Arizona Electric Power Cooperative, Inc. v. Federal Energy Regulatory Commission

631 F.2d 802, 203 U.S. App. D.C. 220, 1980 U.S. App. LEXIS 17330
CourtCourt of Appeals for the D.C. Circuit
DecidedMay 22, 1980
DocketNos. 75-1952, 77-1634, 77-1676, 79-1681, 77-1715, 77-1830, 78-1198 and 79-2087
StatusPublished
Cited by4 cases

This text of 631 F.2d 802 (Arizona Electric Power Cooperative, Inc. v. Federal Energy Regulatory Commission) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Arizona Electric Power Cooperative, Inc. v. Federal Energy Regulatory Commission, 631 F.2d 802, 203 U.S. App. D.C. 220, 1980 U.S. App. LEXIS 17330 (D.C. Cir. 1980).

Opinion

Opinion PER CURIAM

PER CURIAM:

In these consolidated appeals, we are called upon to review several orders of the Federal Energy Regulatory Commission (“the Commission”) issued in response to the continuing shortage of natural gas.1 The controversy arises out of the efforts of the Commission and the El Paso Natural Gas Company (“El Paso”) to assure adequate supplies of gas to east of California (“EOC”) customers who receive natural gas from El Paso. Petitioners Arizona Electric Power Cooperative, Inc. and the City of Willcox, Arizona (collectively “AEPCO”), Southern California Gas Company (“So Cal”), and Pacific Gas and Electric Company (“PG&E”) challenge the Commission’s orders on various substantive and procedural grounds. We find all but one of petitioners’ contentions moot, and therefore dismiss the petitions in Nos. 75-1952, 77-1634, 77-1676, and 77-1830. In the remaining case, No. 78-1198, we affirm the Commission.

I. BACKGROUND

El Paso is an interstate natural gas transmission company serving direct and distrib[224]*224utor customers in California and in five southwestern states east of California. The petitioners in this case are all El Paso customers. In 1971, the Commission ordered El Paso and other pipelines to establish curtailment plans in anticipation of impending natural gas shortages. In response, El Paso designed and eventually began operating under a plan which prioritized different end uses of gas into five categories.2 Priorities 1 and 2 (P-1 and P-2) — the highest priorities — consist of residential uses and commercial uses which cannot be supplied by resort to alternative fuels. Priorities 4 and 5 (P-4 and P-5) — the ’lowest priority uses — involve the use of natural gas as boiler fuel, a use for which substitute products are available. Priority 3 is defined residually as those end uses not included within Priorities 1, 2, 4, and 5.

Under the curtailment plan, El Paso’s customers report their different end use needs by priority to the pipeline each day. El Paso then fills all the P-1 needs, followed by P-2 needs, P-3 needs, and so on until all of its available gas supply for that day is exhausted. If its supplies run out before low priority customers have been fully serviced, those customers must resort to alternative fuels for that day.

While curtailment plans provide for the orderly distribution of gas during times of shortage, they are not alone a means of avoiding any shortage. Accordingly, in 1971 the Commission also ordered El Paso to develop a plan for husbanding gas in the summer, when it is in relatively low demand, for use in the winter by temperature sensitive high priority customers. In compliance with this request, El Paso successfully petitioned the Commission in 1973 for permission to reactivate the Rhodes storage field in New Mexico. The Commission’s order, which was unopposed, authorized El Paso to curtail its EOC P-5 customers so that it could inject up to 16 billion cubic feet (Bcf) of gas into the Rhodes field.

By May of 1974, El Paso became concerned that Rhodes storage would not be sufficient to assure adequate winter gas supplies for all of its EOC high priority customers. Since there were no other EOC storage facilities available, El Paso contacted its two California customers, petitioners PG&E and SoCal, and negotiated two separate agreements known as the “load equation” agreements. In the first of these contracts, El Paso agreed to increase PG&E’s summer deliveries with gas made available by curtailing EOC P-5 customers. PG&E, which had substantial unused storage capacity, would then store this extra gas throughout the winter. If the gas was needed to meet shortages in EOC high priority supplies it would be “returned” by diverting PG&E scheduled deliveries to the EOC market. PG&E would then draw from the stored gas to meet its needs.

El Paso’s agreement with SoCal called for “back-off” rights. Under this arrangement, SoCal agreed to accept reduced deliveries at any point during the winter when shortages of gas for EOC high priority customers would require curtailment. Any gas thus diverted from SoCal would later be repaid by curtailing El Paso’s lower priority EOC customers. During the interim, SoCal would draw on its substantial storage capacity for its requirements.

On May 13, 1974, El Paso applied to the Commission for temporary and permanent certificates authorizing the load equation agreements. The Commission granted a temporary certificate on June 21, 1974, authorizing load equation for the 1974-75 winter, but withholding permanent certification pending hearings.3 Pursuant to the temporary certificate, El Paso made advance sales to PG&E of approximately 13 [225]*225Bcf of gas. The following summer, in anticipation of more winter shortages, El Paso again sought temporary and permanent certificates, this time authorizing an extension of load equation for another two years. By order issued July 9, 1975, the Commission granted the temporary certificate, but once again declined to issue a permanent certificate without public hearings.4

Public hearings were then held before an administrative law judge, who, on June 7, 1976, issued an initial decision denying permanent certification.5 In all but one respect, the ALJ was favorable towards El Paso’s request. But the ALJ accepted AEPCO’s contention that there would have been no need for load equation but for an illegal act, viz., a misclassification of California customer storage injection needs in the high priority 2. (This misclassification is the subject of the court’s opinion in Arizona Electric Power Cooperative, Inc., et al. v. FERC [the “Storage Injection” cases], 203 U.S.App.D.C. 229, 631 F.2d 811 (D.C.Cir.1980).) Based on this finding of illegality, the ALJ recommended that El Paso be denied its permanent certificate.

