90 days in which to file a proof of loss, and gave the insurer an indefinite period of time in which to accept the proof of loss and pay the claim. 2 We found that a conflict existed between the limitation provision and the proof-of-loss and payment-of-claims provisions because the limitation provision purportedly was intended to give the insured a full 12 months in which to bring suit and the proof-of-loss and payment-of-claims provisions had the effect of substantially shortening that period. To resolve this incongruity, we adopted the reconciliation approach of Peloso v Hartford Fire Ins Co, 56 NJ 514; 267 A2d 498 (1970), and held that the limitation period should be tolled "from the time the insured gives notice until the insurer formally denies liability”. 396 Mich 597.

*25 More recently, in In re Certified Question, Ford Motor Co v Lumbermens Mutual Casualty Co, 413 Mich 22; 319 NW2d 320 (1982), we applied the Thomas-Peloso reconciliation analysis to substantially identical provisions in the statutory fire insurance policy. 3 Although statutory rather than contractual, we concluded that the intent of the limitation provisión was the same: to give the insured a full 12 months in which to institute suit. Accordingly, we held that the same tolling occurred from the time the insured gives notice until the insurer finally denies liability.

The Court of Appeals in this case found the provisions in the bond to be analogous to those in Thomas and concluded that they should be similarly construed.

We hold, however, that this is not another conflicting provisions case and that the applicable analysis is found in our decision in Camelot Excavating Co, Inc v St Paul Fire & Marine Ins Co, supra. In Camelot, we upheld a one-year period of limitation on suit in a labor and materials bond as applied to a subcontractor. We held that because the subcontractor was only an incidental third-party beneficiary to the private bond contract, the limitation period should be held valid and enforce *26 able as to the subcontractor so long as it provided a reasonable amount of time in which the subcontractor could have protected its contractual rights. Despite the subcontractor’s claim in that case that it was unaware of the bond contract until after the limitation period had expired, we held that the one-year period was a reasonable amount of time in which the subcontractor could have discovered and protected its rights under the bond.

Although this case might at first glance appear to be another conflicting provisions case like Thomas and Lumbermens, it is not. In both of those cases, we found that the limitation provision was intended to give the insured a full year in which to file suit. We found this intent in Thomas because the case involved a two-party insurance contract written by the insurer purportedly for the benefit of the insured. In Lumbermens, we found a similar intent in a statutory policy because the principal purpose of the Insurance Code is to protect policyholders. 413 Mich 38. The conflict in both cases arose because the proof-of-loss and payment-of-claims provisions had the effect of substantially shortening the period available to the insured in which to file suit. In the instant case, we discern no intent in the limitation provision of the bond to give the subcontractor a full year in which to file suit. Unlike the insured in Thomas and Lumbermens, the subcontractor is merely an incidental third-party beneficiary of a bond contract written for the benefit of others.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Rory v. Continental Insurance
703 N.W.2d 23 (Michigan Supreme Court, 2005)

Cite This Page — Counsel Stack

Bluebook (online)
322 N.W.2d 924, 414 Mich. 21, Counsel Stack Legal Research, https://law.counselstack.com/opinion/armand-v-territorial-construction-inc-mich-1982.