Arkansas Power & Light Company v. Federal Power Commission

517 F.2d 1223
CourtCourt of Appeals for the D.C. Circuit
DecidedAugust 21, 1975
Docket73-1637
StatusPublished

This text of 517 F.2d 1223 (Arkansas Power & Light Company v. Federal Power Commission) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Arkansas Power & Light Company v. Federal Power Commission, 517 F.2d 1223 (D.C. Cir. 1975).

Opinion

517 F.2d 1223

170 U.S.App.D.C. 393, 11 P.U.R.4th 199

ARKANSAS POWER & LIGHT COMPANY, General Motors Corporation
and Arkansas Louisiana Gas Company, Petitioners,
v.
FEDERAL POWER COMMISSION, Respondent, Reynolds Metals
Company, Arkansas Louisiana Gas Company, General Motors
Corporation, Cities Service Gas Company, Arkansas Power &
Light Company, Mississippi River Transmission Corporation,
Laclede Gas Company, Intervenors.

Nos. 73-1637, 73-1655, 73-1717 and 73-1800.

United States Court of Appeals,
District of Columbia Circuit.

Argued Dec. 13, 1974.
Decided Aug. 21, 1975.

Peyton G. Bowman, III, Washington, D. C., with whom Richard M. Merriman, Washington, D. C., was on the brief, for petitioner in Nos. 73-1637 and 73-1717.

Edward J. Grenier, Jr., New York City, with whom Richard P. Noland and Richard J. Pierce, Jr., Washington, D. C., were on the brief, for petitioner in No. 73-1655 and intervenor General Motors Corp. Ronald L. Winkler, Washington, D. C., also entered an appearance for petitioner in No. 73-1655.

Reuben Goldberg, Washington, D. C., with whom David C. Hjelmfelt and Sherman S. Poland, Washington, D. C., were on the brief, for petitioner in No. 73-1800 and intervenor Arkansas Louisiana Gas Co.

John H. Burnes, Jr., Atty., F. P. C., with whom Leo E. Forquer, Gen. Counsel, and George W. McHenry, Jr., Sol., F. P. C., were on the brief, for respondent.

William W. Bedwell, Washington, D. C., and John J. Mullally, Brooklyn, N. Y., were on the brief, for intervenor Mississippi River Transmission Corp.

Philip R. Ehrenkranz, Washington, D. C., entered an appearance for intervenor Reynolds Metals Co.

Daniel R. Hopkins, Oklahoma City, Okl., and Harry S. Littman, Washington, D. C., entered appearances for intervenor Cities Service Gas Co.

J. David Mann, Jr., Washington, D. C., entered an appearance for intervenor Laclede Gas Co.

Before MOORE,* Senior Circuit Judge for the Second Circuit, and MacKINNON and ROBB, Circuit Judges.

Opinion for the court filed by Senior Circuit Judge MOORE.

MOORE, Senior Circuit Judge:

This is a consolidated proceeding to review Opinion Nos. 643, 643-A and 643-B and accompanying orders of the Federal Power Commission.1 These opinions, issued pursuant to the Commission's authority under sections 42 and 53 of the Natural Gas Act to regulate plans for the curtailment of natural gas,4 dealt with a plan filed by the Arkansas Louisiana Gas Company. The opinions represent a portion of the Commission's efforts to cope with the apparently still-worsening5 natural gas shortage. Three companies have petitioned for review: Arkansas Louisiana Gas Company (Arkla), Arkansas Power & Light Company (AP&L), and General Motors Corporation (GM).6 Each of these parties, along with several other interested companies, has also intervened with respect to the petitions brought by the other petitioners.

Arkla is an integrated gas utility engaged in the production, transportation, distribution, and sale of natural gas. Its operations embrace six different states. Unlike most other natural gas pipeline companies, Arkla distributes the majority of its gas at retail, although a limited amount of pipeline sales are made to other gas companies for resale. In 1971, the FPC issued Order No. 431,7 a Statement of General Policy directing that gas pipeline companies take steps to provide as adequate service as supplies and capacities would permit, and, where curtailment of deliveries would be required because of inadequate supplies, to file a tariff sheet containing measures to deal with the shortage. In response to Order No. 431, Arkla filed a tariff setting forth its curtailment plan. The plan classified Arkla's sales of natural gas into five priority categories: Categories I, A, B, C, and D (listed in order of lowest to highest priority). Sales in Category I (sales subject to interruption at Arkla's sole discretion) had the lowest priority, and sales in Category D (sales to schools, churches, residences, hospitals, and other human needs customers) had the highest. Categories A, B, and C included different types of industrial customers categorized mainly according to the use made of the gas and the ability to utilize alternate fuels.8

By FPC orders the Arkla tariff sheets were temporarily suspended and their use deferred.9 Hearings on the Arkla plan commenced on July 13, 1971, and on October 13, 1971, the Administrative Law Judge held that Arkla had no immediately critical gas situation and cancelled the tariff sheet. However, in Opinion No. 643, issued on January 8, 1973, the FPC disagreed and reversed the Administrative Law Judge. The Commission found that curtailment was necessary, held that with some modifications Arkla's curtailment plan was just and reasonable, and prescribed a somewhat revised eight-priority curtailment plan, to become effective upon receipt and acceptance by the FPC of revised tariff sheets submitted by Arkla. Certain parties (including GM, which sought and received leave to intervene at this point in the proceedings) then filed petitions for rehearing, which were granted by the Commission for purposes of further consideration. On April 10, 1973, the Commission issued Opinion No. 643-A, which modified the curtailment priorities and adopted certain definitions to be employed in connection with the curtailment plan. Finally, in Opinion No. 643-B issued June 8, 1973, the FPC denied all further petitions for rehearing but did grant Arkla an extension of time to comply with the Order which had accompanied Opinion 643-A.10

The curtailment plan as finally prescribed11 by the FPC had the following nine priority-of-service categories:

(1) Residential, small commercial (less than 50 Mcf on a peak day).

(2) Large commercial requirements (50 Mcf or more on a peak day), firm industrial requirements for plant protection, feedstock and process needs, and pipeline customer storage injection requirements.

(3) All industrial requirements not specified in (2), (4), (5), (6), (7), (8), or (9).

(4) Firm industrial requirements for boiler fuel use at less than 3,000 Mcf per day, but more than 1,500 Mcf per day, where alternate fuel capabilities can meet such requirements.

(5) Firm industrial requirements for large volume (3,000 Mcf or more per day) boiler fuel use where alternate fuel capabilities can meet such requirements.

(7) Interruptible requirements of intermediate volumes (from 1,500 Mcf per day through 3,000 Mcf per day), when alternate fuel capabilities can meet such requirements.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hormel v. Helvering
312 U.S. 552 (Supreme Court, 1941)
United States v. Bankers Trust Co.
419 U.S. 883 (Supreme Court, 1974)

Cite This Page — Counsel Stack

Bluebook (online)
517 F.2d 1223, Counsel Stack Legal Research, https://law.counselstack.com/opinion/arkansas-power-light-company-v-federal-power-commission-cadc-1975.