On review, the full Commission reversed and ordered permanent certification with some modifications and conditions.6 In a nutshell, the Commission held that the cause of a shortage does not diminish the fact that a shortage exists. The public convenience and necessity according to the best available evidence, said the Commission, still required load equation, lest serious winter shortages necessitate curtailing EOC P-1 and P-2 customers.

The Commission did find, however, that the El Paso plan had a discriminatory feature. It required all of the storage gas to be secured by curtailing only EOC P-5 customers, not P-5 customers in both California and the EOC states. The Commission found this feature to constitute undue discrimination between pipeline customers, and ordered El Paso, as a condition to the permanent certificate, to reallocate deliveries between the California and EOC P-5 customers so that the California customers would contribute their pro rata share to the storage arrangements. El Paso was given substantial discretion in designing an appropriate payback plan.7

On August 19, 1977, El Paso’s proposed payback plan was submitted to the Commission. It was approved with modifications in Opinion 800-B, issued on December 30, 1977.8 The plan, as approved, called for the return to EOC P-5 customers of (1) all the gas predelivered to PG&E under load equation, and (2) the California pro rata share of the Rhodes storage and SoCal “backoff” gas.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Spencer v. National Labor Relations Board
548 F. Supp. 256 (District of Columbia, 1982)
Yusuf Asad Madyun v. James R. Thompson, Governor
657 F.2d 868 (Seventh Circuit, 1981)
Arizona Electric Power Cooperative, Inc. v. Federal Energy Regulatory Commission, Southern Union Gas Co., Southern California Gas Co., El Paso Natural Gas Co., Pacific Gas & Electric Co., People of the State of California and the Public Utilities Commission of the State of California, Intervenors. Arizona Electric Power Cooperative, Inc. And City of Willcox v. Federal Energy Regulatory Commission, Asarco, Inc., Southern Union Company, People of the State of California, General Motors Corporation, Pacific Gas & Electric Company, Tucson Gas & Electric Company, Southwest Gas Corporation, Southern California Gas Company, Arizona Public Service Company, San Diego Gas & Electric Company, El Paso Natural Gas Company, Southern California Edison Company, Intervenors. Southern California Gas Company v. Federal Energy Regulatory Commission, Southern Union Co., People of the State of California, Public Utilities Commission of the State of California, General Motors Corporation, Pacific Gas and Electric Co., Tucson Gas & Electric Co., Arizona Public Service Co., San Diego Gas & Electric Co., El Paso Natural Gas Co., Southern California Edison Co., Arizona Electric Power Coop., City of Willcox, Intervenors. Arizona Electric Power Cooperative, Inc. And the City of Willcox, Arizona,petitioners v. Federal Energy Regulatory Commission, Southern California Gas Company, Pacific Gas and Electric Company, El Paso Natural Gas Company, Intervenors. Southern Union Company v. Federal Energy Regulatory Commission, State of California, General Motors Corp., Pacific Gas and Electric Co., Tucson Gas and Electric Co., Southern California Gas Co., Arizona Public Service Co., San Diego Gas & Electric Co., El Paso Natural Gas Co., Arizona Electric Power Coop., Inc., Salt River Project Agricultural Improvement and Power District, Southwest Gas Corp., Southern California Edison Co., Intervenors. Pacific Gas and Electric Company v. Federal Energy Regulatory Commission, Arizona Electric Power Cooperative, Inc., San Diego Gas & Electric Co., the People of the State of California and the Public Utilities Commission of California, General Motors Corporation, El Paso Natural Gas Company, Southern Union Company, Southwest Gas Corp., Intervenors. Arizona Electric Power Cooperative, Inc. And the City of Willcox, Arizona v. Federal Energy Regulatory Commission, Southern California Gas Co., Southwest Gas Corp., Pacific Gas and Electric Co., Salt River Project Agricultural Improvement and Power District, El Paso Natural Gas Co., Southern Union Co., General Motors Corporation, Intervenors. Arizona Electric Power Cooperative, Inc. And the City of Willcox, Arizona v. Federal Energy Regulatory Commission, Pacific Gas and Electric Company, People of the State of California, Public Utilities Commission of the State of California, Arizona Public Service Company, Southern California Gas Company, El Paso Natural Gas Company, Intervenors
631 F.2d 802 (D.C. Circuit, 1980)

Cite This Page — Counsel Stack

Bluebook (online)
631 F.2d 802, 203 U.S. App. D.C. 220, 1980 U.S. App. LEXIS 17330, Counsel Stack Legal Research, https://law.counselstack.com/opinion/arizona-electric-power-cooperative-inc-v-federal-energy-regulatory-cadc-1980.